Chevalia Fields Construction Updates

From Ground Works to Handover Beside the Polo Fields

Chevalia Fields recorded 10.03% construction at its 21 July 2026 RERA inspection, with enabling and foundation works underway across 179 villa plots beside the polo fields.

Construction tracking against RERA inspection data, updated after every recorded inspection.

Direct advisor access. Every message answered personally, never by a call center.

10.03%Construction Progress
21 July 2026Latest RERA Inspection
179 villas, G+2 formatTotal Units
Project 3701DLD Registration

Construction Snapshot

Chevalia Fields at a Glance

Chevalia Fields is Emaar's 179-villa enclave on plot 1520 in Dubai Investment Park Second, registered under DLD project number 3701 and rising in a G+2 format around the green core of Grand Polo Club and Resort. Sixteen months separate its 13 March 2025 construction start from the 10.03% recorded in July 2026, and the anchors below are what that percentage is measured against. Because these are individual homes on separate plots rather than one core climbing floor by floor, a single figure here averages dozens of parallel fronts, which is the first thing to understand before reading any number on this page.

DLD Project Number

3701

Project Status

Active

Construction Start

13 March 2025

Total Units

179 villas, G+2 format

Total Built-Up Area

Registered Completion Date

30 April 2029 (DLD)

Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.

Inspection Record

Chevalia Fields Construction Update Timeline

This record currently holds one dated reading: 10.03% verified on 21 July 2026, sixteen months after the 13 March 2025 start. The register also publishes an earlier figure of 1.36% with no inspection date attached, so it is quoted in prose as context and deliberately kept off the track and out of the table below, because a percentage without a date cannot be placed on a timeline honestly. Each new cycle joins the table as it publishes, with the full report linked from its row.

Inspection MonthConstruction ProgressInspection DateFull Update
July 202610.03%21 July 2026View the July 2026 update

Pace Analysis

How Fast Chevalia Fields Has Been Built

With a single dated reading on the register, Chevalia Fields has no inspection-to-inspection velocity yet. Three figures can still be computed honestly, and each one says something different:

  • 13 Mar 2025 start to 21 Jul 2026 inspection: 0% to 10.03% across 16.3 monthsAbout 0.6 points per month
  • Register's undated 1.36% figure to the dated 10.03% reading: interval unknown8.67 points, no rate derivable
  • 21 Jul 2026 to the 30 Apr 2029 registered completion: 89.97 points across 33.3 monthsAbout 2.7 points per month

The first number deserves to be held lightly. A since-start average of about 0.6 points per month spreads sixteen months across registration, mobilization and enabling works, none of which converts into percentage points the way superstructure does once it starts. The second is the honest hole in the record: 8.67 points sit between the register's two published figures, but with no date on the earlier one, any monthly rate drawn from that pair would be manufactured, so none is offered here. The third is the figure that matters from the next cycle onward. Holding 30 April 2029 means averaging roughly 2.7 points per month over the remaining 89.97, which is unremarkable for a villa community once 179 plots are building in parallel, and demanding if the enabling phase runs long. For an investor judging Emaar's delivery discipline, and for a buyer planning a Q2 2029 move, the next dated reading is what turns this arithmetic into evidence.

Get the Next Inspection Figure First

Tell me you are tracking Chevalia Fields and I will send you the next recorded figure and site photos directly, ahead of the page update.

Get the Next Update on WhatsApp

Project Profile

About Chevalia Fields at Grand Polo Dubai

A percentage only means something next to what it is building. The full project guide covers what buyers on this page are tracking toward:

Chevalia Fields by Emaar in Grand Polo Club and Resort modern villa front facade with a wood-clad garage, landscaped planting, and a parked car in Dubai - Presented by Tohid Fetrat

Chevalia Fields, a Polo-Field Villa Enclave at Grand Polo Club

Chevalia Fields is a 179 villa enclave on the green core of Grand Polo, looking onto three polo fields.

View the Chevalia Fields Project Guide

Considering an Early-Stage Entry?

Buying at 10.03% is a trade: three years of runway and open choice of plot, against a villa that does not exist yet. Which plots remain open shifts between releases, so it is worth confirming what is available before deciding.

Ask About Remaining Availability on WhatsApp

Stage Record

Chevalia Fields Build Stages, Mapped to the Inspections

The first two stages below carry dates taken from the DLD register and the July 2026 monitoring report. Stages three to five are keyed to the certified-completion triggers published in the Emaar payment plan, which are schedule targets rather than recorded windows, and each will be replaced by real dates as the inspections land.

Mar 2025 to mid 2026

Registration and Site Mobilization

Construction start recorded 13 March 2025, project registration dated 22 April 2025, with mobilization still noted as ongoing at the July 2026 inspection.

Current PhaseJul 2026 at 10.03%

Enabling, Foundations and Substructure

The 21 July 2026 inspection found enabling, foundation and substructure works at uneven stages plot by plot, with envelope, internal and MEP scopes barely begun.

Target 30 percent, Jan 2027

Superstructure Across 179 Plots

Frames climbing to G+2 on plot after plot. This is the band where the percentage moves fastest, and the first trigger written against certified progress rather than a date.

Targets 50 to 90 percent, Jun 2027 to May 2028

Envelope, MEP and Internal Fit-Out

Villas closed in, services run, interiors finished, with three certified milestones falling inside this stretch. Community infrastructure is delivered in parallel rather than after.

Target 100 percent, Apr 2029

Landscaping, Completion and Handover

Plot landscaping, building completion certification and the closing 20% installment, against a registered completion date of 30 April 2029 and Emaar's stated Q2 2029 handover.

What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Chevalia Fields's own record.

