City Walk Crestlane 2 Construction Updates

The Dated Register Record for Two City Walk Buildings, From the Foundations Up

City Walk Crestlane 2 stood at 6.83% on 08 October 2026, the latest dated DLD register reading covered here, setting a foundation-stage baseline for its two mid-rise buildings.

Construction tracking against RERA inspection data, updated after every recorded inspection.

Direct advisor access. Every message answered personally, never by a call center.

6.83%Construction Progress
08 October 2026Latest RERA Inspection
201 residential unitsTotal Units
Project 3530DLD Registration

Construction Snapshot

City Walk Crestlane 2 at a Glance

City Walk Crestlane 2 is the 201-residence Meraas release in City Walk, entered in the Dubai Land Department register as project 3530 on 06 February 2025, with its construction start logged 69 days later on 16 April 2025. The register reading of 6.83% on 08 October 2026 puts it at the foundation stage, and the RERA progress report issued that day lists the main contract as progressing. Because Building A (G+12) and Building B (G+11) stand on one shared basement level, both start from a single foundation footprint, so this record follows them as one site until their frames separate above ground. Handover is expected in Q4 2028.

DLD Project Number

3530

Project Status

Active

Construction Start

16 April 2025

Total Units

201 residential units

Total Built-Up Area

25,933.37 sq m

Registered Completion Date

10 December 2028 (DLD)

Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.

Inspection Record

City Walk Crestlane 2 Construction Update Timeline

Two dated readings are compared in the City Walk Crestlane 2 timeline: 5.20% on 12 June 2026, 422 days after the registered start, then 6.83% on 08 October 2026, 118 days later. Only 1.63 points separate them, so their two dots almost touch on the track below. The October 2026 row links the full monthly update; the June 2026 reading is included here as a register entry alone.

Inspection MonthConstruction ProgressInspection DateFull Update
October 20266.83%08 October 2026View the October 2026 update

Pace Analysis

How Fast City Walk Crestlane 2 Has Been Built

With two dated readings selected for comparison, the City Walk Crestlane 2 pace analysis covers a short interval, so the lines below keep what has been measured apart from plain arithmetic toward the Q4 2028 handover, all in 30-day months:

  • Jun 2026 to Oct 2026: enabling, piling and foundations, 5.20% (12 Jun 2026) to 6.83% (08 Oct 2026)About 0.41 points per month
  • Apr 2025 to Oct 2026: registered start on 16 Apr 2025 to 6.83% on 08 Oct 2026, 540 daysAbout 0.38 points per month
  • Oct 2026 to Dec 2028: 93.17 points left after 08 Oct 2026, over 794 days to the 10 Dec 2028 registered completion dateAbout 3.52 points per month
  • Oct 2026 to end of Q4 2028: the same 93.17 points over 815 days to 31 Dec 2028About 3.43 points per month

Measured and averaged pace sit close together, 0.41 against 0.38, which says the October 2026 reading continues the same gentle slope as the months before it rather than marking a jump. The two remaining-distance lines look steep beside them, but they describe what is left rather than how the build will move: the work RERA recorded at City Walk Crestlane 2 on 08 October 2026 is still enabling, piling and foundations for a shared basement, and readings at that stage usually climb slowly until the frames of Building A and Building B begin to go up. All four lines are arithmetic, not a forecast. For an end user, the signal worth waiting for is a dated reading that shows the basement and ground floor taking shape; for an investor, it is how sharply the slope turns once that happens, which comparisons with further dated readings can show.

Get the Next Inspection Figure First

Tell me you are tracking City Walk Crestlane 2 and I will send you the next recorded figure and site photos directly, ahead of the page update.

Get the Next Update on WhatsApp

Project Profile

About City Walk Crestlane 2 at City Walk

A foundation-stage reading means more once you know what those foundations will carry. The project guide sets out what buyers here are tracking toward:

City Walk Crestlane 2 by Meraas in City Walk project rendering of low-rise residential buildings framing a landscaped swimming pool courtyard in Dubai - Presented by Tohid Fetrat

City Walk Crestlane 2: Waterside Apartments and Duplexes by Meraas

City Walk Crestlane 2, a Meraas release at the centre of City Walk, holds 201 residences in Buildings A and B.

