Imtiaz Developments · Island A, Dubai Islands · Construction Update

Beach Walk Residence Construction Update - May 2026

May 2026 Inspection Records Beach Walk Residence at 100% in the DLD Register on Island A

Civil defence, LPG and Trakhees completion approvals were already issued when RERA inspected Beach Walk Residence on 18 May 2026 and set its progress status to Completed.

Direct advisor access. Every message answered personally, never by a call center.

100%DLD Register Reading
18 May 2026Inspection Date
ReadyHandover Status
3162DLD Project Number

DLD Register Inspection Data

Beach Walk Residence Construction Snapshot

A 6.07 point rise on the previous DLD register reading of 93.93%, a reading the register shows without a date, brings Beach Walk Residence to 100% on 18 May 2026: the top band, where attention moves from building progress to completion paperwork, snagging and keys.

Project Name

Beach Walk Residence by Imtiaz

Project Number

3162

Project Status

Finished

Construction Progress

100%

Inspection Date

18 May 2026

Construction Start

01 June 2024

Total Units

80 Residences

Total Built Area

8,402.73 sq m

Expected Completion

01 June 2026

Data source: RERA inspection conducted on 18 May 2026 (progress status Completed) and the Dubai Land Department project register for project 3162, which carries the 100% and 93.93% readings; the inspection report itself prints no percentage. The image at the top of this page is a developer rendering, not a site photograph. Construction tracking against RERA inspection data runs across the full tohidfetrat.com project portfolio and is reviewed after every published cycle. Last updated: May 2026.

Want to hear if this record changes? Message me on WhatsApp and I will send any register update to you directly: one message per change, nothing else. Message me on WhatsApp

This Inspection Cycle

Beach Walk Residence Construction Progress Summary

Between the undated 93.93% reading and the 18 May 2026 inspection, the record for Beach Walk Residence moved from construction to completion: the RERA report found all building construction activities substantially completed across the G+2P+12+R building, with DEWA services in place, and the DLD register now lists the project as Finished.

Completed
  • Concrete structure and blockwork across ground, two podium levels, twelve residential floors and the roof
  • Internal and external finishes, recorded as substantially completed
  • DCD approval issued 08 January 2026; LPG approval issued on 17 March 2026
  • Building Completion Certificate by Trakhees, issued 14 May 2026
  • DEWA water and electricity meters installed; AC installed and connected by DEWA
On Site at 18 May 2026
  • Snagging across the building
  • Some remaining paint work
  • Deep cleaning
Ahead of Handover
  • The developer's completion notice to each buyer
  • Settlement of the completion instalment or balance under each SPA
  • Unit inspection, key collection and title registration
Next readingNo higher progress reading follows 100%; the live DLD register is where any later status change would appear.
Registered completion date01 June 2026 in the DLD register, 14 days after the 100% reading of 18 May 2026.
Recorded build span100 points over 716 days, from the 01 June 2024 construction start to 18 May 2026: about 4.19 points per month, arithmetic over the recorded build, not a forecast.

Payment Linked Progress

What 100% Progress Means for Beach Walk Residence Buyers

Under the original 60/40 launch payment plan, 60% was scheduled during construction and 40% on completion, so a DLD register reading of 100% on 18 May 2026 means buyers on that plan have reached the completion instalment stage, while anyone buying one of the remaining units is buying a finished building. Four actions matter most now.

Before Any Completion Payment

Verify the escrow account

The 40% completion instalment under the launch plan is paid into the project escrow account per the SPA, so confirm the details with the developer and against the register first: search project 3162, registered as Beach Walk Residences 1, on Dubai REST. Beach Walk Residence escrow account verification walks through it; the lookup itself takes about two minutes against the official DLD project record.

Before the Completion Notice

Reread your SPA completion clauses

Look at how your sale and purchase agreement words the completion notice, the final instalment and the start of service charges, and map those clauses against the 14 May 2026 Building Completion Certificate. Not sure how your instalments map to this reading? Send me your SPA schedule and I will map it against the recorded milestones.

