Binghatti Etherea by Binghatti in Jumeirah Village Circle construction updates cover image featuring a project rendering of an illuminated residential tower within the surrounding urban neighborhood at dusk in Dubai - Presented by Tohid Fetrat

Binghatti · Jumeirah Village Circle

Binghatti Etherea Construction Updates

The Dated Register Record of a Jumeirah Village Circle Tower, from the Substructure Up

Binghatti Etherea reached 7.24% at the 15 September 2026 DLD register reading, the first dated figure for a JVC tower still at foundation and substructure level.

Construction tracking against RERA inspection data, updated after every recorded inspection.

Direct advisor access. Every message answered personally, never by a call center.

7.24%Construction Progress
15 September 2026Latest RERA Inspection
282 residential unitsTotal Units
Project 4303DLD Registration

Construction Snapshot

Binghatti Etherea at a Glance

Binghatti Etherea is a 282-residence apartment tower by Binghatti in Jumeirah Village Circle, entered in the Dubai Land Department register as project 4303 on 26 January 2026, with construction recorded as starting on 01 January 2026. Its record opens on a single dated reading of 7.24% on 15 September 2026, taken while enabling, foundation and substructure works were in progress, so the anchors below describe a compact-plot tower that was still working beneath its future podium when the first figure posted.

DLD Project Number

4303

Project Status

Active

Construction Start

01 January 2026

Total Units

282 residential units

Total Built-Up Area

17,566.75 sq m

Registered Completion Date

31 December 2027 (DLD)

Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.

Inspection Record

Binghatti Etherea Construction Update Timeline

The Binghatti Etherea record holds one dated reading so far: 7.24% on 15 September 2026, posted to the DLD register 257 days after the 01 January 2026 construction start. The register's previous inspection field shows 0%, undated, so it sits on the track below as a starting marker with no month and no table row. The September 2026 row links the full monthly update for that inspection.

Inspection MonthConstruction ProgressInspection DateFull Update
September 20267.24%15 September 2026View the September 2026 update

Pace Analysis

How Fast Binghatti Etherea Has Been Built

A single dated reading cannot show a velocity between inspections, so the three figures below are arithmetic from the Binghatti Etherea register dates (30-day months), not measured pace and not a forecast:

  • 01 Jan 2026 start to 15 Sep 2026 reading: enabling and substructure, 7.24 points over 257 daysAbout 0.85 points per month
  • 15 Sep 2026 to the 31 Dec 2027 registered completion date: 92.76 points over 472 daysAbout 5.90 points per month
  • 15 Sep 2026 to the end of the Q3 2027 handover target (30 Sep 2027): 92.76 points over 380 daysAbout 7.32 points per month

Etherea's record has no curve yet: it has a start date, one dated point at 7.24%, and two completion dates. The 0.85 figure averages everything from mobilisation to the September 2026 substructure work into one number, while the 5.90 and 7.32 figures are simply the remaining 92.76 points divided across the time left to each date. The next dated reading creates the first measured pair, and only then does the record show a real rate. For an end user planning around the Q3 2027 target, and for an investor timing the 50% construction share, the useful habit is to set each new reading against these three figures as it posts.

Get the Next Inspection Figure First

Tell me you are tracking Binghatti Etherea and I will send you the next recorded figure and site photos directly, ahead of the page update.

Get the Next Update on WhatsApp

Project Profile

About Binghatti Etherea at JVC

A 7.24% reading only means something next to the building it leads to. The full project guide covers the tower this record is tracking toward:

Binghatti Etherea by Binghatti in Jumeirah Village Circle project rendering of a slender illuminated residential tower viewed at night above surrounding streets in Dubai - Presented by Tohid Fetrat

Binghatti Etherea: A JVC Tower with a Podium Amenity Deck

Binghatti Etherea is a Binghatti tower in Jumeirah Village Circle of 282 studio, one and two bedroom apartments over ground-floor retail.

View the Binghatti Etherea Project Guide

Considering an Early-Stage Entry?

Availability at Binghatti Etherea shifts as the tower moves from substructure into structure. If the record on this page is what brought you here, ask me which studio, 1 bedroom and 2 bedroom units remain before the inventory narrows further.

Ask About Remaining Availability on WhatsApp

Stage Record

Binghatti Etherea Build Stages, Mapped to the Inspections

Each stage below is pinned to the window it holds in Binghatti Etherea's own register record: the 7.24% September 2026 reading sits on the stage where it was taken, and the stages above the substructure stay unrecorded until a dated reading reaches them.

Jan 2026 start, registered 26 Jan 2026

Site Mobilisation

From the 01 January 2026 construction start, with DLD registration of project 4303 following on 26 January 2026: site set-up on the Jumeirah Village Circle plot.

Current PhaseSep 2026, 7.24% at last reading

Enabling, Foundation and Substructure

The RERA report of 15 September 2026 lists enabling, foundation and substructure works in progress, with the DLD register at 7.24% on that date.

Not yet recorded

Tower Structure

Ground-floor retail, podium parking levels and the residential floors rise above the substructure; no dated reading had reached this stage by 15 September 2026.

Not yet recorded

Exoskeleton, Amenity Deck and Fit-Out

The satin chrome exoskeleton Binghatti describes for the facade, the podium-level pools and wellness zones, and the interiors of 282 apartments.

Q3 2027 target, registered 31 Dec 2027

Completion and Handover

Handover is targeted for Q3 2027, ahead of the 31 December 2027 registered completion date; 92.76 points remained after the September 2026 reading.

What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Binghatti Etherea's own record.

