Meraas · City Walk
City Walk Crestlane 4 Construction Updates
The Register Record for Two Mid-Rise Buildings off Al Wasl Road
City Walk Crestlane 4 read 0.01% on the DLD register on 06 October 2026, its first dated figure and the pre-construction baseline for both mid-rise buildings.
Construction tracking against RERA inspection data, updated after every recorded inspection.
Direct advisor access. Every message answered personally, never by a call center.
Construction Snapshot
City Walk Crestlane 4 at a Glance
City Walk Crestlane 4 is a Meraas release of 201 residences in two mid-rise buildings on the Al Wasl Road side of City Walk, entered on the DLD register as project 4286 on 23 December 2025. The register sets 25 February 2026 as the construction start, 64 days after registration, and 25 April 2030 as the registered completion date, a day that falls inside the expected Q2 2030 handover. What sets this record apart is the distance between paper and plot: the RERA progress report of 06 October 2026 lists the status as Pre-Construction (On Hold) and notes that no construction activities had started at the site. Both entries stand as recorded, and the current site position is one to confirm with Meraas and on Dubai REST before paying.
4286
Active
25 February 2026
201 residential units
27,943.06 sq m
25 April 2030 (DLD)
Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.
Inspection Record
City Walk Crestlane 4 Construction Update Timeline
The record so far holds one dated reading: 0.01% on the DLD register at the inspection of 06 October 2026, a little over seven months after the 25 February 2026 register start. The register also shows a previous inspection at the same 0.01%, but without a date, so it sits on the track below as an unlabelled dot rather than as a table row. The table links the full October 2026 update, and each new dated reading joins it as it appears.
| Inspection Month | Construction Progress | Inspection Date | Full Update |
|---|---|---|---|
| October 2026 | 0.01% | 06 October 2026 | View the October 2026 update |
Pace Analysis
How Fast City Walk Crestlane 4 Has Been Built
A measured pace needs two dated readings, and City Walk Crestlane 4 has one, so the figures below are arithmetic from the register dates, not a forecast:
- Previous inspection (no date) to 06 Oct 2026: 0.01% to 0.01%No measurable pace
- 25 Feb 2026 register start to 06 Oct 2026: 0.01 points over 223 daysEffectively zero
- 06 Oct 2026 to 25 Apr 2030 registered completion: 99.99 points over 1,297 daysAbout 2.31 points per month
- 06 Oct 2026 to 30 Jun 2030, end of Q2 2030: 99.99 points over 1,363 daysAbout 2.20 points per month
The curve has not bent yet: the register has held 0.01% across both readings on record, and the RERA report of 06 October 2026 places the project at Pre-Construction (On Hold) with no site works noted. Pre-construction comes before structure, so a near-zero reading at this point is not by itself a sign of delay, and the two rates above, about 2.31 points per 30-day month to 25 April 2030 and about 2.20 to the close of Q2 2030, are simply what the remaining 99.99 points divide into. The developer's dated schedule runs on its own clock: by its terms 35% of the price (20% on booking, 10% in May 2026, 5% in September 2026) was scheduled by September 2026, while the register read 0.01% on 06 October 2026, which is schedule arithmetic, not a delay claim. For an end user, the figure to watch is the first dated reading above 0.01%, the first sign of site works on the register; for an investor, it is how that reading sits against the dated instalments still to come before the 25% due on handover.
Get the Next Inspection Figure First
Tell me you are tracking City Walk Crestlane 4 and I will send you the next recorded figure and site photos directly, ahead of the page update.
Get the Next Update on WhatsAppProject Profile
About City Walk Crestlane 4 at City Walk
A register reading only means something next to what it measures. The project guide covers the building this record is tracking toward:

City Walk Crestlane 4: Park Duplexes and Water-Facing Apartments by Meraas
City Walk Crestlane 4 by Meraas has 201 residences in two mid-rise City Walk buildings, mixing apartments with park duplexes.
View the City Walk Crestlane 4 Project GuideConsidering a Pre-Construction Entry?
Meraas currently lists limited units available at City Walk Crestlane 4, and what remains can change between one register reading and the next. If this record is what brought you here, ask me for current availability before settling on a unit type.
Ask About Remaining Availability on WhatsAppStage Record
City Walk Crestlane 4 Build Stages, Mapped to the Inspections
Each stage below is tied to the dates the register actually holds for City Walk Crestlane 4, so the first card is the only one with readings behind it so far; the other four show what the 06 October 2026 report describes as still to be built.
Registration and Pre-Construction
Registered on 23 December 2025 with a register start of 25 February 2026; on 06 October 2026 the register read 0.01% and the RERA status was Pre-Construction (On Hold), with no site works noted.
Shared Basement and Ground Level
The one-level basement shared by both buildings, plus a ground floor with three retail units beside the main lobby; no reading up to 06 October 2026 reflects these works.
Building A and Building B Superstructure
Floors rising on Building A to G+12 and Building B to G+10, the stage that carries the 201 residences, starting from the 0.01% register base of 06 October 2026.
Facade, Fit-Out, and Water Landscaping
Enclosure and interiors for both buildings, then the water features, pools and park landscaping the brochure places at the centre of the plot; none recorded as of 06 October 2026.
Finishing, Commissioning, and Handover
Final works and handover, expected in Q2 2030; the registered completion date of 25 April 2030 falls inside that quarter, 1,297 days after the 06 October 2026 reading.
What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on City Walk Crestlane 4's own record.
Buyer Position
Tracking Your Position at City Walk Crestlane 4
This page is one of four project resources that together cover a City Walk Crestlane 4 purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

City Walk Crestlane 4 Construction Updates
This page: the dated DLD register record for City Walk Crestlane 4, from registration to handover.

