Binghatti Amberhall by Binghatti in Jumeirah Village Circle construction updates cover image featuring a project rendering of an illuminated residential building facade at dusk in Dubai - Presented by Tohid Fetrat

Binghatti · Jumeirah Village Circle

Binghatti Amberhall Construction Updates

The Dated Register Record of a Mixed-Use JVC Building

Binghatti Amberhall read 38.03% in the DLD register on 30 April 2026, a climb since February 2025 with frame, services and envelope advancing in parallel in JVC.

Construction tracking against RERA inspection data, updated after every recorded inspection.

Direct advisor access. Every message answered personally, never by a call center.

38.03%Construction Progress
30 April 2026Latest RERA Inspection
630 residential unitsTotal Units
Project 3552DLD Registration

Construction Snapshot

Binghatti Amberhall at a Glance

Binghatti Amberhall is Binghatti's 630-residence building in Jumeirah Village Circle, a single mixed-use block that pairs studio to 2 bedroom apartments with office units and shops at street level. The DLD register logged its construction start on 15 February 2025, sixteen days before project 3552 was registered on 3 March 2025, and read 38.03% on 30 April 2026, so the whole record so far fits inside fifteen months. Those register anchors, not the developer's renderings, are what this page measures the building against.

DLD Project Number

3552

Project Status

Active

Construction Start

15 February 2025

Total Units

630 residential units

Total Built-Up Area

83,445.04 sq m

Registered Completion Date

28 February 2026

Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.

Inspection Record

Binghatti Amberhall Construction Update Timeline

One dated reading anchors the Binghatti Amberhall record so far: 38.03% in the DLD register on 30 April 2026, 439 days after the February 2025 start. The register pairs it with a previous-inspection field of 0% that carries no date, so the track below shows that undated starting reference as a dot without a month, and the table holds a single row linking the April 2026 update with the full RERA notes.

Inspection MonthConstruction ProgressInspection DateFull Update
April 202638.03%30 April 2026View the April 2026 update
!

Reading the dates: the registered completion date for project 3552 in the DLD record is 28 February 2026, and that date has passed; the register reading of 38.03% followed on 30 April 2026, 61 days later. The handover target stated for Binghatti Amberhall is Q4 2026, so confirm the current completion date with Binghatti and on Dubai REST before relying on either date.

Pace Analysis

How Fast Binghatti Amberhall Has Been Built

A measured pace needs two dated readings, and the Binghatti Amberhall register holds one so far. What the record does support is shown below, each figure labelled for what it is:

  • 15 Feb 2025 start to 30 Apr 2026: enabling, foundations and early frame, 0% to 38.03% (arithmetic, not a forecast)About 2.60 points per month
  • Undated previous field to 30 Apr 2026: 0% to 38.03%, no start date for the spanNo measured pace yet

With one dated point, Binghatti Amberhall has no curve yet, only a straight-line average from its recorded start, and that average hides how the work is actually laid out. The RERA report of 30 April 2026 has enabling and foundation works completed while the frame, internal works, finishes, MEP and envelope packages all advance at once, a building running its trades side by side rather than floor by floor. The 61.97 points between that reading and 100% sit against a Q4 2026 handover target, so the next dated reading is what turns this single point into a measured pace: for an end user it frames the move-in timeline, and for an investor it shows whether the 50% construction share is falling due against progress the register can see.

Get the Next Inspection Figure First

Tell me you are tracking Binghatti Amberhall and I will send you the next recorded figure and site photos directly, ahead of the page update.

Get the Next Update on WhatsApp

Project Profile

About Binghatti Amberhall at JVC

The 38.03% recorded on 30 April 2026 only means something next to what is being delivered. The project guide covers the building this record is tracking toward:

Binghatti Amberhall by Binghatti in Jumeirah Village Circle project rendering of a multistorey residential building with balconies and landscaped grounds in Dubai - Presented by Tohid Fetrat

Binghatti Amberhall: Homes and Offices in One JVC Building

Binghatti Amberhall is a mixed-use Binghatti building in Jumeirah Village Circle, 630 residences from studios to two bedrooms beside office units.

