Aurea at Rashid Yachts & Marina by Emaar Properties in Rashid Yachts & Marina project rendering used for the September 2025 construction update showing a marina-facing terrace with residential buildings, yachts, and waterfront views in Dubai - Presented by Tohid Fetrat

Emaar Properties · Rashid Yachts & Marina · Construction Update

Aurea at Rashid Yachts & Marina Construction Update - September 2025

September 2025 Inspection Records Aurea at 0% as the First Reading at Rashid Yachts & Marina

No construction activity had started on the Aurea plot when the first RERA inspection, dated 23 September 2025, recorded 0 percent for the single Emaar tower.

Direct advisor access. Every message answered personally, never by a call center.

0%Construction Progress
23 September 2025Inspection Date
Q2 2030Expected Completion
4115DLD Project Number

Verified DLD Inspection Data

Aurea at Rashid Yachts & Marina Construction Snapshot

A 0% first reading, with no earlier inspection to compare against, opens the Aurea record at the very start of the enabling and foundations band: it documents a baseline taken before works, not a pace of progress.

Project Name

Aurea at Rashid Yachts & Marina

Project Number

4115

Project Status

Active

Construction Progress

0%

Inspection Date

23 September 2025

Construction Start

31 March 2026

Total Units

169 residential units

Total Built Area

18,298.19 sq m

Expected Completion

Q2 2030

Data source: RERA inspection conducted on 23 September 2025 for project 4115, tracked against DLD inspection records; the independent progress monitoring report lists the progress status as N/A and notes that no construction activity had started on site. The DLD record shows project registration on 26 September 2025 and a construction start date of 31 March 2026, both reported as recorded. Construction tracking against RERA inspection data runs across the full tohidfetrat.com project portfolio and is reviewed after every published cycle. Last updated: September 2026.

Want each new reading the day it publishes? Message me on WhatsApp and I will send it to you directly: one message per inspection cycle, nothing else. Message me on WhatsApp

First Inspection on Record

Aurea at Rashid Yachts & Marina Construction Progress Summary

The 23 September 2025 report describes Aurea as one residential building on plot 655: a G+P+13 tower holding 169 residential units, with retail on the ground floor. With no earlier reading and no works yet on site, every construction package of that tower sits in the Ahead column below, and the Completed column holds record milestones rather than building works.

Completed
  • RERA progress inspection of plot 655 on 23 September 2025
  • Trust account bank on record: Abu Dhabi Commercial Bank
  • Project registration in the DLD register on 26 September 2025
In Progress at 0%
  • No construction activity recorded on site at the inspection
  • RERA progress status listed as N/A in the inspection report
  • Construction start entered in the DLD record for 31 March 2026
Ahead of Handover
  • Enabling works and foundations for the single tower
  • Superstructure from ground and podium up to the thirteenth floor
  • Facade, MEP, and interior fit out of the 169 residential units and ground floor retail
  • Handover scheduled for Q2 2030
Next inspectionA reading above 0% can only follow the start of works; the DLD record lists 31 March 2026 as the construction start date, and this page updates with each published cycle.
Completion targetQ2 2030, with 30 June 2030 entered as the completion date in the DLD record, about four years and nine months after this inspection.
Remaining distance100 percentage points: the full construction programme lies ahead of the September 2025 reading.

Payment Linked Progress

What 0% Progress Means for Aurea Buyers

Aurea's 80/20 launch schedule of record puts its calendar-dated instalments first: 10% on booking plus the 4% DLD registration fee, then 10% each in Nov 2025, May 2026, and Nov 2026, before the first instalment the developer pairs with a construction stage (10% construction completion, Jul 2027). At a 0% reading, 40% of the price is therefore scheduled by date rather than by certified works, and four actions matter most.

