City Walk Crestlane 3 by Meraas in City Walk construction updates cover image featuring a project rendering of residential buildings surrounding landscaped swimming pools in Dubai - Presented by Tohid Fetrat

Meraas · City Walk

City Walk Crestlane 3 Construction Updates

Two Water-Facing Buildings, One Dated Register Record in City Walk

City Walk Crestlane 3 read 4.59% on the DLD register at the 15 September 2026 inspection, as enabling and piling works prepared ground for both water-facing buildings.

Construction tracking against RERA inspection data, updated after every recorded inspection.

Direct advisor access. Every message answered personally, never by a call center.

4.59%Construction Progress
15 September 2026Latest RERA Inspection
193 residential unitsTotal Units
Project 3531DLD Registration

Construction Snapshot

City Walk Crestlane 3 at a Glance

City Walk Crestlane 3 is a 193-residence Meraas release in City Walk, entered on the Dubai Land Department register as project 3531 on 6 February 2025, with a registered construction start of 16 April 2025. Its register reading of 4.59% at 15 September 2026 belongs to the ground phase: the RERA report for that visit records enabling and piling works, the foundation package for two mid-rise buildings, G+11 and G+10, that will stand on one shared basement. Because both buildings rise from that single basement, every reading on this record so far measures common groundwork rather than two separate structures.

DLD Project Number

3531

Project Status

Active

Construction Start

16 April 2025

Total Units

193 residential units

Total Built-Up Area

24,583.18 sq m

Registered Completion Date

10 December 2028 (DLD)

Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.

Inspection Record

City Walk Crestlane 3 Construction Update Timeline

This record logs two dated register readings so far: 0.70% on 16 June 2026 and 4.59% on 15 September 2026, taken 91 days apart and both inside the enabling and piling phase. The June reading is logged here as a register entry without a monthly page of its own, while the September reading links to its full update, the page that opens the monthly series for City Walk Crestlane 3. Each dot on the track marks one dated reading, measured against the 100% that handover requires.

Inspection MonthConstruction ProgressInspection DateFull Update
September 20264.59%15 September 2026View the September 2026 update

Pace Analysis

How Fast City Walk Crestlane 3 Has Been Built

Two dated register readings give this record one measured interval, and the register's own start and completion dates frame it on either side. Every rate below is arithmetic on recorded dates, not a forecast:

  • Jun 2026 to Sep 2026: enabling and piling, 0.70% to 4.59%About 1.28 points per 30-day month
  • Apr 2025 to Sep 2026: average since the registered start, up to 4.59%About 0.27 points per 30-day month
  • Sep 2026 to Dec 2028: rate implied to the registered completion date, 4.59% to 100%About 3.50 points per 30-day month

Of the 4.59 points on the register at 15 September 2026, 3.89 were logged in the 91 days after the 16 June 2026 reading, so most of this record's movement sits in a single quarter of enabling and piling work. Spread across the whole span since the registered start of 16 April 2025, the average falls to about 0.27 points per 30-day month, because the register stood at only 0.70% by June 2026, 426 days after that start. Set against the calendar, 517 of the 1,334 days between the registered start and the registered completion date of 10 December 2028 had passed by September 2026, about 38.8% of the window, while the reading stood at 4.59%; that is arithmetic, not a verdict, since basement, structure, fit-out and building services typically move the percentage faster than ground preparation does. Reaching 100% by the registered date works out at about 3.50 points per 30-day month from the September 2026 reading, or about 3.42 to the end of Q4 2028. For an end user, the reading to watch is the one that records basement or structural work at Crestlane 3; for an investor, it is whether later intervals climb toward the rate the remaining window implies, judged one dated reading at a time.

Get the Next Inspection Figure First

Tell me you are tracking City Walk Crestlane 3 and I will send you the next recorded figure and site photos directly, ahead of the page update.