View the City Walk Crestlane 2 Project Guide

Considering a Foundation-Stage Entry?

Meraas lists limited units available at City Walk Crestlane 2, and the mix still on sale shifts between register readings. If the record on this page is what brought you here, ask me what is currently available while the build is still at foundation level.

Ask About Remaining Availability on WhatsApp

Stage Record

City Walk Crestlane 2 Build Stages, Mapped to the Inspections

Each stage below is pinned to the dates City Walk Crestlane 2 has actually logged, from registration on 06 February 2025 to the 6.83% reading of 08 October 2026. The later stages carry no dates yet, because the register has not reached them.

Feb 2025 to Apr 2025

Registration and Construction Start

Project 3530 entered the DLD register on 06 February 2025, and the construction start followed on 16 April 2025, 69 days later.

Current PhaseJun 2026 to Oct 2026, 6.83% at last reading

Enabling, Piling, and Foundations

Both dated readings sit here: 5.20% on 12 June 2026 and 6.83% on 08 October 2026, when RERA recorded enabling, piling and foundation works progressing.

Next on the register, not yet dated

Shared Basement and Ground Floor

The single basement level under both buildings, then the ground floor with the main lobby and its two retail units, none of it recorded as built at 6.83% on 08 October 2026.

After the ground floor, not yet dated

Building A and Building B Frames

Floors rising to G+12 on Building A and G+11 on Building B; neither frame appears in the RERA notes of the 08 October 2026 inspection.

Toward the Q4 2028 handover

Facades, Interiors, Landscape, and Handover

Facades, interiors for 201 residences, and the pools and water features, ending at the Q4 2028 handover; the registered completion date is 10 December 2028.

What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on City Walk Crestlane 2's own record.

Buyer Position

Tracking Your Position at City Walk Crestlane 2

This page is one of four project resources that together cover a City Walk Crestlane 2 purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

City Walk Crestlane 2 by Meraas in City Walk construction updates cover image featuring a project rendering of illuminated residential blocks with landscaped walkways at dusk in Dubai - Presented by Tohid Fetrat
You Are Here

City Walk Crestlane 2 Construction Updates

This page: each DLD register reading for City Walk Crestlane 2, from construction start to handover.

City Walk Crestlane 2 by Meraas in City Walk Golden Visa concept graphic showing a gold visa card over a rendered garden terrace beside residential buildings in Dubai - Presented by Tohid Fetrat

Crestlane 2 Golden Visa: Eligible on Price Across All Six Unit Types

City Walk Crestlane 2 by Meraas qualifies for the AED 2M Golden Visa at every unit type, from 1 bedroom apartment.

Read the City Walk Crestlane 2 Golden Visa Guide
City Walk Crestlane 2 by Meraas in City Walk escrow account concept graphic showing a shield and padlock beside a rendered residential balcony and facade in Dubai - Presented by Tohid Fetrat

Crestlane 2 Escrow: Abu Dhabi Commercial Bank and the 75/25 Plan

City Walk Crestlane 2, DLD project 3530, escrows 201 units at Abu Dhabi Commercial Bank and read 6.83% in October 2026.

Verify the City Walk Crestlane 2 Escrow Account

Approaching Handover

Between 6.83% and Handover: What City Walk Crestlane 2 Buyers Should Do Now

City Walk Crestlane 2 buyers will see little change on site between the foundations recorded on 08 October 2026 and the first floors of Building A and Building B, yet their payments keep moving with the calendar. On the developer's dated launch schedule, the 20% booking share plus four instalments add up to 55% of the price by September 2026, set against a register reading of 6.83% on 08 October 2026; the two figures count different things, so this is schedule arithmetic, not a judgment on progress.

The next date on that launch schedule is February 2027, and for a purchase made now Meraas confirms the dates that apply in the SPA, so the three steps below belong before that date rather than after it.

