Aurea at Rashid Yachts & Marina by Emaar Properties in Rashid Yachts & Marina construction updates cover image featuring a project rendering of marina-facing residences, yachts, and waterfront terraces in Dubai - Presented by Tohid Fetrat

Emaar Properties · Rashid Yachts & Marina

Aurea at Rashid Yachts & Marina Construction Updates

The Plot 655 Build Record for Emaar's Single Marina Tower at Mina Rashid

Aurea at Rashid Yachts & Marina recorded 0% at its 23 September 2025 RERA inspection, the pre-start baseline for all later readings of this G+P+13 marina tower.

Construction tracking against RERA inspection data, updated after every recorded inspection.

Direct advisor access. Every message answered personally, never by a call center.

0%Construction Progress
23 September 2025Latest RERA Inspection
169 residential unitsTotal Units
Project 4115DLD Registration

Construction Snapshot

Aurea at Rashid Yachts & Marina at a Glance

Aurea at Rashid Yachts & Marina is Emaar Properties' single G+P+13 tower of 169 residences on plot 655 at Mina Rashid, registered with the DLD as project 4115. The only RERA inspection on its record so far, dated 23 September 2025, found no site works under way and recorded 0%; the DLD record then shows registration on 26 September 2025 and a construction start date of 31 March 2026. Because Aurea is one building rather than a cluster of phases, every future percentage on this page will describe a single structure rising beside the marina, with no averaging across towers.

DLD Project Number

4115

Project Status

Active

Construction Start

31 March 2026 (DLD)

Total Units

169 residential units

Total Built-Up Area

18,298.19 sq m

Registered Completion Date

30 June 2030 (DLD), handover Q2 2030

Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.

Inspection Record

Aurea at Rashid Yachts & Marina Construction Update Timeline

Aurea's record holds one reading so far: 0% at the RERA inspection of 23 September 2025, dated three days before the 26 September 2025 DLD registration of project 4115 and 189 days before its 31 March 2026 construction start date. The single dot on the track below marks that baseline and the table row links the September 2025 monthly update; each later inspection adds its own dot and row here.

Inspection MonthConstruction ProgressInspection DateFull Update
September 20250%23 September 2025View the September 2025 update

Pace Analysis

How Fast Aurea at Rashid Yachts & Marina Has Been Built

One inspection cannot show a pace, so for Aurea this section sets the yardsticks its next readings will be measured against, drawn from the DLD dates and the payment plan of record:

  • 23 Sep 2025: first RERA inspection, 0%, progress status N/ABaseline only, no pace yet
  • 31 Mar 2026 start to 30 Jun 2030 completion (DLD): 0% to 100% in 51 monthsAbout 2.0 points per month needed
  • Payment plan of record: 10% construction by Jul 2027 to 70% by Jan 2029About 3.3 points per month implied

With a single 0% point, Aurea's record has no curve to read yet, and because the 23 September 2025 inspection came before the 31 March 2026 start date, the first informative figure has to come from a later cycle. The two benchmarks above frame what that figure should look like. Spread evenly, the DLD dates ask for roughly 2 points a month across one G+P+13 tower; the payment plan's own milestone dates are steeper in the middle, packing 60 points into the 18 months between Jul 2027 and Jan 2029, then allowing 17 months for the last 30 points to Jun 2030. For an investor, readings that trail the Jul 2027 and Mar 2028 milestones would be the first signal worth pricing in; for an end user planning a Q2 2030 move, the test is whether the tower is near 70% by Jan 2029, leaving finishing rather than structure for the final stretch.

Get the Next Inspection Figure First

Tell me you are tracking Aurea at Rashid Yachts & Marina and I will send you the next recorded figure and site photos directly, ahead of the page update.

Get the Next Update on WhatsApp

Project Profile

About Aurea at Rashid Yachts & Marina at Mina Rashid

A 0% reading only means something next to what the tower will deliver. The full project guide covers the residences this record is tracking toward:

Aurea waterfront residences exterior at Rashid Yachts & Marina in Mina Rashid, Dubai - Presented by Tohid Fetrat

Aurea at Rashid Yachts & Marina: A Single G+P+13 Tower

Aurea at Rashid Yachts & Marina is a single Emaar tower of 169 waterfront apartments with one, two and three bedrooms.

