DAMAC Properties · DAMAC Islands 2
Bahamas at DAMAC Islands 2 Construction Updates
Cluster 01 of DAMAC Islands 2, Tracked From Its November 2025 Baseline
Bahamas at DAMAC Islands 2 recorded 0.33% in the DLD register on 14 May 2026, its first reading above zero, as enabling works opened the Dubailand cluster.
Construction tracking against RERA inspection data, updated after every recorded inspection.
Direct advisor access. Every message answered personally, never by a call center.
Construction Snapshot
Bahamas at DAMAC Islands 2 at a Glance
Bahamas at DAMAC Islands 2 is the cluster DAMAC numbers 01 among the eight island-themed neighbourhoods of its Dubailand masterplan, with 544 townhouses and villas registered to project 4243. Its record starts earlier than its build: the first inspection, on 24 November 2025, found an untouched plot at 0%, more than five months before the 02 May 2026 construction start the register now lists. The six anchors below are the DLD entries every later reading is measured against, running to a registered completion of 30 June 2030.
4243
Active
02 May 2026
544 residential units
100,825.60 sq m
30 June 2030
Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.
Inspection Record
Bahamas at DAMAC Islands 2 Construction Update Timeline
Two inspections make up the Bahamas record so far: a 0% baseline on 24 November 2025, before any work had begun on plot 20208, and 0.33% on 14 May 2026, twelve days after the registered construction start. Both dots sit at the far left of the track below, which is the plain picture of a cluster at the opening of its build, and each table row links the full monthly update with the inspection notes behind it.
| Inspection Month | Construction Progress | Inspection Date | Full Update |
|---|---|---|---|
| May 2026 | 0.33% | 14 May 2026 | View the May 2026 update |
| November 2025 | 0% | 24 November 2025 | View the November 2025 update |
Pace Analysis
How Fast Bahamas at DAMAC Islands 2 Has Been Built
With two readings on file, the Bahamas record holds a single interval so far, and most of it passed before the site was mobilized:
- Nov 2025 to May 2026: site mobilization and enabling works, 0% to 0.33%About 0.06 points per month
That rate is arithmetic on two dated readings, not a forecast. Of the 171 days between the 24 November 2025 baseline and the 14 May 2026 inspection, 159 came before the registered construction start of 02 May 2026, so the 0.33 points really describe twelve days of mobilization rather than half a year of building. The figure worth holding alongside it is the one the record has to meet: to reach 100% by the registered 30 June 2030, the remaining 99.67 points after 14 May 2026 need to average about 2.0 points per month over roughly 49.5 months. For an end user timing a move, and for an investor matching the 20/55/25 plan against delivery, the next reading is the first that will show whether enabling works are turning into that kind of rate.
Get the Next Inspection Figure First
Tell me you are tracking Bahamas at DAMAC Islands 2 and I will send you the next recorded figure and site photos directly, ahead of the page update.
Get the Next Update on WhatsAppProject Profile
About Bahamas at DAMAC Islands 2 at DAMAC Island 2
The 0.33% reading of 14 May 2026 only means something next to what is being delivered. The full project guide covers the homes this record is tracking toward:

Bahamas at DAMAC Islands 2: Townhouses and Villas with Maid's Rooms
Bahamas at DAMAC Islands 2 is a townhouse and villa cluster of 544 units in Dubailand, up to six bedroom villas.
View the Bahamas at DAMAC Islands 2 Project GuideConsidering an Early-Stage Entry?
Availability at Bahamas moves with each release while the cluster is still at the enabling stage. If the record on this page is what brought you here, ask me for current availability before the layouts you want are taken.
Ask About Remaining Availability on WhatsAppStage Record
Bahamas at DAMAC Islands 2 Build Stages, Mapped to the Inspections
Each stage below is tied to where the Bahamas record actually stands: two stages already carry dated readings, and three are still ahead of the 0.33% recorded on 14 May 2026, with no dates assigned to them until inspections record them.
Baseline on an Unstarted Plot
The 24 November 2025 inspection logged 0% on plot 20208 before any work had begun, and the project entered the register on 27 November 2025.
Mobilization and Enabling Works
From the 02 May 2026 construction start, the 14 May 2026 inspection recorded 0.33% as the site was mobilized and enabling works got under way.
Foundations and Concrete Structure
Concrete structure for the G+1 and G+2 townhouses and villas; no inspection had reached this stage as of the 14 May 2026 reading.
Blockwork and Finishes Across 544 Homes
Blockwork plus internal and external finishes for all 544 units, the bulk of the 99.67 points still open after 14 May 2026.
Completion and Handover
The DLD register holds 30 June 2030 as completion; the final 25% of the Bahamas 1 plan falls due when completion arrives.
What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Bahamas at DAMAC Islands 2's own record.
Buyer Position
Tracking Your Position at Bahamas at DAMAC Islands 2
This page is one of four project resources that together cover a Bahamas at DAMAC Islands 2 purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Bahamas at DAMAC Islands 2 Construction Updates
This page: every dated DLD reading for project 4243, from the November 2025 baseline to handover.

