The Closed Inspection Record of a Delivered Dubai Harbour Address

Beach Isle recorded 100% construction at its 02 May 2023 RERA inspection, closing a Dubai Harbour build that the Dubai Land Department now carries as Finished.

Construction tracking against RERA inspection data, updated after every recorded inspection.

Direct advisor access. Every message answered personally, never by a call center.

100%Construction Progress
02 May 2023Latest RERA Inspection
397 residential unitsTotal Units
Project 2207DLD Registration

Construction Snapshot

Beach Isle at Emaar Beachfront at a Glance

Beach Isle is Emaar's 397-residence pair of buildings inside Emaar Beachfront on Dubai Harbour, registered with the Dubai Land Department as project 2207 on 29 January 2020. Three years and two days separate the 30 April 2020 construction start from the 100% reading taken on 02 May 2023, and the cards below are the registered anchors behind that span. Because the file closed with a single published inspection, every figure on this page traces to one report rather than to a long chain of readings.

DLD Project Number

2207

Project Status

Finished

Construction Start

30 April 2020

Total Units

397 residential units

Total Built-Up Area

45,359.16 sq m

Registered Completion Date

30 April 2023 (DLD)

Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.

Inspection Record

Beach Isle at Emaar Beachfront Construction Update Timeline

This record is short, and the reason matters. The Dubai Land Department application holds two readings for project 2207: a previous inspection at 86.17% that carries no date, and the 100% current progress recorded on 02 May 2023, the report that set the RERA Progress Status to Completed and ended the monitoring cycle. The track below plots both readings at their exact percentages; the table links the published update for the one inspection that carries a date.

Inspection MonthConstruction ProgressInspection DateFull Update
May 2023100%02 May 2023View the May 2023 update
!

Reading the dates: the registered completion date recorded for project 2207 is 30 April 2023, and the inspection two days later, on 02 May 2023, recorded 100% with Progress Status Completed. The registered date is the administrative anchor set at project registration, and in this record the closing inspection confirmed it rather than overran it.

Pace Analysis

How Fast Beach Isle at Emaar Beachfront Has Been Built

Pace is normally read between consecutive inspections. Beach Isle does not allow that, because only one of its two preserved readings carries a date, so the arithmetic below works from the registered dates instead:

  • Apr 2020 to May 2023, whole programme: groundbreaking to 100%About 2.8 points per month
  • Previous reading to 02 May 2023, finishing and commissioning: 86.17% to 100%Plus 13.83 points, earlier reading undated
  • 30 Apr 2023 to 02 May 2023: registered completion to the closing inspectionTwo days

The first figure is an average across the whole 36-month programme rather than a phase velocity: the full 100 points divided by the months between the 30 April 2020 start and the 02 May 2023 inspection. It is the only pace figure this record supports honestly. The 13.83 points between the previous reading and the closing one describe the shape of the ending without dating it, because that earlier figure was never stamped with a date in the application, so no per-month rate can be computed for the pair. What the record does settle is the question both audiences ask first. A Dubai Harbour project that reached 100% within two days of its registered completion date did not slip. For an end user that means the keys were never chased; for an investor it means the delivery risk that normally prices an off-plan discount was not realised here, and any premium in a Beach Isle resale today is paid for a building that exists rather than for a programme still running.

Get the Next Inspection Figure First

Tell me you are tracking Beach Isle at Emaar Beachfront and I will send you the next recorded figure and site photos directly, ahead of the page update.

Get the Next Update on WhatsApp

Project Profile

About Beach Isle at Emaar Beachfront

A closed percentage only means something next to what was delivered. The project guide covers the residences sitting behind the 100% reading:

Beach Isle at Emaar Beachfront exterior towers with the beachfront promenade and sandy beach in Dubai. Presented by Tohid Fetrat.

Beach Isle at Emaar Beachfront: An Island Address in Dubai Harbour

Beach Isle at Emaar Beachfront is a two building Emaar address of 397 units, apartments and villas, with private beach access.

View the Beach Isle at Emaar Beachfront Project Guide

Considering a Ready Beachfront Home?