Buyer Position

Tracking Your Position at Chevalia Fields

This page is one of four project resources that together cover a Chevalia Fields purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Chevalia Fields by Emaar in Grand Polo Club and Resort construction updates cover image featuring a project rendering of a modern villa with an illuminated private pool at dusk in Dubai - Presented by Tohid Fetrat
You Are Here

Chevalia Fields Construction Updates

This page: every dated RERA reading for Chevalia Fields, from the March 2025 start toward handover.

Chevalia Fields by Emaar in Grand Polo Club and Resort Golden Visa concept graphic with a gold visa card above a modern villa and garage in Dubai - Presented by Tohid Fetrat

Chevalia Fields Golden Visa, Carried by One Grand Polo Villa

Emaar's Chevalia Fields inside Grand Polo Club and Resort offers 4 and 5 bedroom villas, both tiers qualifying individually.

Read the Chevalia Fields Golden Visa Guide
Chevalia Fields by Emaar in Grand Polo Club and Resort escrow account protection concept with shield and padlock icons beside a modern villa street view in Dubai - Presented by Tohid Fetrat

Chevalia Fields Escrow, the Polo-Field Villa Account

Emaar banks Chevalia Fields payments with National Bank of Ras Al Khaimah: DLD project 3701, 179 units, 10.03% certified July 2026.

Verify the Chevalia Fields Escrow Account

Approaching Handover

Between 10.03% and Handover: What Chevalia Fields Buyers Should Do Now

Twenty points separate the July 2026 reading from the first installment on this plan that is released by a certified percentage rather than a calendar date. That is the window worth using, because the protections below are simplest to put in place while nothing is due, and awkward to sort out in the weeks when a payment notice has already landed.

First, confirm where your money goes before the next transfer. The Chevalia Fields escrow account page covers the registered trust account for project 3701 and how a certified reading, not a request, is what releases funds to the developer.

Second, read how your own agreement words its milestone triggers. Early installments here run to fixed dates while later ones are written against certified completion, and at 10.03% that distinction decides whether a slower build delays your payments or leaves them unchanged.

Third, if a UAE residency route matters to you, settle Golden Visa eligibility for Chevalia Fields early, because title deed timing decides which application path is open to you at handover.

Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.

The Wider Picture

Explore Grand Polo Dubai Structure

One cluster's percentage reads differently once you see the masterplan it belongs to. These three pages put the Chevalia Fields record in its community, market, and developer context:

Grand Polo Villas and Townhouses for Sale luxury villa with private pool and outdoor lounge at Grand Polo Club and Resort Dubai Presented by Tohid Fetrat

Grand Polo Dubai Properties for Sale

Browse villas and townhouses for sale at Grand Polo Club & Resort, comparing Equiterra, Selvara and Chevalia.

See Grand Polo Dubai Properties for Sale
Grand Polo Club and Resort by Emaar clubhouse overlooking the polo fields with palm lined landscape in Dubai Presented by Tohid Fetrat

Grand Polo Dubai Community Overview

Read the Grand Polo Club & Resort guide: Emaar's 60 million sq ft equestrian estate community of villas and townhouses.

Explore the Grand Polo Dubai Community
Emaar Properties developer showcasing Downtown Dubai skyline with Burj Khalifa and surrounding residential and commercial towers at dusk Presented by Tohid Fetrat

Emaar Properties: Burj Khalifa, Downtown Dubai and Twenty Master Communities

Emaar, founded in 1997, built Burj Khalifa and Downtown Dubai and has delivered over 85,000 homes across twenty master communities.

View the Emaar Properties Developer Profile

Construction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.

FAQs

Chevalia Fields Construction Updates Frequently Asked Questions

Chevalia Fields is an active DLD-registered project (number 3701) in its enabling and substructure phase, recorded at 10.03% at the RERA inspection of 21 July 2026. Every dated reading is held in the inspection timeline above.

The 21 July 2026 inspection recorded 10.03% construction progress, 8.67 points above the register's previous published figure of 1.36%. That earlier figure carries no inspection date, so the length of the interval between the two is not on the record. The cycle report behind the reading is the July 2026 construction update.

The DLD-registered completion date for project 3701 is 30 April 2029, and Emaar states handover from Q2 2029. Measured from the 10.03% recorded on 21 July 2026, 89.97 points of certified progress sit between that reading and completion, and this page records each cycle as it closes that distance.

DLD registration records 179 units, delivered as four and five bedroom villas in a G+2 format on plot 1520 in Dubai Investment Park Second. The layouts and plot differences behind that count are set out in the Chevalia Fields at Grand Polo project guide.

The register puts construction start at 13 March 2025, with project registration dated 22 April 2025. The first dated percentage arrived sixteen months later, when the 21 July 2026 inspection recorded 10.03%.

Not between inspections yet, because the register publishes the earlier 1.36% figure without a date, and a rate quoted from an undated pair would be invented. Two figures do stand up: roughly 0.6 points per month averaged from the 13 March 2025 start to the 21 July 2026 reading, and roughly 2.7 points per month implied by holding the 30 April 2029 registered completion. Both are worked through in the pace analysis above.

At the 21 July 2026 reading, independent monitoring logs enabling, foundation and substructure works at uneven stages from plot to plot, superstructure, envelope, internal and MEP works only just started, and community infrastructure advancing across the site alongside the villas. That mix is what 10.03% represents on a 179-plot parcel.

Its 179 plots curve around the masterplan green core, the band holding three polo fields, the clubhouse and the stables, on the eastern side of the community at plot 1520. What that position means for outlook and frontage is covered in the Grand Polo Club and Resort community guide.

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is keeping the Chevalia Fields construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.

Ask your question, get your answer. No obligation and no follow-up unless you ask for it.

WhatsApp +971543443597
Get the Latest Status