Imtiaz Developments · Island A, Dubai Islands
Beach Walk Residence Construction Updates
The Recorded Build of an 80-Residence Island A Building, June 2024 to May 2026
Beach Walk Residence reached 100% in the DLD register at its 18 May 2026 inspection, completing the Island A building whose construction started in June 2024.
Construction tracking against RERA inspection data, updated after every recorded inspection.
Direct advisor access. Every message answered personally, never by a call center.
Construction Snapshot
Beach Walk Residence at a Glance
Beach Walk Residence is Imtiaz Developments' 80-residence building on Island A at Dubai Islands, a single G+2P+12+R block of ground floor, two podium parking levels, twelve residential floors and a roof. Its register dates frame a compact record: construction started on 01 June 2024, the project was registered on 25 July 2024, and the inspection of 18 May 2026 put it at 100%. With one building and a single dated reading, this page reads less like a progress chart than a completion file, and the six cards below are its anchors.
3162
Finished
01 June 2024
80 residences
8,402.73 sq m
01 June 2026 (DLD)
Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.
Inspection Record
Beach Walk Residence Construction Update Timeline
Only one of the two readings the register holds for Beach Walk Residence carries a date. The previous inspection stands at 93.93% with no date shown; the current entry, dated 18 May 2026, reads 100%, four days after Trakhees issued the Building Completion Certificate on 14 May 2026. The track plots both readings from the June 2024 construction start, and the table keeps the single dated row, linked to its full monthly update.
| Inspection Month | Construction Progress | Inspection Date | Full Update |
|---|---|---|---|
| May 2026 | 100% | 18 May 2026 | View the May 2026 update |
Pace Analysis
How Fast Beach Walk Residence Has Been Built
A single dated reading leaves no inspection-to-inspection velocity to compute for Beach Walk Residence, so the figures below rest on the whole build span and the dated approval sequence instead:
- 01 Jun 2024 to 18 May 2026: whole build, construction start to 100%, arithmetic not a forecastAbout 4.19 points per month
- Previous reading 93.93%, date not shown, to 100% on 18 May 2026Pace not measurable
- 08 Jan 2026 to 14 May 2026: civil defence, LPG and completion certificate approvalsThree approvals in 126 days
The shape of this record is a point, not a curve. The register places Beach Walk Residence at 100% on 18 May 2026 and shows the earlier 93.93% without a date, so the final stretch cannot be converted into a monthly rate. The approvals give the clearer sequence: civil defence approval on 08 January 2026, LPG approval on 17 March 2026, and the Trakhees completion certificate on 14 May 2026, four days before the inspection that recorded 100%. Over the full span from the 01 June 2024 start, 100 points across 716 days averages about 4.19 points per month, a piece of arithmetic, not a forecast. For an end user, that means construction risk is no longer the question at this twelve-floor building; snagging, settlement and title are. For an investor, the record documents a G+2P+12+R building carried from start to completion approvals within 716 days, with the registered completion date of 01 June 2026 falling 14 days after the 100% reading.
Get the Next Inspection Figure First
Tell me you are tracking Beach Walk Residence and I will send you the next recorded figure and site photos directly, ahead of the page update.
Get the Next Update on WhatsAppProject Profile
About Beach Walk Residence at Island A
A 100% reading says the building is finished; the project guide says what was finished, and what a buyer gets inside it:

Beach Walk Residence: A Furnished G+2P+12+R Building on Island A
Beach Walk Residence is an Imtiaz building of 80 studios and apartments, sold fully furnished with custom furniture on Island A.
View the Beach Walk Residence Project GuideConsidering a Ready Unit?
Beach Walk Residence is complete and listed with limited units available, so buying here now means choosing between specific finished apartments rather than a launch allocation. If this record is what brought you here, ask me which units remain and the terms the developer confirms at reservation.
Ask About Remaining Availability on WhatsAppStage Record
Beach Walk Residence Build Stages, Mapped to the Inspections
Beach Walk Residence has one dated inspection, so the five stages below are anchored to register dates and to the approvals in the 18 May 2026 inspection report rather than to a run of readings; windows without a dated reading say so.
Construction Start and Registration
Work on site predates the paperwork here: a 01 June 2024 start, then DLD registration of project 3162 on 25 July 2024, both dates shown as the register holds them.
Ground and Podium Levels
This window covers the ground floor and two podium parking levels of the G+2P+12+R design; the register shows no dated percentage for it, so none is attached.
Twelve Residential Floors and Roof
Concrete structure and blockwork across the twelve residential floors and roof level, recorded as complete in the 18 May 2026 report; no dated reading marks the interim.
Services, Finishes and Approvals
Civil defence approval on 08 January 2026 and LPG approval on 17 March 2026; by 18 May 2026 DEWA meters were installed and AC connected. The previous 93.93% reading is undated, so it is not placed here.
Completion and Handover Preparation
Trakhees issued the Building Completion Certificate on 14 May 2026, and the 18 May 2026 inspection recorded 100% with progress status Completed; unit handover follows each buyer's completion notice.
What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Beach Walk Residence's own record.
Buyer Position
Tracking Your Position at Beach Walk Residence
This page is one of four project resources that together cover a Beach Walk Residence purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Beach Walk Residence Construction Updates
This page: the DLD register record for Beach Walk Residence, from June 2024 start to 100%.