Get the Next Update on WhatsApp

Project Profile

About City Walk Crestlane 3 at City Walk

A register reading at the piling stage says little until it is set next to the finished project. The full project guide covers what buyers are tracking toward on this page:

City Walk Crestlane 3 by Meraas in City Walk project rendering of residential buildings with illuminated windows and landscaped gardens at dusk in Dubai - Presented by Tohid Fetrat

City Walk Crestlane 3: Water-Facing Apartments and 4 Bedroom Duplexes

City Walk Crestlane 3 is a Meraas project of 193 residences in two mid-rise buildings, every one facing the water.

View the City Walk Crestlane 3 Project Guide

Considering an Early-Stage Entry?

Meraas lists limited units available at City Walk Crestlane 3, and the choice of layouts and views tends to narrow as a build moves from groundworks to structure. If this record is what brought you here, ask me what is available today and how the September 2026 reading fits your own timeline.

Ask About Remaining Availability on WhatsApp

Stage Record

City Walk Crestlane 3 Build Stages, Mapped to the Inspections

Each stage below is pinned to the register dates and readings City Walk Crestlane 3 has actually logged, from its February 2025 registration to the registered completion date of 10 December 2028, so the current position reads against this project's own calendar rather than a generic sequence.

Feb 2025 to Apr 2025

Registration and Registered Start

Project 3531 entered the DLD register on 6 February 2025, and the register dates the construction start 69 days later, on 16 April 2025.

Current PhaseApr 2025 onward, 4.59% at 15 Sep 2026

Enabling Works and Piling

The register read 0.70% on 16 June 2026 and 4.59% on 15 September 2026, when RERA recorded enabling and piling works progressing on site.

Not yet recorded

Shared Basement and Ground Floor

Next on this record: the one-level basement shared by both buildings, and a ground floor with two retail units beside the main lobby.

Not yet recorded

Building A and Building B Structure

Building A rises to G+11 and Building B to G+10, the two water-facing residential buildings above the shared basement.

To 10 Dec 2028, registered

Fit-Out, Amenities, and Handover

Interiors, building services, pools and water features, closing at the registered completion date of 10 December 2028, inside the expected Q4 2028 handover.

What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on City Walk Crestlane 3's own record.

Buyer Position

Tracking Your Position at City Walk Crestlane 3

This page is one of four project resources that together cover a City Walk Crestlane 3 purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

City Walk Crestlane 3 by Meraas in City Walk construction updates cover image featuring a project rendering of residential buildings surrounding landscaped swimming pools in Dubai - Presented by Tohid Fetrat
You Are Here

City Walk Crestlane 3 Construction Updates

This page: the dated DLD register record for City Walk Crestlane 3, from registration to handover.

City Walk Crestlane 3 by Meraas in City Walk Golden Visa concept graphic with a gold card over a landscaped pool and residential buildings in Dubai - Presented by Tohid Fetrat

City Walk Crestlane 3 Golden Visa for Water-Facing Apartments and Duplexes

City Walk Crestlane 3 by Meraas clears the AED 2M Golden Visa threshold with every unit type, 1 bedroom apartment included.

Read the City Walk Crestlane 3 Golden Visa Guide
City Walk Crestlane 3 by Meraas in City Walk escrow account concept image with a shield and padlock graphic above an illuminated residential courtyard in Dubai - Presented by Tohid Fetrat

City Walk Crestlane 3 Escrow Account at ADCB for DLD Project 3531

City Walk Crestlane 3, DLD project 3531, escrows 193 units at Abu Dhabi Commercial Bank and read 4.59% in September 2026.

Verify the City Walk Crestlane 3 Escrow Account

Approaching Handover

Between 4.59% and Handover: What City Walk Crestlane 3 Buyers Should Do Now

At 4.59% on the register at 15 September 2026, City Walk Crestlane 3 is still preparing the ground for its shared basement, while by the developer's dated launch schedule 55% of the price was scheduled by September 2026: schedule arithmetic on a date-based plan, not a delay finding, and the schedule that applies to a purchase now is set by Meraas in the SPA. The next dated instalment on that published schedule falls in February 2027, so the three checks below belong before that transfer rather than after it.

First, confirm that every instalment goes into the DLD-registered escrow account held with Abu Dhabi Commercial Bank (ADCB) for project 3531; the City Walk Crestlane 3 escrow account page shows how to check the account against the DLD record.

