Binghatti Circle Construction Updates
The Dated Register Record of One Mixed-Use Tower in JVC
Binghatti Circle reached 10.33% on the DLD register at the 30 April 2026 inspection, a first dated reading from a record that begins below ground in JVC.
Construction tracking against RERA inspection data, updated after every recorded inspection.
Direct advisor access. Every message answered personally, never by a call center.
Construction Snapshot
Binghatti Circle at a Glance
Binghatti Circle is Binghatti's 776-residence mixed-use tower in Jumeirah Village Circle, registered with the Dubai Land Department as project 3819 and recorded at 10.33% on 30 April 2026. The developer fact sheet and the RERA report of that date both describe two basement levels, a ground floor, four podium levels and 58 floors above, set on a compact plot of 6,421.58 sq m (69,121 sq ft) per the fact sheet, so the opening months of this record are spent largely below ground. The cards below are the register anchors under every figure on this page.
3819
Active
01 June 2025
776 residential units
52,186.26 sq m
31 May 2027 (DLD)
Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.
Inspection Record
Binghatti Circle Construction Update Timeline
One dated reading anchors the Binghatti Circle record so far: 10.33% on the DLD register at the RERA inspection of 30 April 2026, 333 days after the recorded 01 June 2025 start. The register's previous inspection field shows 0%, undated, so it sits on the track below as a baseline dot with no month and takes no table row. The single row links the full April 2026 update.
| Inspection Month | Construction Progress | Inspection Date | Full Update |
|---|---|---|---|
| April 2026 | 10.33% | 30 April 2026 | View the April 2026 update |
Pace Analysis
How Fast Binghatti Circle Has Been Built
With one dated reading on the register, the pace at Binghatti Circle can be read two ways: the average since construction started, and the rate the remaining distance implies. All three figures are arithmetic on a 30-day month, not a forecast:
- 01 Jun 2025 to 30 Apr 2026: enabling and substructure phase, 0% to 10.33% over 333 daysAbout 0.93 points per month
- 30 Apr 2026 to 31 May 2027 registered completion: structure, facade and fit-out, 10.33% to 100% over 396 daysAbout 6.79 points per month
- 30 Apr 2026 to the end of the Q2 2027 handover quarter: same remaining 89.67 points over 426 daysAbout 6.31 points per month
Read together, the three figures describe a curve that has not yet turned upward. The first 333 days on record went into mobilisation, enabling works and two basement levels on a compact JVC plot, work that adds little to a register percentage because nothing yet rises above ground level. The two required rates assume the build steepens once the four podium levels and 58 floors begin to stack, the sequence a tower of this configuration usually follows; whether it does is something only the next dated readings can show. For an end user holding a Q2 2027 handover expectation, the reading after 30 April 2026 matters most, because it gives the first measured pace between two dated inspections. For an investor, the distance between about 0.93 and about 6.79 points per month is the one number worth following through 2026 and 2027.
Get the Next Inspection Figure First
Tell me you are tracking Binghatti Circle and I will send you the next recorded figure and site photos directly, ahead of the page update.
Get the Next Update on WhatsAppProject Profile
About Binghatti Circle at JVC
A percentage only means something next to what is being built. The project guide covers what the record on this page is tracking toward:

Binghatti Circle: A Mixed-Use Tower of 58 Floors in JVC
Binghatti Circle is a Binghatti tower in Jumeirah Village Circle with 776 studio to three bedroom apartments beside offices and shops.
View the Binghatti Circle Project GuideConsidering an Early-Stage Entry?
Units at Binghatti Circle are limited, and the choice of layouts and floors narrows as construction moves on. If the record on this page is what brought you here, ask me what is available now before you compare further.
Ask About Remaining Availability on WhatsAppStage Record
Binghatti Circle Build Stages, Mapped to the Inspections
Each stage below is pinned to the window it occupies in the Binghatti Circle record. With one dated reading at 10.33% on 30 April 2026, two stages carry register dates and three still lie ahead of the next readings.
Construction Start and DLD Registration
The register records construction as started on 01 June 2025 and project 3819 as registered on 22 July 2025, 51 days later, with its trust account at Dubai Islamic Bank.
Enabling, Foundations and Substructure
The RERA report of 30 April 2026 lists mobilisation, enabling, foundation and substructure works as ongoing for the two basement levels, with the register at 10.33% that day.
Podium and Tower Structure
Superstructure works were already listed as ongoing on 30 April 2026; this stage carries the four podium levels and the 58 floors upward.
Facade, MEP and Residence Fit-Out
Enclosure, building services and interior fit-out for 776 residences, the offices and the ground-floor shops; MEP works had begun by 30 April 2026.
Finishing, Commissioning and Handover
Final finishes, systems commissioning and handover, expected in Q2 2027; the DLD registered completion date of 31 May 2027 falls inside that quarter.
What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Binghatti Circle's own record.
Buyer Position
Tracking Your Position at Binghatti Circle
This page is one of four project resources that together cover a Binghatti Circle purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Binghatti Circle Construction Updates
This page: the dated DLD register record for Binghatti Circle, from June 2025 to handover.