Before Each Dated Instalment

Verify the escrow account

The inspection record names Abu Dhabi Commercial Bank as the trust account bank for project 4115, and every early payment should go only to the DLD regulated escrow account registered for that project. Aurea at Rashid Yachts & Marina escrow account verification is the step before any transfer; the lookup itself takes about two minutes against the official DLD project record.

Before Signing

Reread your SPA milestone schedule

Check how your sale and purchase agreement words each instalment from Jul 2027 to Jun 2030: whether it falls due on the stated date or on the certified construction stage, and which applies if the two diverge. Not sure how your instalments map to this reading? Send me your SPA schedule and I will map it against the certified milestones.

After Booking

Confirm your Oqood registration

Oqood is the DLD interim registration that records an off plan purchase against its project. With Aurea entered in the DLD register on 26 September 2025, ask for your Oqood certificate under project 4115 once the booking payment and the 4% DLD registration fee are processed.

Every Cycle

Watch for the first reading above 0%

The first measurable reading will show whether works began near the 31 March 2026 start date on record. Aurea at Rashid Yachts & Marina construction updates tracks each cycle from this baseline.

General framework, not legal advice: instalment triggers, notice periods, and fee obligations are set by your individual SPA and the DLD record, and both should be read directly.

Buying at 0%?

Entering before any works start trades certainty for runway: at this reading the tower exists only on paper, while the payment schedule stretches to Jun 2030 and holds the final 20% until 100% construction completion. Every payment goes to the DLD-registered escrow account for project 4115, released against certified construction progress.

Entering Now at 0%
  • No construction activity recorded at the 23 September 2025 inspection
  • Handover scheduled for Q2 2030, with the full build still ahead
  • 20% of the 80/20 plan held until 100% construction completion
Typical Late Stage Entry
  • Structure already visible in inspection readings before you commit
  • A shorter wait between purchase and handover
  • Less payment runway, with larger sums due close to completion
AED 2.31M ≈ USD 629KStarting Price
80/20 Plan20% Due Jun 2030
Q2 2030Expected Handover
Ask What Is Available at Aurea

Limited units available on the project page as of this update; availability shifts between cycles.

About the Development

Aurea at Rashid Yachts & Marina Project Details

Aurea waterfront residences exterior at Rashid Yachts & Marina in Mina Rashid, Dubai - Presented by Tohid Fetrat
Rashid Yachts & Marina · Emaar Properties

At the first inspection on 23 September 2025, no construction activity had started on the Aurea site, where Emaar Properties plans a single G+P+13 tower of 169 one, two, and three bedroom apartments. Starting prices: AED 2.31M ≈ USD 629K.

Entering at this stage gives the longest payment runway, with 2 bedroom apartments from AED 3.32M ≈ USD 904K and 3 bedroom from AED 4.89M ≈ USD 1.33M, against the widest gap to a handover scheduled for Q2 2030.

Aurea at Rashid Yachts & Marina Project Guide

Site Context This Cycle

Explore Aurea at Rashid Yachts & Marina Location on Dubai Map

Aurea sits on plot 655, recorded in the Madinat Dubai Almelaheyah area of the DLD record, inside the Rashid Yachts & Marina masterplan at Mina Rashid, where the site opens toward the port and marina with views back to the Downtown Dubai skyline. On a marina edge plot like this one, ground preparation and foundations are typically the first packages an inspection can measure, so that is where Aurea's next readings should register once works begin.

The setting is further along than the plot: Sheikh Rashid Road and Al Mina Road already carry access, the developer quotes about 15 minutes to Al Shindagha Heritage District and 20 minutes to Dubai International Airport, and the masterplan places Aurea among the Marina Promenade, The Canal Pool, a school, a mosque, a hotel, and the QE2. For buyers at 0%, the location case can be judged now while the building case waits for measured readings. See the project’s position on the interactive Dubai real estate map.