Second, if residency is part of your plan, settle eligibility well before handover through the City Walk Crestlane 3 Golden Visa guide, since buying off-plan ahead of a Q4 2028 handover shapes the application path.

Third, read your SPA dates against the dated readings: the September 2026 inspection report for City Walk Crestlane 3 carries the detail behind the 4.59% reading, and the timeline above adds each later reading as it is logged.

Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.

The Wider Picture

Explore City Walk Structure

A register reading describes one plot; the pages below describe the market, the district and the developer around it, each read for what it means while Crestlane 3 is in its enabling and piling stage:

Aerial view of City Walk properties for sale in Dubai showing modern residential buildings, landscaped community spaces and surrounding urban development, Presented by Tohid Fetrat

City Walk: Crestlane Apartments in the Meraas Lifestyle District Facing Downtown Dubai

City Walk is the Meraas lifestyle district in Al Wasl facing Downtown Dubai, with Crestlane apartments on a 75/25 payment plan.

See City Walk Properties for Sale
Aerial view of City Walk community in Dubai showing modern residential buildings, landscaped public spaces and the surrounding city skyline, Presented by Tohid Fetrat

City Walk: Meraas's Urban Quarter With Coca-Cola Arena and Central Park

City Walk is an urban district in Al Wasl with low and mid-rise residences, 236 retail outlets and Burj Khalifa views.

Explore the City Walk Community
Meraas developer Dubai – luxury residential towers including Atélis, Jumeirah Residences, The Edit, Verve City Walk, and Bluewaters Bay

Meraas: Lifestyle Destinations From City Walk to Port de La Mer

Meraas is the name behind City Walk, Bluewaters Island and Madinat Jumeirah Living, from beachfront communities to luxury mixed-use districts.

View the Meraas Developer Profile

Construction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.

FAQs

City Walk Crestlane 3 Construction Updates Frequently Asked Questions

City Walk Crestlane 3 is an active DLD-registered project (number 3531) in its enabling and piling stage, at 4.59% on the DLD register for the inspection of 15 September 2026. The RERA progress report of that date records the status as Enabling Works, Progressing, and every dated reading is listed in the inspection timeline above.

This page logs two dated DLD register readings for City Walk Crestlane 3: 0.70% on 16 June 2026 and 4.59% on 15 September 2026, a rise of 3.89 points in 91 days. The September reading has its own report in the City Walk Crestlane 3 September 2026 construction update; the June reading is logged here without a separate page, and the Dubai REST inspection list for project 3531 is the authoritative place to check for any entry not shown here.

The DLD register gives City Walk Crestlane 3 a registered completion date of 10 December 2028, which falls inside the expected Q4 2028 handover, so the two dates agree. At the 4.59% reading of 15 September 2026 that registered date was 817 days away; actual handover is confirmed by Meraas as completion approaches, and this record adds each dated reading in between.

City Walk Crestlane 3 has 193 residences in two mid-rise buildings over a one-level shared basement, with two ground-floor retail units beside the main lobby. The RERA progress report of 15 September 2026 configures Building A as B+G+11+R with 112 units and Building B as B+G+10+R with 81 units; layouts from 1 bedroom apartments to 4 bedroom duplexes are covered in the City Walk Crestlane 3 project guide.

Between the 16 June 2026 and 15 September 2026 readings, City Walk Crestlane 3 moved about 1.28 points per 30-day month, while the average since the registered start of 16 April 2025 is about 0.27 points per 30-day month up to the 4.59% recorded on 15 September 2026. Reaching 100% by the registered completion date of 10 December 2028 implies about 3.50 points per 30-day month from that reading; all three figures are arithmetic on recorded dates, not a forecast, and the full breakdown is in the pace analysis above.

The DLD register dates the City Walk Crestlane 3 construction start to 16 April 2025, 69 days after the project was registered on 6 February 2025. The earliest dated reading logged on this page is 0.70% on 16 June 2026, 426 days after that registered start.

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is keeping the City Walk Crestlane 3 construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.

Ask your question, get your answer. No obligation and no follow-up unless you ask for it.

WhatsApp +971543443597
Get the Latest Status