Binghatti Moonlight Construction Updates
One Mixed-Use Tower in Al Jaddaf, Tracked From Its First Dated Reading
Binghatti Moonlight stood at 19.24% in the DLD register on 29 June 2026, a first dated reading: foundations completed, the Al Jaddaf tower's structure under way.
Construction tracking against RERA inspection data, updated after every recorded inspection.
Direct advisor access. Every message answered personally, never by a call center.
Construction Snapshot
Binghatti Moonlight at a Glance
Registered with the Dubai Land Department as project 3722, Binghatti Moonlight is one tower in Al Jaddaf that stacks 236 residences over a band of office floors, with retail at street level. Its record is still short: construction was logged as starting on 15 April 2025, the only dated reading is 19.24% on 29 June 2026, and the registered completion date of 15 June 2026 had already passed 14 days before that reading arrived. The six cards below are the register anchors this page is built on.
3722
Active
15 April 2025
236 residential units
25,746.46 sq m
15 June 2026
Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.
Inspection Record
Binghatti Moonlight Construction Update Timeline
One dated reading makes up the Binghatti Moonlight record so far: 19.24% in the DLD register on 29 June 2026, the visit at which RERA listed enabling and foundation works as completed and the structure, internal works and MEP as progressing. The same register card shows a previous inspection at 0% with no date attached, so that figure sits on the track below as a marker only and has no row in the table. The June 2026 update holds the full account of that visit.
| Inspection Month | Construction Progress | Inspection Date | Full Update |
|---|---|---|---|
| June 2026 | 19.24% | 29 June 2026 | View the June 2026 update |
Reading the dates: the DLD-registered completion date for project 3722 is 15 June 2026, which had passed 14 days before the 29 June 2026 reading of 19.24%, and the Q2 2026 handover target originally stated for Binghatti Moonlight has also passed. The register shows no replacement date. A registered date is an administrative anchor set at registration, so confirm the current expected completion date with Binghatti and on Dubai REST before committing.
Pace Analysis
How Fast Binghatti Moonlight Has Been Built
With a single dated reading, Binghatti Moonlight has no inspection-to-inspection pace yet. The one span that can be measured runs from the recorded construction start to the June 2026 register entry:
- 15 Apr 2025 to 29 Jun 2026: enabling, foundations and early structure, 19.24% over 440 daysAbout 1.31 points per month
That average folds two very different kinds of work into one number. Most of those 440 days went on enabling works and the foundations beneath four basement levels, below-ground work that adds little to a percentage for the effort involved, and the RERA notes of 29 June 2026 put the site right at the hand-off from that phase into structure, internal works and MEP. The 80.76 points still open at that reading cover the rest of the frame up through 22 upper floors, the mechanical floor and the roof, then the glass facades and fit-out. The 1.31 figure is arithmetic, not a forecast, and with both the registered completion date and the original Q2 2026 target passed, it is the next register entry that will give Moonlight its first measured structural-phase velocity. For an end user, that entry is the timeline signal worth waiting for; for an investor, it is the first real read on how quickly this tower climbs once it is out of the ground.
Get the Next Inspection Figure First
Tell me you are tracking Binghatti Moonlight and I will send you the next recorded figure and site photos directly, ahead of the page update.
Get the Next Update on WhatsAppProject Profile
About Binghatti Moonlight at Al Jaddaf
The 19.24% recorded on 29 June 2026 only means something against what is being delivered. The full project guide covers the tower this record is tracking:

Binghatti Moonlight: Crystalline Glass in Al Jaddaf
Binghatti Moonlight is a mixed-use Al Jaddaf tower of 236 homes and office units, topped by a framework lit at night.
View the Binghatti Moonlight Project GuideConsidering an Early-Stage Entry?
Availability at Binghatti Moonlight keeps moving while the tower is still in its structural phase. If the record on this page is what brought you here, ask me what is available now and how the 20/50/30 plan would apply to a purchase made today.
Ask About Remaining Availability on WhatsAppStage Record
Binghatti Moonlight Build Stages, Mapped to the Inspections
Each stage below is pinned to the window it occupies in Binghatti Moonlight's own record, which so far means one recorded start date, one dated reading, two stages logged as completed and two still ahead of any register entry.
Site Activation and Enabling Works
Opened by the recorded construction start of 15 April 2025 on the Al Jaddaf plot; the RERA report of 29 June 2026 lists the enabling works as completed.
Foundations Under Four Basement Levels
Foundation works for a tower that starts four levels below ground, recorded as completed at the 29 June 2026 inspection that put the register at 19.24%.
Tower Structure, Internal Works and MEP
Recorded as progressing on 29 June 2026, climbing toward three podium levels and 22 upper floors, office levels first, then a mechanical floor and the roof.
Glass Facades and Fit-Out
Binghatti's crystalline glass facades, the lit open framework at the crown, and fit-out of the office floors and 236 residences; no reading has recorded this stage yet.
Rooftop, Commissioning and Handover
Rooftop pool and gym, building systems commissioning and handover, for which Binghatti has yet to confirm a date since the original Q2 2026 target passed.
What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Binghatti Moonlight's own record.
Buyer Position
Tracking Your Position at Binghatti Moonlight
This page is one of four project resources that together cover a Binghatti Moonlight purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Binghatti Moonlight Construction Updates
This page: the dated DLD register record for Binghatti Moonlight, from its April 2025 start onward.