View the Aurea at Rashid Yachts & Marina Project Guide

Considering an Entry at the Start of the Record?

Limited units are available at Aurea as of this update, and the mix shifts between inspection cycles. If entering at the 0% recorded on 23 September 2025, with handover scheduled for Q2 2030, fits your horizon, ask me what is open now.

Ask About Remaining Availability on WhatsApp

Stage Record

Aurea at Rashid Yachts & Marina Build Stages, Mapped to the Inspections

Only the first of the five stages below has an inspection behind it: Aurea stood at 0% on 23 September 2025, so the remaining windows are anchored to the DLD start and completion dates and to the construction milestones the payment plan of record dates for this tower.

Current PhaseSep 2025, 0% at last reading

Registration and Pre-Start Record

The 23 September 2025 inspection logged plot 655 at 0% with no works under way, and DLD registration as project 4115 followed on 26 September 2025.

From 31 Mar 2026 (DLD start date)

Site Enabling and Foundations

The DLD record schedules works to begin on 31 March 2026; the first reading above 0% will date the actual start of groundworks on the marina plot.

Not yet recorded

Podium and Tower Structure

Ground, podium, and 13 upper floors of the single tower; readings here will be set against the plan's 10% (Jul 2027) and 30% (Mar 2028) milestones.

Not yet recorded

Facade, Services, and Marina-Side Works

Enclosure and building services for 169 residences; the plan pairs 50% with Sep 2028 and 70% with Jan 2029, the yardsticks for this band.

Handover scheduled Q2 2030

Finishing, Commissioning, and Delivery

Apartment finishing and final approvals toward the 30 June 2030 DLD completion date, with the last 20% instalment tied to 100% construction completion in Jun 2030.

What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Aurea at Rashid Yachts & Marina's own record.

Buyer Position

Tracking Your Position at Aurea at Rashid Yachts & Marina

This page is one of four project resources that together cover a Aurea at Rashid Yachts & Marina purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Aurea at Rashid Yachts & Marina by Emaar Properties in Rashid Yachts & Marina construction updates cover image featuring a project rendering of marina-facing residences, yachts, and waterfront terraces in Dubai - Presented by Tohid Fetrat
You Are Here

Aurea at Rashid Yachts & Marina Construction Updates

This page: every RERA reading for Aurea's G+P+13 tower, starting from 0% on 23 September 2025.

Aurea at Rashid Yachts & Marina by Emaar Properties in Rashid Yachts & Marina Golden Visa concept with a Golden Visa card above an infinity pool overlooking the marina and Dubai skyline in Dubai - Presented by Tohid Fetrat

Aurea at Rashid Yachts & Marina Golden Visa at Every Tier

Aurea at Rashid Yachts & Marina, Emaar's single tower of 169 apartments in Mina Rashid, qualifies at all three apartment types.

Read the Aurea at Rashid Yachts & Marina Golden Visa Guide
Aurea at Rashid Yachts & Marina by Emaar Properties in Rashid Yachts & Marina escrow account protection concept with shield and padlock icons above a waterfront promenade beside the marina in Dubai - Presented by Tohid Fetrat

Aurea at Rashid Yachts & Marina: The Escrow Record for 172 Homes

Aurea at Rashid Yachts & Marina, DLD project 4115: 172 units, Abu Dhabi Commercial Bank escrow, 0% certified September 2025.

Verify the Aurea at Rashid Yachts & Marina Escrow Account

Approaching Handover

Between 0% and Handover: What Aurea at Rashid Yachts & Marina Buyers Should Do Now

With Aurea at 0% on 23 September 2025 and a 31 March 2026 start date in the DLD record, buyers pay against dates before they pay against certified works: under the launch schedule of record, 40% falls due by date ahead of the first construction-linked instalment at 10% completion in Jul 2027. The next dated instalment in that schedule is Nov 2026, so the three checks below belong before that payment, not after it.

