Meraas · City Walk
City Walk Crestlane 2 Construction Updates
The Dated Register Record for Two City Walk Buildings, From the Foundations Up
City Walk Crestlane 2 stood at 6.83% on 08 October 2026, the latest dated DLD register reading covered here, setting a foundation-stage baseline for its two mid-rise buildings.
Construction tracking against RERA inspection data, updated after every recorded inspection.
Direct advisor access. Every message answered personally, never by a call center.
Construction Snapshot
City Walk Crestlane 2 at a Glance
City Walk Crestlane 2 is the 201-residence Meraas release in City Walk, entered in the Dubai Land Department register as project 3530 on 06 February 2025, with its construction start logged 69 days later on 16 April 2025. The register reading of 6.83% on 08 October 2026 puts it at the foundation stage, and the RERA progress report issued that day lists the main contract as progressing. Because Building A (G+12) and Building B (G+11) stand on one shared basement level, both start from a single foundation footprint, so this record follows them as one site until their frames separate above ground. Handover is expected in Q4 2028.
3530
Active
16 April 2025
201 residential units
25,933.37 sq m
10 December 2028 (DLD)
Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.
Inspection Record
City Walk Crestlane 2 Construction Update Timeline
Two dated readings are compared in the City Walk Crestlane 2 timeline: 5.20% on 12 June 2026, 422 days after the registered start, then 6.83% on 08 October 2026, 118 days later. Only 1.63 points separate them, so their two dots almost touch on the track below. The October 2026 row links the full monthly update; the June 2026 reading is included here as a register entry alone.
| Inspection Month | Construction Progress | Inspection Date | Full Update |
|---|---|---|---|
| October 2026 | 6.83% | 08 October 2026 | View the October 2026 update |
Pace Analysis
How Fast City Walk Crestlane 2 Has Been Built
With two dated readings selected for comparison, the City Walk Crestlane 2 pace analysis covers a short interval, so the lines below keep what has been measured apart from plain arithmetic toward the Q4 2028 handover, all in 30-day months:
- Jun 2026 to Oct 2026: enabling, piling and foundations, 5.20% (12 Jun 2026) to 6.83% (08 Oct 2026)About 0.41 points per month
- Apr 2025 to Oct 2026: registered start on 16 Apr 2025 to 6.83% on 08 Oct 2026, 540 daysAbout 0.38 points per month
- Oct 2026 to Dec 2028: 93.17 points left after 08 Oct 2026, over 794 days to the 10 Dec 2028 registered completion dateAbout 3.52 points per month
- Oct 2026 to end of Q4 2028: the same 93.17 points over 815 days to 31 Dec 2028About 3.43 points per month
Measured and averaged pace sit close together, 0.41 against 0.38, which says the October 2026 reading continues the same gentle slope as the months before it rather than marking a jump. The two remaining-distance lines look steep beside them, but they describe what is left rather than how the build will move: the work RERA recorded at City Walk Crestlane 2 on 08 October 2026 is still enabling, piling and foundations for a shared basement, and readings at that stage usually climb slowly until the frames of Building A and Building B begin to go up. All four lines are arithmetic, not a forecast. For an end user, the signal worth waiting for is a dated reading that shows the basement and ground floor taking shape; for an investor, it is how sharply the slope turns once that happens, which comparisons with further dated readings can show.
Get the Next Inspection Figure First
Tell me you are tracking City Walk Crestlane 2 and I will send you the next recorded figure and site photos directly, ahead of the page update.
Get the Next Update on WhatsAppProject Profile
About City Walk Crestlane 2 at City Walk
A foundation-stage reading means more once you know what those foundations will carry. The project guide sets out what buyers here are tracking toward:

City Walk Crestlane 2: Waterside Apartments and Duplexes by Meraas
City Walk Crestlane 2, a Meraas release at the centre of City Walk, holds 201 residences in Buildings A and B.
View the City Walk Crestlane 2 Project GuideConsidering a Foundation-Stage Entry?
Meraas lists limited units available at City Walk Crestlane 2, and the mix still on sale shifts between register readings. If the record on this page is what brought you here, ask me what is currently available while the build is still at foundation level.
Ask About Remaining Availability on WhatsAppStage Record
City Walk Crestlane 2 Build Stages, Mapped to the Inspections
Each stage below is pinned to the dates City Walk Crestlane 2 has actually logged, from registration on 06 February 2025 to the 6.83% reading of 08 October 2026. The later stages carry no dates yet, because the register has not reached them.
Registration and Construction Start
Project 3530 entered the DLD register on 06 February 2025, and the construction start followed on 16 April 2025, 69 days later.
Enabling, Piling, and Foundations
Both dated readings sit here: 5.20% on 12 June 2026 and 6.83% on 08 October 2026, when RERA recorded enabling, piling and foundation works progressing.
Shared Basement and Ground Floor
The single basement level under both buildings, then the ground floor with the main lobby and its two retail units, none of it recorded as built at 6.83% on 08 October 2026.
Building A and Building B Frames
Floors rising to G+12 on Building A and G+11 on Building B; neither frame appears in the RERA notes of the 08 October 2026 inspection.
Facades, Interiors, Landscape, and Handover
Facades, interiors for 201 residences, and the pools and water features, ending at the Q4 2028 handover; the registered completion date is 10 December 2028.
What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on City Walk Crestlane 2's own record.
Buyer Position
Tracking Your Position at City Walk Crestlane 2
This page is one of four project resources that together cover a City Walk Crestlane 2 purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

City Walk Crestlane 2 Construction Updates
This page: each DLD register reading for City Walk Crestlane 2, from construction start to handover.