Binghatti Moonlight Golden Visa: A Mixed-Use Tower in Al Jaddaf
Binghatti Moonlight, Binghatti's freehold Al Jaddaf tower, holds 236 residences over office and retail levels, under Oqood now.
Read the Binghatti Moonlight Golden Visa Guide
Binghatti Moonlight Escrow: The Dubai Islamic Bank Account in Al Jaddaf
Binghatti Moonlight escrows 286 units at Dubai Islamic Bank, DLD project 3722, 19.24% certified at the June 2026 inspection.
Verify the Binghatti Moonlight Escrow AccountApproaching Handover
Between 19.24% and Handover: What Binghatti Moonlight Buyers Should Do Now
At the 29 June 2026 reading, 80.76 points of the build were still open and no confirmed completion date was on record, which makes the construction years, not handover, the window where a Moonlight buyer's checks pay off. Instalments under the 50% construction share fall due while the tower is rising, so the three steps below belong before each payment rather than after the next notice arrives.
First, match every construction instalment to the trust account shown on the Binghatti Moonlight escrow account page, so your money reaches the Dubai Islamic Bank account registered for project 3722 and nowhere else.
Second, if residency matters to you, settle eligibility early through the Binghatti Moonlight Golden Visa guide, since the 2 and 3 bedroom apartments clear the AED 2M value on price while a 1 bedroom at AED 1.52M does not on its own.
Third, keep the record tied to what you are paying for by checking the 20/50/30 plan, unit sizes and office units in the Binghatti Moonlight project guide each time a new reading posts.
Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.
The Wider Picture
Explore Al Jaddaf Structure
The 19.24% recorded on 29 June 2026 is only half the picture; the other half is the Al Jaddaf market, community and developer around the site. These three pages put Moonlight's build in that context:

Al Jaddaf: Binghatti Wraith and Amazonia Apartments on the Creek
Al Jaddaf, the creekside district on the Bur Dubai bank, lists apartments in Binghatti Wraith and Amazonia on 60/40 payment plans.
See Al Jaddaf Properties for Sale
Al Jaddaf: A Creek-Side District With Two Green Line Metro Stations
Al Jaddaf sits on the Bur Dubai bank of the Creek, home to Jaddaf Waterfront and a growing branded-residence pipeline.
Explore the Al Jaddaf Community
Binghatti: Record Construction Speed and Branded Towers With Bugatti and Mercedes-Benz
Binghatti has delivered more than 60 projects since 2008, with 27 under development and two master communities across Dubai.
View the Binghatti Developer ProfileConstruction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.
FAQs
Binghatti Moonlight Construction Updates Frequently Asked Questions
Binghatti Moonlight, DLD project 3722, is an active project under construction, recorded at 19.24% in the Dubai Land Department register on 29 June 2026, the most recent dated entry in this record. At that date the main contract was progressing, with the tower's structure, internal works and MEP under way above completed foundations. The full record is in the inspection timeline above.
Binghatti Moonlight has one dated reading, 19.24% on 29 June 2026, so no change between two dated inspections exists yet. The register card lists a previous inspection at 0% but no date for it, which means the 19.24-point difference cannot be tied to a specific period; the only dated reference is the construction start of 15 April 2025. That inspection is covered in full in the Binghatti Moonlight June 2026 construction update.
No confirmed completion date for Binghatti Moonlight is on record. The DLD-registered completion date for project 3722 was 15 June 2026, and the Q2 2026 handover target first stated for the project closed on 30 June 2026; both passed with the register at 19.24% on 29 June 2026, and the register used for this page shows no replacement date. The current expected completion date should be confirmed with Binghatti and on Dubai REST, and this page's record is updated when a new date or reading is recorded.
Binghatti Moonlight holds 236 residences in 1, 2 and 3 bedroom layouts inside a single mixed-use tower that also contains office units and ground-floor retail. The RERA project description dated 29 June 2026 lists four basement levels, a ground floor, three podium levels and 22 upper floors, plus a mechanical floor and the roof, and Binghatti's fact sheet places the office floors below the residential floors.
Averaged over the whole build, Binghatti Moonlight has moved about 1.31 percentage points per month: 19.24 points across the 440 days from the recorded start on 15 April 2025 to the 29 June 2026 reading, on a 30-day month. That figure is arithmetic, not a forecast, and with no dated previous inspection no phase-by-phase pace can be measured yet. The reasoning is set out in the pace analysis above.
Two of the five stages in the Binghatti Moonlight stage record were logged as completed at the 29 June 2026 inspection: the enabling works and the foundations. The third stage, covering the structure, internal works and MEP across the basements, podium and 22 upper floors, was in progress with the register at 19.24%, and no facade, fit-out or rooftop amenity work had been recorded by that date. The stage-by-stage view is in the stage record above.

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is keeping the Binghatti Moonlight construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.
Ask your question, get your answer. No obligation and no follow-up unless you ask for it.