First, confirm that every transfer goes to the project 4115 escrow account at Abu Dhabi Commercial Bank; the Aurea at Rashid Yachts & Marina escrow account page shows how to check it against the DLD record.

Second, if residency is part of the plan, settle eligibility early through the Aurea at Rashid Yachts & Marina Golden Visa eligibility guide, since every tier starts above AED 2M ≈ USD 545K and the guide explains how an off-plan purchase is treated.

Third, follow the record from its baseline: the Aurea at Rashid Yachts & Marina September 2025 inspection report documents the 0% starting point, and the first reading above it will show whether works began near 31 March 2026.

Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.

The Wider Picture

Explore Mina Rashid Structure

A record that opened at 0% in September 2025 is only part of the picture; the rest is the marina district forming around plot 655. These three pages set Aurea's build in its listing, community, and developer context:

Waterfront apartment buildings with modern architecture overlooking a marina filled with luxury yachts at Rashid Yachts and Marina by Emaar in Dubai Presented by Tohid Fetrat

Mina Rashid Properties for Sale

Browse waterfront apartments for sale at Rashid Yachts & Marina, with projects, prices and payment plans.

See Mina Rashid Properties for Sale
Luxury yachts at Rashid Yachts and Marina waterfront community with modern residences and marina promenade in Mina Rashid Dubai Presented by Tohid Fetrat

Mina Rashid Community Overview

Read the Rashid Yachts & Marina guide: Emaar's transformation of historic Port Rashid into a marina lifestyle community.

Explore the Mina Rashid Community
Emaar Properties developer showcasing Downtown Dubai skyline with Burj Khalifa and surrounding residential and commercial towers at dusk Presented by Tohid Fetrat

Emaar Properties: Burj Khalifa, Downtown Dubai and Twenty Master Communities

Emaar, founded in 1997, built Burj Khalifa and Downtown Dubai and has delivered over 85,000 homes across twenty master communities.

View the Emaar Properties Developer Profile

Construction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.

FAQs

Aurea at Rashid Yachts & Marina Construction Updates Frequently Asked Questions

Aurea at Rashid Yachts & Marina is an Active DLD-registered project, number 4115, and its latest recorded RERA inspection, dated 23 September 2025, put construction at 0% with no works yet under way on plot 655. That single reading is the whole record so far and is set out in the Aurea inspection timeline above.

The 23 September 2025 inspection recorded 0% for Aurea at Rashid Yachts & Marina, and as the first reading for project 4115 it has no earlier figure to measure a point change against. The inspection report left the RERA progress status as N/A; the full breakdown sits in the Aurea at Rashid Yachts & Marina September 2025 construction update.

Aurea at Rashid Yachts & Marina is scheduled for handover in Q2 2030, and the DLD record for project 4115 carries a completion date of 30 June 2030, 51 months after its 31 March 2026 construction start date. The payment plan of record ties its final 20% instalment to 100% construction completion in Jun 2030, and at the 0% measured on 23 September 2025 the whole build still lay ahead.

Aurea at Rashid Yachts & Marina includes 169 residential units, all one, two, and three bedroom apartments, in a single G+P+13 tower with retail on the ground floor. Apartment sizes run from 799 sq ft (74 sq m) for the smallest 1 bedroom to 2,484 sq ft (231 sq m) for the largest 3 bedroom, and all 169 were still ahead of any site works when the 23 September 2025 inspection recorded 0%.

Construction at Aurea at Rashid Yachts & Marina is dated to begin on 31 March 2026 in the DLD record for project 4115, 189 days after the 0% inspection of 23 September 2025. From that start date, the 30 June 2030 completion date leaves 51 months for the full G+P+13 build, and the first published reading above 0% will confirm when site works actually began.

Nothing had been built at Aurea at Rashid Yachts & Marina as of the 23 September 2025 inspection, which found no construction activity on plot 655 and recorded 0%. Every package, from enabling works and foundations through the podium and 13 upper floors to facade and fit-out for 169 residences, remained ahead at that date, as the Aurea stage record shows.

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is keeping the Aurea at Rashid Yachts & Marina construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.