Emaar Properties · Rashid Yachts & Marina
Avonlea at Rashid Yachts & Marina Construction Updates
The Verified Build Record on Plot 468 at Mina Rashid
Avonlea reached 63.71% construction at its 21 July 2026 RERA inspection, and the climb from a February 2024 start now reads as fit-out rather than structure.
Construction tracking against RERA inspection data, updated after every recorded inspection.
Direct advisor access. Every message answered personally, never by a call center.
Construction Snapshot
Avonlea at Rashid Yachts & Marina at a Glance
Avonlea is Emaar's 163-residence address on plot 468 inside Rashid Yachts & Marina, registered with the Dubai Land Department on 07 November 2023 and recorded as under construction since 29 February 2024. Its 63.71% reading of 21 July 2026 covers two residential buildings over a shared retail ground floor rather than a single tower, so progress here is measured across the width of the plot instead of floors climbed. The figures below are the registration anchors behind that record.
2838
Active
29 February 2024
163 residential units
18,118.62 sq m
November 2027
Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.
Inspection Record
Avonlea at Rashid Yachts & Marina Construction Update Timeline
This record opens with one published RERA inspection: 63.71% certified on 21 July 2026, the first reading published for Avonlea on this site. The same report carries a previous certified reading of 45.89% without an inspection date, a 17.82-point step that shows how much of the two buildings was already standing before July. Every further reading joins the track and the table below as it is recorded, and each row links the full monthly update.
| Inspection Month | Construction Progress | Inspection Date | Full Update |
|---|---|---|---|
| July 2026 | 63.71% | 21 July 2026 | View the July 2026 update |
Pace Analysis
How Fast Avonlea at Rashid Yachts & Marina Has Been Built
Reading the pace behind a percentage tells buyers more than the percentage itself. Avonlea's record so far gives two measurable intervals:
- Feb 2024 start to Jul 2026: enabling, foundations, and superstructure, 0% to 63.71%About 2.2 points per month
- Previous certified reading to 21 Jul 2026: 45.89% to 63.71%, interval date not publishedPlus 17.82 points
The 63.71% certified on 21 July 2026 sits 28.7 months after the 29 February 2024 construction start, an average of about 2.2 percentage points per month. That average is honest but conservative, because the opening months of any plot go into excavation, piling, and foundations that consume time while barely moving the certified figure, so the recent monthly rate is almost certainly above the lifetime average. The 17.82 points between the previous certified reading of 45.89% and the July figure support that, although the earlier inspection date is not published, so that interval cannot be converted into a monthly rate here without guessing. For a buyer on the 10/80/10 plan, the practical reading is that Avonlea has crossed from structure into envelope and fit-out, the phase where progress stops being visible from the road and the inspection record becomes the only reliable measure. For an investor, 36.29 points remain between this reading and the November 2027 handover, a comfortable runway at the pace recorded so far.
Get the Next Inspection Figure First
Tell me you are tracking Avonlea at Rashid Yachts & Marina and I will send you the next recorded figure and site photos directly, ahead of the page update.
Get the Next Update on WhatsAppProject Profile
About Avonlea at Rashid Yachts & Marina at Mina Rashid
A build percentage only matters against what is being delivered. The full project guide covers what buyers on this page are tracking toward:

Avonlea at Rashid Yachts & Marina: Apartments on a Swimmable Canal Pool
Avonlea at Rashid Yachts & Marina holds 163 Emaar apartments beside a swimmable canal pool, gardens and the promenade.
View the Avonlea at Rashid Yachts & Marina Project GuideConsidering an Entry at 63.71%?
Availability at Avonlea keeps shifting as each certified reading moves the project closer to November 2027. If the record on this page is what brought you here, ask for the current list before it narrows further.
Ask About Remaining Availability on WhatsAppStage Record
Avonlea at Rashid Yachts & Marina Build Stages, Mapped to the Inspections
Rather than a generic construction sequence, each stage below is anchored to the window it actually occupied in Avonlea's own DLD and RERA record, from the 07 November 2023 registration to the 63.71% certified in July 2026.
Registration and Site Mobilisation
Project 2838 was registered with the Dubai Land Department on 07 November 2023, and construction on plot 468 was recorded as started on 29 February 2024.
Enabling Works and Foundations
Excavation and foundations on the 18,118.62 sq m registered land parcel were behind the project by July 2026, signed off as substantially complete. This is the phase that absorbs the most calendar time for the fewest certified points.
Superstructure Across Both Buildings
Floor plates rose off the shared ground level to six, seven, and nine storeys across the two buildings. By 21 July 2026 both the frame and the internal works behind it sat in the advanced band of the inspector's assessment.
Envelope, MEP, and Internal Fit-Out
Three packages were still moving at their own rates on 21 July 2026: interior finishes, the MEP installation, and the external envelope, with site works running in parallel around the retail ground floor.
Finishing, Commissioning, and Handover
Apartment finishing, systems commissioning, and final external works close the 36.29 points between the July 2026 record and the November 2027 handover.
What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Avonlea at Rashid Yachts & Marina's own record.
Buyer Position
Tracking Your Position at Avonlea at Rashid Yachts & Marina
This page is one of four project resources that together cover a Avonlea at Rashid Yachts & Marina purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Avonlea at Rashid Yachts & Marina Construction Updates
This page: the verified RERA inspection record for Avonlea, from the February 2024 start toward handover.