Window Open Now

Book the snagging inspection

A furnished, completed apartment is inspected as delivered, custom furniture included, so the inspection belongs before you accept the unit and sign the handover documents. Beach Walk Residence snagging inspection guide covers what to check in this building and when to book.

Through to Title

Follow the record to your title deed

After 100%, the remaining milestones are paperwork: the developer's completion notice, final settlement, keys and title registration. Beach Walk Residence construction updates hub keeps the full register record in one place.

General framework, not legal advice: completion notice periods, final instalment terms, and fee obligations are set by your individual SPA and the DLD record, and both should be read directly.

Buying at 100%?

Buying into a building that is already complete trades the launch plan's long payment runway for certainty: construction is recorded at 100%, the completion certificate is issued, and the choice comes down to which of the remaining units suits you. Payments under the launch plan went to the DLD-registered escrow account for project 3162 with First Abu Dhabi Bank, released against RERA-verified construction milestones; terms for the remaining units are confirmed with the developer at reservation.

Entering Now at 100%
  • Construction recorded at 100% in the DLD register on 18 May 2026
  • Building Completion Certificate issued by Trakhees on 14 May 2026
  • A furnished unit that can be viewed and snagged as delivered
Typical Launch Entry
  • Building risk carried from groundwork through to completion
  • Several years between booking and keys, judged from renderings
  • A longer instalment schedule set at launch pricing
AED 1.65M ≈ USD 449KStarting Price
80 ResidencesTotal in the Building
ReadyHandover Status
Ask What Is Available at Beach Walk Residence

Limited units available per the project page as of this update; availability can change at any time.

About the Development

Beach Walk Residence Project Details

Beach Walk Residence by Imtiaz in Island A, Dubai Islands aerial rendering of a residential building with planted balconies and a landscaped rooftop garden in Dubai - Presented by Tohid Fetrat
Island A · Imtiaz Developments

With construction recorded at 100% and the Building Completion Certificate issued on 14 May 2026, Beach Walk Residence is a finished G+2P+12+R building on Island A whose 80 residences, studios through 2 bedroom apartments, are sold furnished. Starting prices: AED 1.65M ≈ USD 449K.

At this stage the trade off is a shorter wait and a unit you can inspect against the long runway of the original launch plan; handover status is Ready, and terms for the remaining units are confirmed with the developer at reservation.

Beach Walk Residence by Imtiaz Project Guide

Site Context This Cycle

Explore Beach Walk Residence Location on Dubai Map

Beach Walk Residence stands on Island A within what the developer describes as a five minute walk of the beach, and its brochure maps sunrise over the east side of the building and sunset over the west. With construction recorded as complete in May 2026, that exposure matters less for site works than for buyers comparing units: west facing balconies and glazing take the afternoon sun, which is where cooling and sealing are worth checking at handover.

Dubai Islands is planned as a long-term destination, which the developer's brochure frames around 86 resorts and hotels and two golf courses aligned with Dubai's 2040 vision, but the mainland is already close: the brochure puts the Infinity Bridge 5 minutes and Dubai International Airport 12 minutes away by car. For buyers of a finished unit, that means mainland services are within reach from the day of handover, whatever pace the wider island plan takes. See the project's position on the interactive Dubai real estate map. See the project’s position on the interactive Dubai real estate map.

Interactive Dubai real estate map preview
Click to view Beach Walk Residence on Dubai Map

Buyer Resources for This Project

Investing in Beach Walk Residence at Construction Completion

At completion, residency planning, the final escrow payment, and snagging all arrive at once. Each resource below is matched to where Beach Walk Residence stands after the May 2026 inspection.

Beach Walk Residence by Imtiaz in Island A, Dubai Islands construction updates cover image featuring two project renderings of a residential tower with landscaped surroundings in Dubai - Presented by Tohid Fetrat
You Are Here

Beach Walk Residence Construction Updates

This page: the 18 May 2026 inspection record for Beach Walk Residence at 100% completion.