Beach Isle was handed over after the 2023 record closed, so what trades now is resale stock and whatever remains unsold rather than a launch list. If the record on this page is what brought you here, ask me what is genuinely available before you shortlist.

Ask About Remaining Availability on WhatsApp

Stage Record

Beach Isle at Emaar Beachfront Build Stages, Mapped to the Inspections

One inspection was published for this project, so the stages below are anchored to the dates the record does carry: the registration and start dates, the authority clearances named in the monitoring report, and the closing reading itself.

From 30 April 2020

Site Activation on Plot 3651

Construction began on 30 April 2020 on plot 3651 in Marsa Dubai, three months after project 2207 was registered with the Dubai Land Department on 29 January 2020.

2020 to 2022, no dated reading

Two Buildings Over a Shared Podium

Building 1 rose to 23 floors plus roof and upper roof and Building 2 to 16, over a podium of one basement, ground, mezzanine and four parking levels shared between them. No inspection figure was preserved for this window.

Previous reading, 86.17%

Enclosure, Fit-Out and District Cooling

The only pre-completion figure the application holds is 86.17%, recorded without a date, covering the residential, retail and district cooling plant scope through enclosure and internal fit-out.

Feb to Mar 2023

Clearances and Utility Connection

Three clearances sit in this window, every one of them ahead of the final reading: DCD on 22 Feb 2023, the Building Completion Certificate issued by DDA on 16 Mar 2023, and every DEWA meter installed and connected across the two buildings.

Current Phase02 May 2023, 100% recorded

Snagging, Deep Cleaning and Handover

At 02 May 2023 the monitoring report placed all building construction activity in the substantially completed category and left only snagging and deep cleaning live on site, which is why RERA Progress Status moved to Completed at 100%.

What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Beach Isle at Emaar Beachfront's own record.

Buyer Position

Tracking Your Position at Beach Isle at Emaar Beachfront

This page is one of four project resources that together cover a Beach Isle at Emaar Beachfront purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Beach Isle at Emaar Beachfront by Emaar construction updates cover image featuring a project rendering of an infinity pool beside the residential building with Gulf and waterfront views in Dubai - Presented by Tohid Fetrat
You Are Here

Beach Isle at Emaar Beachfront Construction Updates

This page: the full Beach Isle build record, from groundbreaking to the closing 100% reading.

Beach Isle at Emaar Beachfront by Emaar Golden Visa card graphic above a balcony overlooking Palm Jumeirah and Gulf waters in Dubai - Presented by Tohid Fetrat

Beach Isle at Emaar Beachfront Golden Visa: Apartments and Villas

Beach Isle at Emaar Beachfront, 397 Emaar units in Dubai Harbour, qualifies at every apartment and villa tier on transfer.

Read the Beach Isle at Emaar Beachfront Golden Visa Guide
Beach Isle at Emaar Beachfront by Emaar escrow account protection concept with shield and padlock graphics above a landscaped waterfront courtyard between residential buildings in Dubai - Presented by Tohid Fetrat

Beach Isle at Emaar Beachfront Escrow: Mashreq's Certified Beachfront File

Beach Isle at Emaar Beachfront read 100% certified May 2023, DLD project 2207, its 397 units escrowed with Mashreq.

Verify the Beach Isle at Emaar Beachfront Escrow Account
Beach Isle at Emaar Beachfront by Emaar snagging inspection cover image featuring a bedroom rendering with floor to ceiling windows and waterfront skyline view in Dubai - Presented by Tohid Fetrat

Beach Isle at Emaar Beachfront Snagging: Apartments and Beachfront Villas

Beach Isle at Emaar Beachfront is two Emaar Properties buildings of 23 and 16 floors, 397 residences from apartments to villas.

Book Beach Isle at Emaar Beachfront Snagging

Approaching Handover

Between 100% and Handover: What Beach Isle at Emaar Beachfront Buyers Should Do Now

With 100% recorded on 02 May 2023 and the buildings handed over, the sequence a buyer follows changes shape. Nothing waits on a construction milestone any more, so the checks that used to run alongside a payment plan now all land in the days around a transfer. Once a home is ready, that transfer moves on the buyer's own paperwork rather than on the developer's programme, which means none of the three below can be left until the appointment itself.

