City Walk Crestlane 2 Construction Update - October 2026

October 2026 DLD Register Reading Places City Walk Crestlane 2 at 6.83% as Foundation Works Progress in City Walk

Enabling, piling and foundation works were progressing at City Walk Crestlane 2 when RERA inspected on 08 October 2026; the backdrop is a developer rendering.

Direct advisor access. Every message answered personally, never by a call center.

6.83%DLD Register Reading
08 October 2026Inspection Date
Q4 2028Expected Handover
3530DLD Project Number

DLD Register Reading, October 2026

City Walk Crestlane 2 Construction Snapshot

A 1.63 point rise since the 12 June 2026 reading takes City Walk Crestlane 2 from 5.20% to 6.83% on the DLD register, which keeps the project in the enabling and foundations band: the stage where escrow checks, Oqood registration and the SPA payment dates matter more to a buyer than the percentage itself.

Project Name

City Walk Crestlane 2 by Meraas

Project Number

3530

Project Status

Active

Construction Progress

6.83%

Inspection Date

08 October 2026

Construction Start

16 April 2025

Total Units

201 residential units

Total Built Area

25,933.37 sq m

Expected Completion

Q4 2028

Data source: DLD project register reading dated 08 October 2026 for project 3530, read with the RERA progress report of the same date. Construction tracking against RERA inspection data runs across the full tohidfetrat.com project portfolio and is reviewed after every published cycle. Last updated: October 2026.

Want each new reading the day it publishes? Message me on WhatsApp and I will send it to you directly: one message per inspection cycle, nothing else. Message me on WhatsApp

This Inspection Cycle

City Walk Crestlane 2 Construction Progress Summary

Over the 118 days between the two dated register readings, City Walk Crestlane 2 gained 1.63 points, about 0.41 points per 30-day month; averaged across the 540 days since the registered construction start of 16 April 2025, the rate is about 0.38 (arithmetic, not a forecast). Readings at the piling and foundation stage tend to climb slowly until the structure starts to rise, so neither figure by itself predicts the finish.

On the Register
  • Project 3530 registered on 06 February 2025
  • Construction start recorded on 16 April 2025
  • Register reading of 5.20% on 12 June 2026
  • Escrow trust account with Abu Dhabi Commercial Bank (ADCB)
In Progress at 6.83%
  • Main contract recorded as progressing (RERA report, 08 October 2026)
  • Enabling works across the site
  • Piling for the two buildings
  • Foundation works for the shared basement level
Still to Come Before Handover
  • Basement and ground floor, including the lobby and two retail units
  • Structure of Building A (G+12) and Building B (G+11)
  • Facade, building services and interiors for 201 residences
  • Further register readings up to the Q4 2028 handover
Next inspectionNo date is announced; the next RERA visit will show up as a new reading on the DLD register for project 3530, and this cluster adds it as a dated update.
Completion targetHandover expected in Q4 2028; the registered completion date in the DLD record, 10 December 2028, falls inside the same quarter.
Remaining distance93.17 percentage points separate the 08 October 2026 reading from 100%, about 3.52 points per 30-day month over the 794 days to the registered completion date (arithmetic, not a forecast).

Payments and the Register

What 6.83% Progress Means for City Walk Crestlane 2 Buyers

The 75/25 plan for City Walk Crestlane 2 runs on a calendar, not on construction stages, so a reading of 6.83% does not by itself trigger any instalment. As schedule arithmetic, the developer's dated plan put 55% of the price on the calendar by September 2026 while the register stood at 6.83% on 08 October 2026: the two percentages measure different things. During the foundation works, four actions matter most.

Before Any Transfer

Verify the escrow account

Every instalment for project 3530 should go only to the DLD regulated escrow account held with ADCB, and never to a personal or agency account. City Walk Crestlane 2 escrow account verification walks through the check; the lookup takes about two minutes against the official DLD project record.

At Booking

Reread your SPA payment dates

Four launch dates (July 2025, November 2025, April 2026 and September 2026) fall before this reading, so check how your sale and purchase agreement treats them, whether past-dated shares are collected at booking, and how it defines the handover notice for Q4 2028. Not sure how your SPA dates sit against this reading? Send me your SPA schedule and I will map it against the recorded register readings.

Within Weeks of Booking

Confirm your Oqood registration

Oqood is the DLD registration of an off-plan unit, and with the buildings still at foundation level it is the official record that links your purchase to project 3530. Ask Meraas for the Oqood confirmation and check the unit number, project number and price against your SPA.

Every Cycle

Follow the next readings

With 93.17 points still to go, many register readings lie between this one and handover, and one cycle says little about the pace of the build. City Walk Crestlane 2 construction updates hub lists each dated reading so the trend can be judged across several of them.

General framework, not legal advice: payment dates, catch-up amounts, notice periods and fee obligations are set by your individual SPA and the DLD record, and both should be read directly.

Buying at 6.83%?

Entering while the foundations go in trades a long wait for paying from the current Meraas price list, with a quarter of the price left to pay at handover. Every payment goes to the DLD-registered escrow account for project 3530, released against verified construction progress.

Entering Now at 6.83%
  • Main contract progressing, with piling and foundations recorded on 08 October 2026
  • Handover expected in Q4 2028, about two years after this reading
  • 20% on booking and 25% held until handover under the 75/25 plan
Typical Near-Completion Entry
  • Structure already standing, so less construction risk left to carry
  • Keys within months rather than years
  • Most of the price due in a short window, often at resale levels
AED 2.60M ≈ USD 708KStarting Price
75/25 Payment Plan20% on Booking
Q4 2028Expected Handover
Ask What Is Available at City Walk Crestlane 2

Limited Units Available per the developer as of this update; availability shifts between cycles.