Beach Walk Residence by Imtiaz in Island A, Dubai Islands Golden Visa concept graphic showing a gold visa card beside a residential tower rendering in Dubai - Presented by Tohid Fetrat

Beach Walk Residence Golden Visa: Three Tiers, Three Positions

Beach Walk Residence, Imtiaz's 80 furnished apartments, qualifies at 2 bedrooms; 1 bedrooms only on a qualifying title deed value.

Read Beach Walk Residence Golden Visa Guide
Beach Walk Residence by Imtiaz in Island A, Dubai Islands escrow account concept graphic with a shield and padlock over a rendering of curved balconies and landscaped areas in Dubai - Presented by Tohid Fetrat

Beach Walk Residence Escrow: Imtiaz's Island A Account at 100%

Imtiaz's Beach Walk Residence read 100% certified May 2026; DLD project 3162 escrowed 76 units at First Abu Dhabi Bank.

Verify Beach Walk Residence Escrow Account
Beach Walk Residence by Imtiaz in Island A, Dubai Islands snagging inspection cover graphic showing a furnished living room with glazing and a balcony in Dubai - Presented by Tohid Fetrat

Beach Walk Residence Snagging for Furnished Studios and Apartments

Beach Walk Residence is an Imtiaz Developments building on Island A at Dubai Islands, with 80 fully furnished studios and apartments.

Book Beach Walk Residence Snagging

Update Timeline

Other Beach Walk Residence Construction Updates

May 2026 is the only monthly record for Beach Walk Residence and the one that carries the 100% reading; the hub holds the full register history from construction start to completion.

All Beach Walk Residence Construction Updates

FAQs

Beach Walk Residence Construction Progress in May 2026: Frequently Asked Questions

As of the RERA inspection on 18 May 2026, the Dubai Land Department project register shows Beach Walk Residence, project 3162, at 100%, with the project status Finished and the inspection report's progress status Completed. The register's previous reading was 93.93%, shown without the date of that earlier inspection.

The construction record itself closes at 100%, and the Building Completion Certificate issued by Trakhees on 14 May 2026 is a dated approval rather than a projection. Register fields such as the project status and the registered completion date of 01 June 2026 can still be amended by the Dubai Land Department, so the live record for project 3162 on Dubai REST is the reference for anything after 18 May 2026.

The report found all building construction activities substantially completed. It records Dubai Civil Defence (DCD) approval issued on 08 January 2026, LPG approval issued on 17 March 2026 and the Building Completion Certificate issued by Trakhees on 14 May 2026, with all DEWA water and electricity meters installed and air conditioning installed and connected by DEWA. Snagging, some paint work and deep cleaning were still progressing at site on the inspection date.

It shows the building was already in its final stretch at the inspection before May 2026, but the register gives no date for that reading, so the time taken to move from 93.93% to 100% cannot be measured. The dated construction record for the project, from its 01 June 2024 start, is kept on the Beach Walk Residence construction updates hub.

The Dubai Land Department register records construction as started on 01 June 2024 and the project as registered on 25 July 2024, 54 days later. Both dates appear here exactly as recorded for project 3162, and the same entries show for anyone checking the project on Dubai REST.

No. It is a developer rendering of the rooftop pool and curved terraces, used to illustrate the project, not a photograph of the site or of the completed building. The register for project 3162 carries its own inspection photographs; they are not reproduced on this page, so the finished condition of any specific unit is best confirmed at a viewing or during snagging.

A Question the FAQ Can Not Answer?

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is helping you read the May 2026 inspection record for Beach Walk Residence correctly before your next payment decision. Client identities and transactions are never published or referenced. Message me directly: you will always reach me personally, never a call center or sales team.

Ask your question, get your answer. No obligation and no follow-up unless you ask for it.

Get Progress Alerts