View the Binghatti Amberhall Project Guide

Considering a Mid-Construction Entry?

Units at Binghatti Amberhall are listed as limited, and a purchase made mid-build can bring part of the 50% construction share due at signing. If the record on this page is what brought you here, ask me what is currently available and how the payment schedule applies to a unit bought now.

Ask About Remaining Availability on WhatsApp

Stage Record

Binghatti Amberhall Build Stages, Mapped to the Inspections

Rather than a generic sequence, each stage below is placed where the Binghatti Amberhall record actually puts it: the 15 February 2025 start, the single 38.03% register reading of 30 April 2026, and the RERA notes filed with it, so completed, current and remaining work sit in their true order.

From 15 Feb 2025

Site Activation and Enabling Works

Construction was recorded as started on 15 February 2025, before the 3 March 2025 registration of project 3552; the RERA report of 30 April 2026 lists enabling works completed.

Feb 2025 to Apr 2026

Foundations and Basement Levels

Foundation works are logged as completed in the 30 April 2026 RERA report; the record gives no separate date for when they closed out beneath the building.

Current Phase38.03% at 30 Apr 2026

Substructure and Superstructure

Substructure and superstructure works were progressing at the 30 April 2026 inspection, the stage in which the DLD register read 38.03% for project 3552.

Already under way at 30 Apr 2026

MEP, Envelope and Interiors

MEP, internal works, internal finishes, and external and envelope packages were all logged as progressing on 30 April 2026, alongside the frame rather than after it.

Ahead, Q4 2026 target

Completion and Handover

61.97 points remain after the 30 April 2026 reading, covering the fit-out of every residence, office unit and shop in the building toward the Q4 2026 handover target.

What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Binghatti Amberhall's own record.

Buyer Position

Tracking Your Position at Binghatti Amberhall

This page is one of four project resources that together cover a Binghatti Amberhall purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Binghatti Amberhall by Binghatti in Jumeirah Village Circle construction updates cover image featuring a project rendering of an illuminated residential building facade at dusk in Dubai - Presented by Tohid Fetrat
You Are Here

Binghatti Amberhall Construction Updates

This page: the dated DLD register record for Binghatti Amberhall, from February 2025 groundbreaking to handover.

Binghatti Amberhall by Binghatti in Jumeirah Village Circle Golden Visa concept graphic with a gold card over a rendering of residential towers at dusk in Dubai - Presented by Tohid Fetrat

Binghatti Amberhall Golden Visa: A Mixed-Use Jumeirah Village Circle Building

Binghatti Amberhall is a freehold mixed-use Binghatti building of 630 residences in Jumeirah Village Circle, under Oqood registration.

Read the Binghatti Amberhall Golden Visa Guide
Binghatti Amberhall by Binghatti in Jumeirah Village Circle escrow account concept graphic with a shield and padlock over a rendered landscaped courtyard in Dubai - Presented by Tohid Fetrat

Binghatti Amberhall Escrow: A United Arab Bank Account in JVC

Binghatti Amberhall, DLD project 3552 in JVC, holds 710 units' instalments at United Arab Bank, 38.03% certified in April 2026.

Verify the Binghatti Amberhall Escrow Account

Approaching Handover

Between 38.03% and Handover: What Binghatti Amberhall Buyers Should Do Now

At 38.03% on 30 April 2026, Binghatti Amberhall sits inside the 50% construction share of its 20/50/30 plan, so the buyer work right now is payment discipline rather than handover logistics. For anyone entering now, installments already falling due may be payable at signing under the developer's current terms, so the three steps below come before the next transfer, not after it.

First, before any construction installment leaves your account, confirm it is going to the project 3552 trust account at United Arab Bank; the Binghatti Amberhall escrow account page shows how to check it against the DLD record.