Interactive Dubai real estate map preview
Click to view Aurea at Rashid Yachts & Marina on Dubai Map

Buyer Resources for This Project

Investing in Aurea at Rashid Yachts & Marina Before Construction Begins

At a 0% reading, residency planning and payment protection come before any build milestone. Each resource below is matched to where Aurea stands at this first inspection.

Aurea at Rashid Yachts & Marina by Emaar Properties in Rashid Yachts & Marina construction updates cover image featuring a project rendering of marina-facing residences, yachts, and waterfront terraces in Dubai - Presented by Tohid Fetrat
You Are Here

Aurea at Rashid Yachts & Marina Construction Updates

This page: the first RERA inspection for Aurea, recorded at 0% on 23 September 2025.

Aurea at Rashid Yachts & Marina by Emaar Properties in Rashid Yachts & Marina Golden Visa concept with a Golden Visa card above an infinity pool overlooking the marina and Dubai skyline in Dubai - Presented by Tohid Fetrat

Aurea at Rashid Yachts & Marina Golden Visa at Every Tier

Aurea at Rashid Yachts & Marina, Emaar's single tower of 169 apartments in Mina Rashid, qualifies at all three apartment types.

Read Aurea Golden Visa Guide
Aurea at Rashid Yachts & Marina by Emaar Properties in Rashid Yachts & Marina escrow account protection concept with shield and padlock icons above a waterfront promenade beside the marina in Dubai - Presented by Tohid Fetrat

Aurea at Rashid Yachts & Marina: The Escrow Record for 172 Homes

Aurea at Rashid Yachts & Marina, DLD project 4115: 172 units, Abu Dhabi Commercial Bank escrow, 0% certified September 2025.

Verify Aurea Escrow Account

Update Timeline

Other Aurea at Rashid Yachts & Marina Construction Updates

September 2025 is the first entry in the Aurea inspection history, so there is no earlier reading to compare; each later cycle joins the timeline as it publishes.

All Aurea at Rashid Yachts & Marina Construction Updates

FAQs

Aurea at Rashid Yachts & Marina Construction Progress in September 2025: Frequently Asked Questions

Aurea at Rashid Yachts & Marina recorded 0% construction progress at the RERA inspection of 23 September 2025, the first reading on record for DLD project 4115. The independent progress monitoring report behind that reading lists the progress status as N/A and notes that no construction activity had started on site at the time of inspection.

Yes. The DLD record lists 30 June 2030 as the completion date, which falls inside the Q2 2030 handover, and registered completion dates can be revised between inspection cycles. With no works started at the September 2025 reading, there is not yet a recorded construction pace against which to test that date; any revision will appear in a later update for project 4115.

The record for project 4115 shows an inspection date of 23 September 2025, project registration on 26 September 2025, a construction start date of 31 March 2026, and a completion date of 30 June 2030. The inspection date falls three days before the registration date, and both are reported here exactly as recorded.

Under the launch payment schedule of record, 10% is due on booking together with the 4% DLD registration fee, followed by 10% in Nov 2025, 10% in May 2026, and 10% in Nov 2026. The first instalment the developer pairs with a construction stage is 10% in Jul 2027 at 10% construction completion, so 40% of the price comes before it; the SPA sets the binding trigger for each payment.

The DLD record lists 31 March 2026 as the construction start date for project 4115, so a reading above 0% depends on works beginning on site around or after that date. How later inspection cycles are scheduled and read is covered in the Aurea at Rashid Yachts & Marina construction updates guide.

No. The image at the top of the September 2025 update is a developer rendering of the finished project, not a site photograph. The 23 September 2025 inspection found no construction activity under way, so no image on the page represents built progress.

A Question the FAQ Can Not Answer?

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is helping you read the September 2025 inspection record for Aurea at Rashid Yachts & Marina correctly before your next payment decision. Client identities and transactions are never published or referenced. Message me directly: you will always reach me personally, never a call center or sales team.

Ask your question, get your answer. No obligation and no follow-up unless you ask for it.

Get Progress Alerts