Crestlane 2 Golden Visa: Eligible on Price Across All Six Unit Types
City Walk Crestlane 2 by Meraas qualifies for the AED 2M Golden Visa at every unit type, from 1 bedroom apartment.
Read the City Walk Crestlane 2 Golden Visa Guide
Crestlane 2 Escrow: Abu Dhabi Commercial Bank and the 75/25 Plan
City Walk Crestlane 2, DLD project 3530, escrows 201 units at Abu Dhabi Commercial Bank and read 6.83% in October 2026.
Verify the City Walk Crestlane 2 Escrow AccountApproaching Handover
Between 6.83% and Handover: What City Walk Crestlane 2 Buyers Should Do Now
City Walk Crestlane 2 buyers will see little change on site between the foundations recorded on 08 October 2026 and the first floors of Building A and Building B, yet their payments keep moving with the calendar. On the developer's dated launch schedule, the 20% booking share plus four instalments add up to 55% of the price by September 2026, set against a register reading of 6.83% on 08 October 2026; the two figures count different things, so this is schedule arithmetic, not a judgment on progress.
The next date on that launch schedule is February 2027, and for a purchase made now Meraas confirms the dates that apply in the SPA, so the three steps below belong before that date rather than after it.
First, make sure every payment goes only into the escrow account registered for project 3530 with ADCB; the City Walk Crestlane 2 escrow account page shows how to match the account details in your SPA digit by digit.
Second, if residency is part of the plan, work through the City Walk Crestlane 2 Golden Visa guide now, since every unit type is priced above the threshold and the application timing runs alongside the Q4 2028 handover.
Third, judge the build reading by reading rather than by headline: the October 2026 construction update for City Walk Crestlane 2 sets out the 6.83% reading and the RERA site notes that go with it, and each later dated reading joins the timeline above.
Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.
The Wider Picture
Explore City Walk Structure
Two buildings at foundation level are easier to judge against what already stands around them. These three pages place City Walk Crestlane 2 within its market, its district, and its developer:

City Walk: Crestlane Apartments in the Meraas Lifestyle District Facing Downtown Dubai
City Walk is the Meraas lifestyle district in Al Wasl facing Downtown Dubai, with Crestlane apartments on a 75/25 payment plan.
See City Walk Properties for Sale
City Walk: Meraas's Urban Quarter With Coca-Cola Arena and Central Park
City Walk is an urban district in Al Wasl with low and mid-rise residences, 236 retail outlets and Burj Khalifa views.
Explore the City Walk Community
Meraas: Lifestyle Destinations From City Walk to Port de La Mer
Meraas is the name behind City Walk, Bluewaters Island and Madinat Jumeirah Living, from beachfront communities to luxury mixed-use districts.
View the Meraas Developer ProfileConstruction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.
FAQs
City Walk Crestlane 2 Construction Updates Frequently Asked Questions
City Walk Crestlane 2 is an active project on the DLD register (number 3530), recorded at 6.83% on 08 October 2026, and the RERA progress report of that date lists the main contract as progressing through enabling, piling and foundation works. Both dated readings are set out in the inspection timeline above.
The City Walk Crestlane 2 timeline compares two dated DLD register readings: 5.20% on 12 June 2026 and 6.83% on 08 October 2026, a rise of 1.63 points over 118 days. Earlier inspection records also exist in the DLD register. The later reading and its RERA site notes are covered on the October 2026 inspection page.
Between 12 June 2026 and 08 October 2026 the City Walk Crestlane 2 register reading rose by about 0.41 points per 30-day month, and averaged over the 540 days from the 16 April 2025 construction start to the 6.83% reading of 08 October 2026 it comes to about 0.38 points per month. Both figures are arithmetic, not a forecast: at the piling and foundation stage, readings usually climb slowly until the structure rises. All four pace lines are in the pace analysis above.
The two agree: the DLD register lists 10 December 2028 as the registered completion date for City Walk Crestlane 2 (project 3530), and that date falls inside the Q4 2028 quarter in which handover is expected. Closing the 93.17 points left after the 6.83% reading of 08 October 2026 within the 794 days to the registered date implies roughly 3.52 points per 30-day month, which is arithmetic, not a forecast; this record is updated as each new reading appears.
City Walk Crestlane 2 consists of two mid-rise residential buildings, Building A at G+12 and Building B at G+11 (coded B+G+12+R and B+G+11+R in the RERA progress report of 08 October 2026), set over one shared basement level, with two retail units beside the main lobby on the ground floor and 201 residences in total. Layouts by unit type are in the City Walk Crestlane 2 project guide.
The DLD register records the City Walk Crestlane 2 construction start on 16 April 2025, 69 days after project 3530 was registered on 06 February 2025. The 5.20% reading on 12 June 2026, selected for comparison in this timeline, came 422 days after that start.

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is keeping the City Walk Crestlane 2 construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.
Ask your question, get your answer. No obligation and no follow-up unless you ask for it.