Chevalia Estate at Grand Polo Construction Updates
The Verified Inspection Record for Eighty Villas Beside the Grand Polo Green Core
Chevalia Estate at Grand Polo reached 2.28% construction at its 21 April 2026 inspection, a short record in which eighty villa plots moved from mobilisation to foundations.
Construction tracking against RERA inspection data, updated after every recorded inspection.
Direct advisor access. Every message answered personally, never by a call center.
Construction Snapshot
Chevalia Estate at Grand Polo at a Glance
Chevalia Estate is Emaar's eighty-villa release on the outer edge of the Grand Polo Club and Resort Green Core, registered with the Dubai Land Department as project 3699 and on site since 27 March 2025. Thirteen months later the April 2026 inspection certified 2.28%, a figure that on a horizontal estate is earned across eighty separate plots rather than in one rising structure. The anchors below are the registration values that percentage is measured against.
3699
Active
27 March 2025
80 five-bedroom villas
6,516 sq ft (605 sq m) average built-up area per villa
Q1 2029 (expected handover)
Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.
Inspection Record
Chevalia Estate at Grand Polo Construction Update Timeline
Two readings sit in this project's register. The earlier one, held in the DLD record as the previous inspection, stood at 0.35%; the inspection of 21 April 2026 raised it to 2.28%, a movement of 1.93 points. Only the April 2026 reading carries a published date, so it is the single labelled dot on the track below, and the row beneath it links the full site report for that cycle.
| Inspection Month | Construction Progress | Inspection Date | Full Update |
|---|---|---|---|
| April 2026 | 2.28% | 21 April 2026 | View the April 2026 update |
Pace Analysis
How Fast Chevalia Estate at Grand Polo Has Been Built
With one dated inspection and one undated predecessor, the pace question at Chevalia Estate is answered by the distance travelled from the construction start rather than by a long series of readings:
- Mar 2025 to Apr 2026: enabling, foundations and infrastructure, construction start to 2.28%About 0.2 points per month
- Previous register reading to 21 Apr 2026: 0.35% to 2.28%, interval undatedUp 1.93 points
Two figures, one message: Chevalia Estate is still in the band where site effort and certified percentage move at very different speeds. Roughly thirteen months of activity converted into 2.28 percentage points, because excavation, foundations and the road and utility corridors that serve eighty plots carry a small weight in a villa community's certified progress. What matters next is the shape after the ground closes, since the figure on an estate of this kind tends to move in larger steps once eighty superstructures rise in parallel, and Emaar's own payment plan is written around that expectation, with the first construction-linked instalment set at 40% completion. For an end user, that means a long wait on a legible schedule. For an investor, the test is not the 2.28% itself but whether the readings after it show the estate leaving the groundworks band on time.
Get the Next Inspection Figure First
Tell me you are tracking Chevalia Estate at Grand Polo and I will send you the next recorded figure and site photos directly, ahead of the page update.
Get the Next Update on WhatsAppProject Profile
About Chevalia Estate at Grand Polo at Grand Polo Dubai
A percentage only means something next to what it is building. The project guide covers the eighty five-bedroom villas this record is tracking toward:

Chevalia Estate at Grand Polo: Emaar's Five Bedroom Villa Enclave
Chevalia Estate at Grand Polo is a development of 80 five bedroom villas around the Green Core, by three polo fields.
View the Chevalia Estate at Grand Polo Project GuideConsidering an Early-Stage Entry?
Chevalia Estate is listed with limited units available while the record still reads 2.28%, and the five-bedroom villas start at AED 9.00M ≈ USD 2.45M. Ask me what is left before the estate moves out of its groundworks band.
Ask About Remaining Availability on WhatsAppStage Record
Chevalia Estate at Grand Polo Build Stages, Mapped to the Inspections
Each stage below is placed against the windows this project's own record has produced so far, so you can see where the 2.28% reading sits and what has to be certified before the next milestone percentage is reached.
Mobilisation and DLD Registration
Construction started on 27 March 2025 and the project entered the DLD register on 22 April 2025 as number 3699, with the escrow trust account held at Abu Dhabi Commercial Bank.
Enabling, Foundations, Substructure and Infrastructure
The independent monitoring report for 21 April 2026 records these four packages progressing together on plot 1779 in Dubai Investment Park Second, with the main contract listed as progressing at 2.28%.
Villa Superstructure to Ground Plus One Plus Roof
Eighty villa shells have to rise before the certified figure passes the 40% and 50% marks carrying the February 2027 and May 2027 instalments on the published payment plan.
Facades, MEP and Interior Fit-Out
The 80% and 90% certification points, dated January 2028 and April 2028 on the same plan, fall inside this band rather than at the end of it.
Landscaping, Commissioning and Delivery
Community landscaping, systems commissioning and completion certification close the 97.72 points still open at the last reading, with the final 20% instalment due at 100% construction completion and handover expected in Q1 2029.
What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Chevalia Estate at Grand Polo's own record.
Buyer Position
Tracking Your Position at Chevalia Estate at Grand Polo
This page is one of four project resources that together cover a Chevalia Estate at Grand Polo purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Chevalia Estate at Grand Polo Construction Updates
This page: the verified inspection record for Chevalia Estate, from the March 2025 start to handover.