Avonlea at Rashid Yachts & Marina Golden Visa: Two of Three Layouts
Avonlea at Rashid Yachts & Marina, 163 apartments in Madinat Dubai Almelaheyah, qualifies at 2 and 3 bedrooms only.
Read the Avonlea at Rashid Yachts & Marina Golden Visa Guide
Avonlea at Rashid Yachts & Marina Escrow, Banked at Emirates NBD
Emirates NBD holds Avonlea at Rashid Yachts & Marina escrow: DLD project 2838, 163 units, 63.71% certified in July 2026.
Verify the Avonlea at Rashid Yachts & Marina Escrow Account
Avonlea at Rashid Yachts & Marina Snagging Beside the Superyacht Harbour
Avonlea at Rashid Yachts & Marina is two Emaar Properties buildings of 163 apartments above a shared ground floor with retail.
Book Avonlea at Rashid Yachts & Marina SnaggingApproaching Handover
Between 63.71% and Handover: What Avonlea at Rashid Yachts & Marina Buyers Should Do Now
At 63.71% the visible half of Avonlea is largely done, and the value of each further inspection sits in what it releases rather than in what it shows from the road. That changes what a buyer should be watching between now and the next report. Avonlea runs a 10/80/10 payment plan, so 80% of the price falls due during construction and every certified reading between today and the November 2027 handover can move an installment date. The three checks below belong now, not when the handover notice arrives.
First, match your remaining installments to certified milestones using the Avonlea escrow account record, so any payment request can be tested against a RERA reading before it is paid.
Second, if your purchase may qualify for residency, settle eligibility early through the Avonlea Golden Visa eligibility guide, because title deed timing at handover sets which application path is open to you.
Third, put the defect inspection in the calendar now: the Avonlea snagging inspection page covers when the window opens and what gets documented before you accept the keys.
Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.
The Wider Picture
Explore Mina Rashid Structure
A build record is only half the picture; the other half is what is rising around it. These three pages put Avonlea's progress in its masterplan, community, and developer context:

Mina Rashid Properties for Sale
Browse waterfront apartments for sale at Rashid Yachts & Marina, with projects, prices and payment plans.
See Mina Rashid Properties for Sale
Mina Rashid Community Overview
Read the Rashid Yachts & Marina guide: Emaar's transformation of historic Port Rashid into a marina lifestyle community.
Explore the Mina Rashid Community
Emaar Properties: Burj Khalifa, Downtown Dubai and Twenty Master Communities
Emaar, founded in 1997, built Burj Khalifa and Downtown Dubai and has delivered over 85,000 homes across twenty master communities.
View the Emaar Properties Developer ProfileConstruction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.
FAQs
Avonlea at Rashid Yachts & Marina Construction Updates Frequently Asked Questions
Avonlea at Rashid Yachts & Marina is an active DLD-registered project (number 2838) in its envelope and fit-out phase, recorded at 63.71% at the RERA inspection of 21 July 2026. The full record is in the inspection timeline above.
The 21 July 2026 inspection recorded 63.71% construction progress, up 17.82 points from the previous certified reading of 45.89%. Groundworks were signed off as substantially complete at that visit, the frame and the internal works behind it sat in the advanced band, and interior finishes, MEP, and the external envelope were each moving at their own rate. The site report is in the Avonlea July 2026 construction update.
Across the 28.7 months between the 29 February 2024 construction start and the 21 July 2026 inspection, Avonlea averaged about 2.2 percentage points per month to reach 63.71%. The 45.89% previous reading is published without its inspection date, so that shorter interval cannot be converted into a monthly rate. The full reading of the curve is in the pace analysis above.
Handover for Avonlea is scheduled for November 2027. The latest RERA inspection, dated 21 July 2026, recorded 63.71% progress, leaving 36.29 points of certified construction to run against that date. Emaar confirms handover as final inspections complete, and this page is updated each time a new inspection is recorded for project 2838.
DLD registration records 163 residential units for project 2838, made up of one, two, and three bedroom apartments in two residential buildings over a shared ground floor with retail frontage. The registration lists 18,118.62 sq m as the registered land area of plot 468 and publishes no built-up area figure, so none is shown in the key facts above.
Construction on plot 468 was recorded as started on 29 February 2024, about sixteen weeks after project 2838 was registered with the Dubai Land Department on 07 November 2023. The first inspection reading published on this site is the 63.71% certified on 21 July 2026.

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is keeping the Avonlea at Rashid Yachts & Marina construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.
Ask your question, get your answer. No obligation and no follow-up unless you ask for it.