Second, if residency is part of the plan, settle eligibility early through the Binghatti Amberhall Golden Visa eligibility guide: the 2 bedroom tier at AED 2.58M ≈ USD 702K meets the property value on price, and the guide sets out how an off plan purchase is treated.

Third, keep the unit types, the 20/50/30 plan and the Q4 2026 handover target in view on the Binghatti Amberhall project page, so each new reading can be checked against your own unit and payment dates.

Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.

The Wider Picture

Explore JVC Structure

One building at 38.03% on 30 April 2026 is rising inside a community that is already lived in. These three pages place the Binghatti Amberhall record in its market, community and developer context:

Aerial view of Jumeirah Village Circle properties for sale in Dubai showing residential homes, landscaped greenery and the circular community layout, Presented by Tohid Fetrat

Jumeirah Village Circle: Five Imtiaz and Binghatti Towers in New Dubai

Jumeirah Village Circle, Nakheel's freehold ring of ten districts in New Dubai, lists apartments in five Imtiaz and Binghatti towers.

See JVC Properties for Sale
Aerial view of Jumeirah Village Circle (JVC) in Dubai showcasing circular urban planning residential villas green spaces and high-rise buildings with the Dubai skyline in the background. Presented by Tohid Fetrat.

JVC Community Overview

Read the Jumeirah Village Circle guide: Nakheel's freehold community of apartments, townhouses and villas with strong rental yields.

Explore the JVC Community
Binghatti luxury towers in Dubai – Bugatti Residences, Mercedes-Benz Places, and Skyblade by Binghatti, representing iconic branded architecture and innovation, presented by Tohid Fetrat.

Binghatti: Record Construction Speed and Branded Towers With Bugatti and Mercedes-Benz

Binghatti has delivered more than 60 projects since 2008, with 27 under development and two master communities across Dubai.

View the Binghatti Developer Profile

Construction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.

FAQs

Binghatti Amberhall Construction Updates Frequently Asked Questions

Binghatti Amberhall is an active DLD-registered project, number 3552, in its substructure and superstructure stage, with the DLD register reading 38.03% on 30 April 2026 and the RERA report of the same date listing its status as Main Contract, Progressing. Readings post after each RERA site visit, so a newer figure for project 3552 may already be live on Dubai REST; every dated reading on record is in the inspection timeline above.

The 30 April 2026 reading of 38.03% sits 38.03 points above the previous inspection field of 0% in the DLD record. That previous field carries no date, so the rise cannot be spread over a known period or turned into a monthly pace; the April record and the RERA notes filed with it are in the Binghatti Amberhall April 2026 construction update.

The registered completion date for Binghatti Amberhall in the DLD record is 28 February 2026, and it had passed 61 days before the 38.03% reading of 30 April 2026. The handover target stated for the project is Q4 2026, the project remains registered and Active, and the current completion date is best checked with Binghatti and on Dubai REST. This page's record is updated when the next dated reading is recorded.

Binghatti Amberhall holds 630 residences across studio, 1 bedroom and 2 bedroom apartments, in a single building that also includes office units and ground-floor retail, making it a residential, retail and commercial development. The DLD register reading of 38.03% on 30 April 2026 is recorded for project 3552 as a whole, not for one part of the building.

As arithmetic, not a forecast: the 38.03 points recorded over the 439 days from the 15 February 2025 construction start to the 30 April 2026 reading average about 2.60 points per month on a 30-day month. No inspection-to-inspection pace exists yet, because the only earlier figure is an undated 0% field; the first measured pace arrives with the next dated reading. The workings are in the pace analysis above.

After the 30 April 2026 reading of 38.03%, 61.97 points remain to 100%. The RERA report of that date had enabling and foundation works completed, so what is left is carrying the substructure and superstructure, internal works and finishes, MEP systems and the external envelope through to completion, then fitting out the 630 residences alongside the office and retail space toward the Q4 2026 handover target.

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is keeping the Binghatti Amberhall construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.

Ask your question, get your answer. No obligation and no follow-up unless you ask for it.

WhatsApp +971543443597
Get the Latest Status