About the Development

City Walk Crestlane 2 Project Details

City Walk Crestlane 2 by Meraas in City Walk project rendering of low-rise residential buildings framing a landscaped swimming pool courtyard in Dubai - Presented by Tohid Fetrat
City Walk · Meraas

While piling and foundation works continue, City Walk Crestlane 2 exists mostly below ground: Building A (G+12) and Building B (G+11), both mid-rise, will contain 201 homes ranging from 1 bedroom apartments up to 4 bedroom duplexes. Starting prices: AED 2.60M ≈ USD 708K.

For buyers entering at this stage, the trade off is a wait to the Q4 2028 expected handover in return for buying from the current Meraas price list instead of at resale levels once the buildings stand.

City Walk Crestlane 2 by Meraas Project Guide

Site Context This Cycle

Explore City Walk Crestlane 2 Location on Dubai Map

City Walk Crestlane 2 runs along Al Multaqa Street on the wider City Walk Crestlane plot, with both buildings turned inward toward the central pools and water features. Because Building A and Building B share a single basement level, the piling and foundation works in this cycle form one continuous footprint, and the lobby and two ground-floor retail units will later sit on that common base.

Around the site, City Walk is already a working district along Al Wasl Road, a short drive from Sheikh Zayed Road, with its retail streets, restaurants and hotels open today. For buyers that narrows the open question to the buildings themselves and the Q4 2028 timing, since the setting can be judged now in person. See the project's position on the interactive Dubai real estate map. See the project’s position on the interactive Dubai real estate map.

Interactive Dubai real estate map preview
Click to view City Walk Crestlane 2 by Meraas on Dubai Map

Buyer Resources for This Project

Investing in City Walk Crestlane 2 During the Foundation Stage

With the buildings still at foundation level, residency planning and payment protection are the two questions worth settling before the next dated instalment. Each resource below is matched to where City Walk Crestlane 2 stands in October 2026.

City Walk Crestlane 2 by Meraas in City Walk construction updates cover image featuring a project rendering of illuminated residential blocks with landscaped walkways at dusk in Dubai - Presented by Tohid Fetrat
You Are Here

City Walk Crestlane 2 Construction Updates

This page: the October 2026 register reading for City Walk Crestlane 2 and its foundation works.

City Walk Crestlane 2 by Meraas in City Walk Golden Visa concept graphic showing a gold visa card over a rendered garden terrace beside residential buildings in Dubai - Presented by Tohid Fetrat

Crestlane 2 Golden Visa: Eligible on Price Across All Six Unit Types

City Walk Crestlane 2 by Meraas qualifies for the AED 2M Golden Visa at every unit type, from 1 bedroom apartment.

Read City Walk Crestlane 2 Golden Visa Guide
City Walk Crestlane 2 by Meraas in City Walk escrow account concept graphic showing a shield and padlock beside a rendered residential balcony and facade in Dubai - Presented by Tohid Fetrat

Crestlane 2 Escrow: Abu Dhabi Commercial Bank and the 75/25 Plan

City Walk Crestlane 2, DLD project 3530, escrows 201 units at Abu Dhabi Commercial Bank and read 6.83% in October 2026.

Verify City Walk Crestlane 2 Escrow Account

Update Timeline

Other City Walk Crestlane 2 Construction Updates

October 2026 is the first monthly report for City Walk Crestlane 2; the hub keeps every dated register reading in one place as further cycles publish.

All City Walk Crestlane 2 Construction Updates

FAQs

City Walk Crestlane 2 Construction Progress in October 2026: Frequently Asked Questions

As of 08 October 2026, the DLD project register records City Walk Crestlane 2 (project 3530) at 6.83% construction progress. The RERA progress report of the same date gives the project status as Main Contract, Progressing, and the reading was the latest on the register when this update was prepared.

The register moved from 5.20% on 12 June 2026 to 6.83% on 08 October 2026, a gain of 1.63 points over 118 days, or about 0.41 points per 30-day month (arithmetic, not a forecast). Percentages in the enabling, piling and foundation stage usually rise slowly before the structure goes up, so this rate alone says little about the pace once the buildings start to climb.

Yes. As of the October 2026 reading, handover is expected in Q4 2028, and the registered completion date in the DLD record, 10 December 2028, falls inside that same quarter. Covering the remaining 93.17 points in the 794 days to that registered date works out at about 3.52 points per 30-day month (arithmetic, not a forecast), and register dates can be revised between cycles. How readings and dates are logged over the whole build is covered on the City Walk Crestlane 2 construction updates hub.

The RERA progress report dated 08 October 2026 records that enabling, piling and foundation works were progressing at site. That is groundwork for a single shared basement level under Building A (G+12) and Building B (G+11); the report describes no work above the foundations at that date.

It is the status the RERA progress report of 08 October 2026 assigns to City Walk Crestlane 2: the project is in its main contract stage and the works under that contract were recorded as progressing. Read together with the 6.83% register reading, it describes an active site at the start of its build rather than a finished or stalled one.

No. The developer's 75/25 plan is tied to calendar dates, not to construction percentages. By that dated schedule, 55% of the price (20% on booking plus 10%, 5%, 10% and 10%) was scheduled by September 2026, while the register stood at 6.83% on 08 October 2026; payment shares and progress readings measure different things. For a purchase made now, Meraas fixes in the SPA how the shares for dates already passed are collected.

A Question the FAQ Can Not Answer?

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is helping you read the October 2026 inspection record for City Walk Crestlane 2 correctly before your next payment decision. Client identities and transactions are never published or referenced. Message me directly: you will always reach me personally, never a call center or sales team.

Ask your question, get your answer. No obligation and no follow-up unless you ask for it.

Get Progress Alerts