Binghatti Circle Golden Visa: One Tier Carries the Case
In Binghatti Circle, a 776-residence Jumeirah Village Circle tower, studio, 1 and 2 bedroom apartments sit below; the 3 bedroom qualifies.
Read the Binghatti Circle Golden Visa Guide
Binghatti Circle: The 822-Unit JVC Escrow at Dubai Islamic Bank
Binghatti Circle escrows 822 units at Dubai Islamic Bank as DLD project 3819, certified 10.33% in April 2026.
Verify the Binghatti Circle Escrow AccountApproaching Handover
Between 10.33% and Handover: What Binghatti Circle Buyers Should Do Now
At 10.33% on 30 April 2026, Binghatti Circle was still working through its basements and substructure, and the plan's 50% construction share is spread across the build ahead per the developer's schedule. Construction installments fall due while the tower rises, so the three checks below belong before the next one is paid, not after it.
First, match every installment to the Binghatti Circle escrow account page, which sets out the Dubai Islamic Bank account registered to project 3819, so each transfer goes where the register says it should.
Second, if residency is part of the plan, read the Binghatti Circle Golden Visa eligibility guide now: of the four apartment tiers, only the 3 bedroom from AED 2.30M ≈ USD 626K clears the property value threshold.
Third, keep the Binghatti Circle unit and payment plan guide beside this record, so the 20% at booking, 50% during construction and 30% on handover in Q2 2027 can be read against each new register reading.
Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.
The Wider Picture
Explore JVC Structure
A build record is half the picture; the rest is what already stands around it. These three pages set the Binghatti Circle record in its market, community, and developer context:

Jumeirah Village Circle: Five Imtiaz and Binghatti Towers in New Dubai
Jumeirah Village Circle, Nakheel's freehold ring of ten districts in New Dubai, lists apartments in five Imtiaz and Binghatti towers.
See JVC Properties for Sale
JVC Community Overview
Read the Jumeirah Village Circle guide: Nakheel's freehold community of apartments, townhouses and villas with strong rental yields.
Explore the JVC Community
Binghatti: Record Construction Speed and Branded Towers With Bugatti and Mercedes-Benz
Binghatti has delivered more than 60 projects since 2008, with 27 under development and two master communities across Dubai.
View the Binghatti Developer ProfileConstruction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.
FAQs
Binghatti Circle Construction Updates Frequently Asked Questions
Binghatti Circle is an active Dubai Land Department project, number 3819, in its enabling, foundation and substructure stage: the DLD register showed 10.33% following the RERA inspection of 30 April 2026, with the main contract recorded as progressing. The full dated record is in the Binghatti Circle inspection timeline above.
The most recent reading on record for project 3819 is 10.33%, posted after the RERA inspection of 30 April 2026. No earlier dated reading exists on the register, so no point change between two inspections can be measured yet. The inspection detail sits in the Binghatti Circle April 2026 construction update.
Handover for Binghatti Circle is expected in Q2 2027, and the DLD registered completion date of 31 May 2027 falls inside that quarter, so the two dates agree. As of the 30 April 2026 reading of 10.33%, the registered date was 396 days away and had not lapsed; any revision to it would show in a later register update and be recorded on this page.
Binghatti Circle holds 776 residences, from studio to 3 bedroom apartments, in a single mixed-use tower that also contains offices and ground-floor shops. The developer fact sheet and the RERA report of 30 April 2026 both describe two basement levels, a ground floor, four podium levels and 58 floors, plus mechanical and service levels and a roof.
Across the 333 days from the 01 June 2025 start to the 30 April 2026 reading of 10.33%, Binghatti Circle averaged about 0.93 points per month. Reaching 100% by the 31 May 2027 registered completion date works out to about 6.79 points per month over the remaining 396 days, or about 6.31 per month to the end of Q2 2027. These figures are arithmetic, not a forecast, and the Binghatti Circle pace analysis sets them out in full.
The Binghatti Circle record runs from a construction start on 01 June 2025 and DLD registration on 22 July 2025 to the first dated reading, 10.33% on 30 April 2026, with registered completion set for 31 May 2027 and handover expected in Q2 2027. Each later reading joins this sequence as it reaches the register.

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is keeping the Binghatti Circle construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.