Bahamas at DAMAC Islands 2 Golden Visa: Cluster 01, Three Tiers
Bahamas at DAMAC Islands 2, cluster 01 in Dubailand, qualifies at both townhouse tiers and the 6 bedroom luxury villa.
Read the Bahamas at DAMAC Islands 2 Golden Visa Guide
Bahamas at DAMAC Islands 2 Escrow: 544 Units, One Account
Bahamas at DAMAC Islands 2, DLD project 4243, escrows 544 units at First Abu Dhabi Bank, certified 0.33% May 2026.
Verify the Bahamas at DAMAC Islands 2 Escrow AccountApproaching Handover
Between 0.33% and Handover: What Bahamas at DAMAC Islands 2 Buyers Should Do Now
At 0.33% on 14 May 2026, the Bahamas site has more than four years of recorded progress ahead of it, but the payment plan does not wait for the build: its instalments count from each buyer's sale date, with 3% steps at months 8, 14, 20 and 26, so the three steps below belong to the months before the structure rises, not after.
First, before every transfer, match the beneficiary details to the Bahamas project 4243 escrow account, so each of the 47 instalments lands in the DLD-regulated account and nowhere else.
Second, set your own instalment dates beside each new register reading; the Bahamas May 2026 inspection update is the current reference point, and each later cycle adds the next.
Third, if residency is part of the plan, read how an off plan Bahamas unit is treated in the Bahamas Golden Visa eligibility guide now, while 75% of the price is still being paid down before handover.
Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.
The Wider Picture
Explore DAMAC Island 2 Structure
A single cluster at 0.33% on 14 May 2026 is only part of the picture; the rest is the masterplan being built around it. These three pages put the Bahamas record in its community, market, and developer context:

DAMAC Island 2 Properties for Sale
Explore DAMAC Islands 2 properties for sale: lagoon-front villas and townhouses with flexible payment plans and resort-style island living.
See DAMAC Island 2 Properties for Sale
DAMAC Island 2 Community Overview
Read the DAMAC Islands 2 guide: eight island-themed clusters of lagoon-front villas and townhouses, with masterplan and payment plans.
Explore the DAMAC Island 2 Community
DAMAC Properties: Lagoon Communities, Golf Villas and Branded Collaborations
Founded in 2002, DAMAC has delivered 48,000 homes and is known for large-scale master communities, luxury residential projects and branded collaborations.
View the DAMAC Developer ProfileConstruction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.
FAQs
Bahamas at DAMAC Islands 2 Construction Updates Frequently Asked Questions
Bahamas at DAMAC Islands 2 is an active DLD-registered project, number 4243, in its mobilization and enabling works phase, recorded at 0.33% in the DLD register at the inspection of 14 May 2026. The full dated record is in the Bahamas inspection timeline above.
Two inspections are on record for Bahamas at DAMAC Islands 2: 0% on 24 November 2025 and 0.33% on 14 May 2026, the latest, a rise of 0.33 points across 171 days. The May reading and its inspection notes are covered in the Bahamas at DAMAC Islands 2 May 2026 construction update.
The DLD register holds 30 June 2030 as the completion date for Bahamas at DAMAC Islands 2, the same date the Bahamas 1 payment plan prints as its anticipated completion, with handover expected in June 2030. At the 0.33% reading of 14 May 2026 that date was about four years and one month away and had not passed, and this page's record is updated when each new inspection is recorded.
The DLD register lists 544 units for Bahamas at DAMAC Islands 2 under project 4243, with the project registered on 27 November 2025 and its status shown as Active. The inspection reports name DAMAC PRIME DEVELOPMENT L.L.C, developer number 2464, as the registered developer.
About 2.0 points per month. After the 0.33% reading of 14 May 2026, 99.67 points remained, and about 49.5 months separate that inspection from the registered completion of 30 June 2030. The only interval on record so far, 24 November 2025 to 14 May 2026, averaged about 0.06 points per month, most of it before the 02 May 2026 construction start; both figures are arithmetic on dated readings, not forecasts, and the working is in the Bahamas pace analysis above.
No structure had been recorded at Bahamas at DAMAC Islands 2 by the 14 May 2026 inspection, which found the site being mobilized and enabling works in their first weeks, at 0.33% in the DLD register. The earlier 24 November 2025 inspection recorded 0%, before any work had begun on plot 20208.

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is keeping the Bahamas at DAMAC Islands 2 construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.
Ask your question, get your answer. No obligation and no follow-up unless you ask for it.