Beach Walk Residence Golden Visa: Three Tiers, Three Positions
Beach Walk Residence, Imtiaz's 80 furnished apartments, qualifies at 2 bedrooms; 1 bedrooms only on a qualifying title deed value.
Read the Beach Walk Residence Golden Visa Guide
Beach Walk Residence Escrow: Imtiaz's Island A Account at 100%
Imtiaz's Beach Walk Residence read 100% certified May 2026; DLD project 3162 escrowed 76 units at First Abu Dhabi Bank.
Verify the Beach Walk Residence Escrow Account
Beach Walk Residence Snagging for Furnished Studios and Apartments
Beach Walk Residence is an Imtiaz Developments building on Island A at Dubai Islands, with 80 fully furnished studios and apartments.
Book Beach Walk Residence SnaggingApproaching Handover
Between 100% and Handover: What Beach Walk Residence Buyers Should Do Now
At Beach Walk Residence the percentage has nothing left to climb: the 18 May 2026 inspection recorded 100% and the completion certificate was issued four days earlier, so what stands between a buyer and the keys is paperwork and inspection, not building work. Completion notices typically give buyers a short window to settle and attend their handover appointment, so the three steps below are worth doing before that notice arrives, not after.
First, arrange an independent inspection of your furnished apartment, custom furniture included, before you sign for it; the Beach Walk Residence snagging page sets out the timing and what gets checked.
Second, confirm where the launch plan's 40% completion instalment goes: per the SPA it is paid into the project escrow account, so check it with the developer and on the Beach Walk Residence escrow account page, which shows how to verify the First Abu Dhabi Bank account for project 3162.
Third, if you hold a 1 or 2 bedroom unit and want residency, line up eligibility with the title deed issue; the Beach Walk Residence Golden Visa guide explains why a 1 bedroom qualifies only if its deed value reaches AED 2,000,000.
Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.
The Wider Picture
Explore Island A Structure
A single completed building is only part of what is taking shape on Island A. These three pages set the Beach Walk Residence record beside the island's other stock, its masterplan and the developer behind it:

Island A: Four Imtiaz Projects, From Furnished Apartments to Marina-Front Penthouses
Island A is the urban waterfront core of Dubai Islands, with furnished apartments, duplexes and penthouses across four Imtiaz projects.
See Island A Properties for Sale
Island A Community Overview
Read the full Island A guide: the island's role in the Dubai Islands masterplan, property types, connectivity and pricing.
Explore the Island A Community
Imtiaz Developments: Fully Furnished Residences in Dubai Islands, JVC and Meydan
Imtiaz Developments, founded in 2011, has completed and under-construction design led residential projects in Meydan, JVC and Dubai Islands.
View the Imtiaz Developments Developer ProfileConstruction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.
FAQs
Beach Walk Residence Construction Updates Frequently Asked Questions
The Beach Walk Residence construction record has reached its end point: the Dubai Land Department register shows project 3162 at 100% as of the inspection of 18 May 2026, with the project status Finished, and the RERA inspection report of that date gives the progress status Completed. Trakhees issued the Building Completion Certificate on 14 May 2026. Each entry behind that status is laid out in the inspection timeline above.
Progress at Beach Walk Residence rose 6.07 points between its last two DLD register readings, from a previous 93.93% to 100% at the inspection of 18 May 2026. The register shows no date for the 93.93% reading, so the time between the two, and any monthly pace, cannot be calculated. The dated reading is covered in the Beach Walk Residence May 2026 construction update.
The DLD register gives Beach Walk Residence, project 3162, a registered completion date of 01 June 2026 and records 100% progress at the inspection of 18 May 2026, 14 days before that date. The registered date is an administrative register entry rather than a handover date: the project's handover status is Ready, individual unit handover follows the developer's completion notice to each buyer, and this page's record is updated if the register changes.
Beach Walk Residence has 80 residences, made up of studio, 1 bedroom and 2 bedroom apartments that the developer's brochure describes as fully furnished, all in the one building recorded at 100% on 18 May 2026. Prices, sizes and layouts are in the Beach Walk Residence by Imtiaz project guide.
Construction at Beach Walk Residence ran 716 days, from the 01 June 2024 start recorded in the DLD register to the 100% reading of 18 May 2026, or about 23.9 months on a 30-day month. Spread over that span, 100 points average about 4.19 points per month; that is plain arithmetic, not a measured pace between inspections or a forecast, because the register shows only one dated reading. The breakdown is in the pace analysis above.
Construction at Beach Walk Residence, project 3162, was tracked through two records: the Dubai Land Department project register, which carries the readings of 93.93% (undated) and 100% (18 May 2026), and the RERA inspection report of 18 May 2026, which records the progress status Completed but prints no percentage of its own. The general method is described on the Dubai Construction Updates hub.

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is keeping the Beach Walk Residence construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.
Ask your question, get your answer. No obligation and no follow-up unless you ask for it.