Buyer Position

Tracking Your Position at Binghatti Etherea

This page is one of four project resources that together cover a Binghatti Etherea purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Binghatti Etherea by Binghatti in Jumeirah Village Circle construction updates cover image featuring a project rendering of an illuminated residential tower within the surrounding urban neighborhood at dusk in Dubai - Presented by Tohid Fetrat
You Are Here

Binghatti Etherea Construction Updates

This page: the dated DLD register record for Binghatti Etherea, from its 7.24% September 2026 reading.

Binghatti Etherea by Binghatti in Jumeirah Village Circle Golden Visa concept graphic with a gold visa card over an aerial rendering of the residential tower and surrounding neighborhood in Dubai - Presented by Tohid Fetrat

Binghatti Etherea Golden Visa: Each Apartment Against the AED 2M Line

Binghatti Etherea, 282 apartments in Jumeirah Village Circle, has no type that qualifies individually; even the 2 bedroom sits below.

Read the Binghatti Etherea Golden Visa Guide
Binghatti Etherea by Binghatti in Jumeirah Village Circle escrow account concept graphic with a white shield and padlock over a night rendering of the illuminated residential tower in Dubai - Presented by Tohid Fetrat

Binghatti Etherea Escrow: Binghatti's JVC Account at Mashreq

Binghatti Etherea in JVC is DLD project 4303, 287 units in Mashreq escrow, certified 7.24% in September 2026.

Verify the Binghatti Etherea Escrow Account

Approaching Handover

Between 7.24% and Handover: What Binghatti Etherea Buyers Should Do Now

With the September 2026 reading taken during foundation and substructure work, most of the Binghatti Etherea plan's 50% construction share still lies ahead, paid across the build per the developer's schedule. That makes the checks below worth settling before the next instalment falls due, not after it has been paid.

First, confirm that every construction instalment goes to the trust account on the Binghatti Etherea escrow account page, registered at Mashreq Bank for project 4303, so your money follows recorded progress.

Second, if residency is part of your plan, read the Binghatti Etherea Golden Visa guide before committing, since at current prices no single Etherea apartment reaches the AED 2M ≈ USD 545K threshold on its own.

Third, keep the 20/50/30 structure in view: the Binghatti Etherea project page sets out the 20% at booking, the 50% across construction and the 30% due on handover against the Q3 2027 target.

Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.

The Wider Picture

Explore JVC Structure

A foundation-stage reading in one JVC tower reads differently once you see the market, community and developer around it. These three pages put Binghatti Etherea's record in context:

Aerial view of Jumeirah Village Circle properties for sale in Dubai showing residential homes, landscaped greenery and the circular community layout, Presented by Tohid Fetrat

Jumeirah Village Circle: Five Imtiaz and Binghatti Towers in New Dubai

Jumeirah Village Circle, Nakheel's freehold ring of ten districts in New Dubai, lists apartments in five Imtiaz and Binghatti towers.

See JVC Properties for Sale
Aerial view of Jumeirah Village Circle (JVC) in Dubai showcasing circular urban planning residential villas green spaces and high-rise buildings with the Dubai skyline in the background. Presented by Tohid Fetrat.

JVC Community Overview

Read the Jumeirah Village Circle guide: Nakheel's freehold community of apartments, townhouses and villas with strong rental yields.

Explore the JVC Community
Binghatti luxury towers in Dubai – Bugatti Residences, Mercedes-Benz Places, and Skyblade by Binghatti, representing iconic branded architecture and innovation, presented by Tohid Fetrat.

Binghatti: Record Construction Speed and Branded Towers With Bugatti and Mercedes-Benz

Binghatti has delivered more than 60 projects since 2008, with 27 under development and two master communities across Dubai.

View the Binghatti Developer Profile

Construction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.

FAQs

Binghatti Etherea Construction Updates Frequently Asked Questions

Binghatti Etherea, DLD project 4303, is an active project in its enabling, foundation and substructure stage according to the RERA report of 15 September 2026, with the Dubai Land Department project register reading 7.24% on that date. Work on the tower above the substructure had not entered the record by then. The dated entries are in the inspection timeline above.

One. The Binghatti Etherea record holds a single dated reading, 7.24% on 15 September 2026 in the DLD project register, so no point change between two dated inspections can be measured yet; the next posted reading will form the first measured pair. That reading and its context are covered in the September 2026 Binghatti Etherea construction update.

Progress at Binghatti Etherea is tracked through the Dubai Land Department project register for project 4303, which showed 7.24% on 15 September 2026, read alongside the RERA Independent Progress Monitoring Report of the same date. That report lists the status as Main Contract, Progressing and prints no percentage of its own, so every percentage on this page is a register reading shown with its date. The general approach is explained in the Dubai construction tracking methodology.

Binghatti Etherea's handover is targeted for Q3 2027, while 31 December 2027 is the registered completion date in the DLD record for project 4303, the regulatory deadline that sits one quarter later. The registered date has not passed, and at the 15 September 2026 register reading of 7.24% both dates lay ahead; this page's record is updated as later readings post.

From the 01 January 2026 construction start to the 15 September 2026 register reading of 7.24%, Binghatti Etherea averaged about 0.85 points per month over 257 days. Reaching 100% by the 31 December 2027 registered completion date works out to about 5.90 points per month from that reading, and by the end of Q3 2027 to about 7.32. These figures are arithmetic on 30-day months, not a forecast; the working is in the pace analysis above.

Binghatti Etherea will hold 282 residential units, all studio, 1 bedroom and 2 bedroom apartments, within one tower that adds ground-floor retail, podium parking levels and a podium-level amenity deck, on a plot of 2,321.56 sq m (24,989 sq ft) per the developer fact sheet. At the 15 September 2026 register reading of 7.24%, those levels were not yet part of the recorded works. Layouts are in the Binghatti Etherea layouts and prices guide.

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is keeping the Binghatti Etherea construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.