First, have the residence documented independently before you sign for it. The Beach Isle snagging inspection page sets out what an inspector covers in a completed Emaar apartment and when to arrange it.

Second, read how money moved while the building was going up. The Beach Isle escrow account page shows how instalments on project 2207 were tied to certified progress, which is the history a resale buyer inherits with the unit.

Third, if residency is part of the plan, the title deed issued on a completed building is what an application rests on. The Beach Isle Golden Visa guide covers the threshold, the typologies and the route.

Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.

The Wider Picture

Explore Emaar Beachfront Structure

A build record reads differently next to what surrounds it. These three pages place the Beach Isle result inside its listing set, its master community, and its developer's wider output:

Emaar Beachfront luxury skyline terrace lifestyle Dubai Presented by Tohid Fetrat

Emaar Beachfront Properties for Sale

Browse apartments and penthouses for sale in Emaar Beachfront, Dubai's private beach community in Dubai Harbour.

See Emaar Beachfront Properties for Sale
Aerial master plan view of Emaar Beachfront in Dubai Harbour, showing beachfront residential towers, private beaches, marina berths, yacht access, and direct waterfront connectivity between Dubai Marina and Palm Jumeirah, presented by Tohid Fetrat

Emaar Beachfront: A Private-Beach Island Community Inside Dubai Harbour

Emaar Beachfront holds 27 residential towers and around 10,000 homes along a private beachfront, with two marinas, retail and dining.

Explore the Emaar Beachfront Community
Emaar Properties developer showcasing Downtown Dubai skyline with Burj Khalifa and surrounding residential and commercial towers at dusk Presented by Tohid Fetrat

Emaar Properties: Burj Khalifa, Downtown Dubai and Twenty Master Communities

Emaar, founded in 1997, built Burj Khalifa and Downtown Dubai and has delivered over 85,000 homes across twenty master communities.

View the Emaar Properties Developer Profile

Construction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.

FAQs

Beach Isle at Emaar Beachfront Construction Updates Frequently Asked Questions

The Dubai Land Department carries Beach Isle at Emaar Beachfront as project 2207 with the status Finished, 397 units and 45,359.16 sq m on the record. Construction progress reached 100% at the inspection of 02 May 2023, and the readings behind that entry are set out in the inspection timeline above.

Construction started on 30 April 2020 and the 100% reading was recorded on 02 May 2023, a span of three years and two days. Averaged across that programme the build ran at about 2.8 percentage points per month, which is the only pace figure this record supports, and the working is shown in the pace analysis above.

Every percentage on this page comes from the RERA Independent Progress Monitoring Report filed against project 2207 and published in the Dubai Land Department application, not from a developer estimate. The Beach Isle figure of 100% is dated 02 May 2023 and carries the RERA Progress Status Completed. How readings are sourced for every project on this site is explained on the Dubai Construction Updates hub.

Independent monitoring reports stop once a project is marked Completed, and Beach Isle at Emaar Beachfront reached that point at its 02 May 2023 inspection. The application preserves one earlier figure, a previous inspection reading of 86.17%, but it carries no date, so the 100% report is the only dated inspection in this record.

The registered description for project 2207 covers residential and retail space plus a district cooling plant, delivered as Building 1 at 23 floors with roof and upper roof, Building 2 at 16 floors with roof and upper roof, and a shared podium of one basement, ground, mezzanine, four parking levels and one further level. All 397 units sit inside that structure on plot 3651 in Marsa Dubai.

The record is closed, so there is no further inspection pending: project 2207 reads Finished with 100% recorded on 02 May 2023. The dated report behind that figure is published in full on the Beach Isle May 2023 construction update, and this page is revised whenever the Dubai Land Department entry for project 2207 changes.

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is keeping the Beach Isle at Emaar Beachfront construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.