Crestlane 4 Golden Visa: Every Apartment Type Above the Residency Line
City Walk Crestlane 4, a Meraas project in City Walk, clears the AED 2M Golden Visa threshold with every apartment type.
Read the City Walk Crestlane 4 Golden Visa Guide
City Walk Crestlane 4 Escrow Account With First Abu Dhabi Bank
City Walk Crestlane 4, DLD project 4286, escrows 201 units at First Abu Dhabi Bank and read 0.01% in October 2026.
Verify the City Walk Crestlane 4 Escrow AccountApproaching Handover
Between 0.01% and Handover: What City Walk Crestlane 4 Buyers Should Do Now
With the register at 0.01% on 06 October 2026 and no site works noted, the steps that matter now concern payments and paperwork rather than the building. The dated schedule does not wait for the site: the May 2026 and September 2026 instalment dates already fall before today, so the three steps below belong before your next transfer, not after the first structural reading.
First, check that every transfer goes to the escrow account registered for project 4286; the City Walk Crestlane 4 escrow account page shows how to match the account against the DLD record.
Second, if residency is part of the plan, settle eligibility well ahead of the Q2 2030 handover through the City Walk Crestlane 4 Golden Visa guide, since all six unit types start above the AED 2M property threshold.
Third, read each new dated reading as it lands, starting with the October 2026 City Walk Crestlane 4 inspection update, and confirm the current site status with Meraas and on Dubai REST before paying.
Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.
The Wider Picture
Explore City Walk Structure
A plot at 0.01% in October 2026 is only part of the picture; the rest is the finished district around it and the developer building it. These three pages supply that context:

City Walk: Crestlane Apartments in the Meraas Lifestyle District Facing Downtown Dubai
City Walk is the Meraas lifestyle district in Al Wasl facing Downtown Dubai, with Crestlane apartments on a 75/25 payment plan.
See City Walk Properties for Sale
City Walk: Meraas's Urban Quarter With Coca-Cola Arena and Central Park
City Walk is an urban district in Al Wasl with low and mid-rise residences, 236 retail outlets and Burj Khalifa views.
Explore the City Walk Community
Meraas: Lifestyle Destinations From City Walk to Port de La Mer
Meraas is the name behind City Walk, Bluewaters Island and Madinat Jumeirah Living, from beachfront communities to luxury mixed-use districts.
View the Meraas Developer ProfileConstruction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.
FAQs
City Walk Crestlane 4 Construction Updates Frequently Asked Questions
City Walk Crestlane 4 is an active DLD-registered project, number 4286, recorded at 0.01% on the DLD register at the inspection of 06 October 2026. The RERA progress report for that date lists the status as Pre-Construction (On Hold) and notes that no construction activities had started at the site; the full record is in the inspection timeline above.
Two readings are on record for City Walk Crestlane 4, both at 0.01%: the current reading dated 06 October 2026 and a previous inspection that the register shows without a date, a change of 0.00 points. Only the 06 October 2026 reading carries a date, so it is the single row in the timeline table, and its full detail is in the October 2026 construction update for City Walk Crestlane 4.
The DLD register gives City Walk Crestlane 4 a registered completion date of 25 April 2030, which falls inside the expected Q2 2030 handover, so the two agree. That date was set on the register when the project was registered on 23 December 2025; the reading measured against it was 0.01% on 06 October 2026, and this page is updated with each new dated reading.
City Walk Crestlane 4 holds 201 residential units in two mid-rise buildings over one shared basement, with three retail units at ground level beside the main lobby. The RERA report of 06 October 2026 lists Building A as B+G+12+R with 110 units and Building B as B+G+10+R with 91 units; layouts and unit types are covered in the City Walk Crestlane 4 project guide.
Progress at City Walk Crestlane 4 is tracked through the DLD project register for project 4286, whose 0.01% reading of 06 October 2026 is the figure on this page, alongside the RERA progress report for the same inspection, which records the status and site notes but prints no percentage. Each new dated reading is added to the timeline, and the method used across this site is set out on the Dubai Construction Updates hub.
As arithmetic rather than a forecast, the 99.99 points remaining after the 0.01% reading of 06 October 2026 average about 2.31 points per 30-day month to the registered completion date of 25 April 2030, and about 2.20 points per month to the end of Q2 2030. No measured pace exists yet, because the only other reading has no date; the breakdown is in the pace arithmetic above.

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is keeping the City Walk Crestlane 4 construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.
Ask your question, get your answer. No obligation and no follow-up unless you ask for it.