Chevalia Estate at Grand Polo Golden Visa Through One 5 Bedroom Villa
Emaar's Chevalia Estate at Grand Polo offers one freehold typology, the 5 bedroom villa, which qualifies more than four times over.
Read the Chevalia Estate at Grand Polo Golden Visa Guide
Chevalia Estate at Grand Polo: The Villa Release's Escrow Record
Chevalia Estate at Grand Polo, DLD project 3699, escrows 80 villas with Abu Dhabi Commercial Bank, 2.28% certified in April 2026.
Verify the Chevalia Estate at Grand Polo Escrow AccountApproaching Handover
Between 2.28% and Handover: What Chevalia Estate at Grand Polo Buyers Should Do Now
At 2.28% the useful work is administrative rather than physical. The record will not move quickly for several cycles, and the decisions that protect an early-stage villa purchase are all made inside this window. The fourth instalment is the first payment tied to a certified percentage rather than a calendar date, dated February 2027 at 40% construction completion, so the three steps below belong before that reading rather than after it.
First, confirm that every transfer lands in the DLD-registered escrow account for project 3699; the Chevalia Estate escrow account page shows the account and how certified milestones release funds.
Second, read your own instalment schedule against the certified marks of 40%, 50%, 80%, 90% and 100%, because the dates printed on the plan and the percentages behind them are two separate tests.
Third, if the purchase is meant to support residency, settle eligibility early through the Chevalia Estate Golden Visa guide rather than in the weeks around title deed issue.
Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.
The Wider Picture
Explore Grand Polo Dubai Structure
A build record is only half the picture; the other half is the masterplan rising around it. These three pages put the 2.28% reading in its listing, community, and developer context:

Grand Polo Dubai Properties for Sale
Browse villas and townhouses for sale at Grand Polo Club & Resort, comparing Equiterra, Selvara and Chevalia.
See Grand Polo Dubai Properties for Sale
Grand Polo Dubai Community Overview
Read the Grand Polo Club & Resort guide: Emaar's 60 million sq ft equestrian estate community of villas and townhouses.
Explore the Grand Polo Dubai Community
Emaar Properties: Burj Khalifa, Downtown Dubai and Twenty Master Communities
Emaar, founded in 1997, built Burj Khalifa and Downtown Dubai and has delivered over 85,000 homes across twenty master communities.
View the Emaar Properties Developer ProfileConstruction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.
FAQs
Chevalia Estate at Grand Polo Construction Updates Frequently Asked Questions
Chevalia Estate at Grand Polo is an active DLD-registered project, number 3699, recorded at 2.28% construction progress at the inspection of 21 April 2026, with enabling, foundation, substructure and infrastructure works in progress. The full record is in the inspection timeline above.
The 21 April 2026 inspection recorded 2.28% construction progress, 1.93 points above the previous reading of 0.35% held in the DLD register. The site report behind that figure is published in the April 2026 construction update.
From the 27 March 2025 construction start to the 21 April 2026 inspection, the certified figure reached 2.28%, an average of about 0.2 percentage points per month across roughly thirteen months, with the undated previous reading of 0.35% falling inside that span. The full calculation is in the pace analysis above.
Handover is expected in Q1 2029. The project stood at 2.28% on 21 April 2026, so almost the entire programme is still ahead of it, and the closing 20% instalment on the published payment plan falls due at 100% construction completion. This page's record is updated each time a new inspection percentage is registered.
The DLD register lists 80 units for project 3699, released as five-bedroom villas built to ground plus one floor plus roof, averaging 6,516 sq ft (605 sq m) of built-up area each. That count is unchanged since registration on 22 April 2025.
Construction started on 27 March 2025, four weeks before the project was registered with the Dubai Land Department on 22 April 2025. The first reading published on this site is the 21 April 2026 inspection at 2.28%; the earlier register reading of 0.35% carries no published date.

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is keeping the Chevalia Estate at Grand Polo construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.
Ask your question, get your answer. No obligation and no follow-up unless you ask for it.