First, make sure every payment goes only into the escrow account registered for project 3530 with ADCB; the City Walk Crestlane 2 escrow account page shows how to match the account details in your SPA digit by digit.

Second, if residency is part of the plan, work through the City Walk Crestlane 2 Golden Visa guide now, since every unit type is priced above the threshold and the application timing runs alongside the Q4 2028 handover.

Third, judge the build reading by reading rather than by headline: the October 2026 construction update for City Walk Crestlane 2 sets out the 6.83% reading and the RERA site notes that go with it, and each later dated reading joins the timeline above.

Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.

The Wider Picture

Explore City Walk Structure

Two buildings at foundation level are easier to judge against what already stands around them. These three pages place City Walk Crestlane 2 within its market, its district, and its developer:

Aerial view of City Walk properties for sale in Dubai showing modern residential buildings, landscaped community spaces and surrounding urban development, Presented by Tohid Fetrat

City Walk: Crestlane Apartments in the Meraas Lifestyle District Facing Downtown Dubai

City Walk is the Meraas lifestyle district in Al Wasl facing Downtown Dubai, with Crestlane apartments on a 75/25 payment plan.

See City Walk Properties for Sale
Aerial view of City Walk community in Dubai showing modern residential buildings, landscaped public spaces and the surrounding city skyline, Presented by Tohid Fetrat

City Walk: Meraas's Urban Quarter With Coca-Cola Arena and Central Park

City Walk is an urban district in Al Wasl with low and mid-rise residences, 236 retail outlets and Burj Khalifa views.

Explore the City Walk Community
Meraas developer Dubai – luxury residential towers including Atélis, Jumeirah Residences, The Edit, Verve City Walk, and Bluewaters Bay

Meraas: Lifestyle Destinations From City Walk to Port de La Mer

Meraas is the name behind City Walk, Bluewaters Island and Madinat Jumeirah Living, from beachfront communities to luxury mixed-use districts.

View the Meraas Developer Profile

Construction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.

FAQs

City Walk Crestlane 2 Construction Updates Frequently Asked Questions

City Walk Crestlane 2 is an active project on the DLD register (number 3530), recorded at 6.83% on 08 October 2026, and the RERA progress report of that date lists the main contract as progressing through enabling, piling and foundation works. Both dated readings are set out in the inspection timeline above.

The City Walk Crestlane 2 timeline compares two dated DLD register readings: 5.20% on 12 June 2026 and 6.83% on 08 October 2026, a rise of 1.63 points over 118 days. Earlier inspection records also exist in the DLD register. The later reading and its RERA site notes are covered on the October 2026 inspection page.

Between 12 June 2026 and 08 October 2026 the City Walk Crestlane 2 register reading rose by about 0.41 points per 30-day month, and averaged over the 540 days from the 16 April 2025 construction start to the 6.83% reading of 08 October 2026 it comes to about 0.38 points per month. Both figures are arithmetic, not a forecast: at the piling and foundation stage, readings usually climb slowly until the structure rises. All four pace lines are in the pace analysis above.

The two agree: the DLD register lists 10 December 2028 as the registered completion date for City Walk Crestlane 2 (project 3530), and that date falls inside the Q4 2028 quarter in which handover is expected. Closing the 93.17 points left after the 6.83% reading of 08 October 2026 within the 794 days to the registered date implies roughly 3.52 points per 30-day month, which is arithmetic, not a forecast; this record is updated as each new reading appears.

City Walk Crestlane 2 consists of two mid-rise residential buildings, Building A at G+12 and Building B at G+11 (coded B+G+12+R and B+G+11+R in the RERA progress report of 08 October 2026), set over one shared basement level, with two retail units beside the main lobby on the ground floor and 201 residences in total. Layouts by unit type are in the City Walk Crestlane 2 project guide.

The DLD register records the City Walk Crestlane 2 construction start on 16 April 2025, 69 days after project 3530 was registered on 06 February 2025. The 5.20% reading on 12 June 2026, selected for comparison in this timeline, came 422 days after that start.

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is keeping the City Walk Crestlane 2 construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.