Emaar · Rashid Yachts & Marina · Construction Update
Clearpoint at Rashid Yachts & Marina Construction Update - April 2026
April 2026 DLD Register Reading Places Clearpoint at 45.05% Construction Progress in Rashid Yachts & Marina
Superstructure, envelope, MEP and finishing works were progressing across Clearpoint's three buildings at the April 2026 inspection; the backdrop is a developer rendering, not a site photograph.
Direct advisor access. Every message answered personally, never by a call center.
Verified DLD Inspection Data
Clearpoint Construction Snapshot
A 12.77 point difference from the previous register reading of 32.28%, an earlier inspection whose date the record does not show, brings Clearpoint to 45.05% on 21 April 2026: mid-construction, with the superstructure still progressing while envelope and MEP works run alongside it.
Clearpoint
2743
Active
45.05%
21 April 2026
9 November 2023
477 Residential Units
53,820.71 sq m
Q3 2027
Data source: Dubai Land Department project register reading for project 2743 dated 21 April 2026, the latest reading in the record supplied for this update, read with the RERA Independent Progress Monitoring Report for the same inspection, which describes the works but prints no percentage. The image at the top of this page is a developer rendering of the planned project, not a photograph of the site. Construction tracking against RERA inspection data runs across the full tohidfetrat.com project portfolio and is reviewed after every published cycle. Last updated: April 2026.
Want each new reading the day it publishes? Message me on WhatsApp and I will send it to you directly: one message per inspection cycle, nothing else. Message me on WhatsApp
This Inspection Cycle
Clearpoint Construction Progress Summary
The 21 April 2026 inspection found Clearpoint's groundwork phase finished: enabling, piling, foundation and substructure works were recorded as completed, and every remaining package, from the superstructure to the external works, was progressing. Set side by side, the record gives 894 days from the 9 November 2023 construction start to that reading and 54.95 points still to be recorded before 100%, calendar and register arithmetic rather than a forecast, against a Q3 2027 expected handover.
- Enabling works across the Clearpoint plot
- Piling and foundation works
- Substructure works beneath the three buildings
- Superstructure of the three G+10+R residential buildings
- External envelope
- MEP: mechanical, electrical and plumbing works
- Internal works and internal finishes
- External works around the buildings
- Further Dubai Land Department register readings toward 100%
- Completion of every package still progressing in April 2026
- Final inspections and completion formalities with the Dubai authorities
- Handover of the 477 residential units, expected in Q3 2027
Payment Linked Progress
What 45.05% Progress Means for Clearpoint Buyers
Clearpoint's plan places 80% of the price in the construction period, between 10% on booking and 10% upon handover, so the 45.05% register reading falls in the middle of the stretch where most of a buyer's money is paid. At this stage of the build, four actions matter most.
Verify the escrow account
Every instalment of the 80% construction share should go only to the DLD regulated escrow account registered for project 2743 with Emirates NBD. Clearpoint escrow account verification comes before any transfer; the lookup itself takes about two minutes against the official DLD project record.
Reread your SPA milestone schedule
Check how your sale and purchase agreement times the construction instalments and what it says about the handover notice, then set those clauses against the 45.05% reading and the Q3 2027 expected handover. Not sure how your instalments map to this reading? Send me your SPA schedule and I will map it against the recorded register readings.
Confirm your Oqood registration
A Clearpoint unit bought off plan is recorded with the Dubai Land Department through Oqood, the interim registration that ties your name and unit to project 2743 until title is issued after completion. Check that the entry matches your SPA before the next construction instalment falls due.
Track the remaining cycles
At 45.05%, the larger share of Clearpoint's recorded progress was still ahead in April 2026, so further readings will land while construction instalments are being paid. The Clearpoint construction updates hub adds each reading as it is posted.
General framework, not legal advice: milestone definitions, notice periods, and fee obligations are set by your individual SPA and the DLD record, and both should be read directly.
Buying at 45.05%?
Entering Clearpoint mid-construction trades some payment-plan runway for evidence: the groundwork is recorded as complete, the remaining packages are under way, and the choice narrows to the units still on offer. Every payment goes to the DLD-registered escrow account for project 2743, released against verified construction progress.
- Enabling, piling, foundation and substructure recorded complete on 21 April 2026
- Handover expected in Q3 2027
- Construction instalments already due under Emaar's current terms are settled at signing
- Excavation and foundation risk carried from the first payment
- The longest wait between booking and handover
- Instalments spread across the whole build at launch pricing
2 Units Available on the Clearpoint project page as of this page's publication; availability shifts between cycles.
About the Development
Clearpoint Project Details

With its substructure recorded as complete at the April 2026 inspection, Clearpoint is a mid-construction Emaar project of 477 residential units in three G+10+R buildings, split between 1, 2 and 3 bedroom apartments and 3 bedroom duplexes laid out over two levels. Starting prices: AED 2.26M ≈ USD 616K.
Buying at this stage means joining part way through the 80% construction share rather than at its start, with handover expected in Q3 2027 and envelope and MEP works still progressing at the last recorded inspection.
Clearpoint at Rashid Yachts & Marina Project GuideSite Context This Cycle
Explore Clearpoint Location on Dubai Map
Clearpoint's plot in Rashid Yachts & Marina has landscaped green space wrapping three of its sides and Emaar's Seagate, Seascape and Sunridge as neighbours, with its three midrise buildings planned around a shared landscaped podium. On a compact three-building site, the grounds and podium are built around structures that are still going up, which is consistent with the April 2026 record listing external works as progressing alongside the superstructure and envelope.
Rashid Yachts & Marina is a masterplanned Emaar marina district at Mina Rashid, beside one of Dubai's oldest neighbourhoods, with a 430-berth marina, a promenade, and a developer masterplan that places a school, a mosque and a ferry station inside the community. For Clearpoint buyers at this stage, the useful question is how much of that district will be operating around a Q3 2027 handover, which is worth weighing before further instalments are committed. See the project's position on the interactive Dubai real estate map. See the project’s position on the interactive Dubai real estate map.

Buyer Resources for This Project
Investing in Clearpoint During Mid-Construction Progress
Mid-construction is when most of Clearpoint's instalments are being paid, so payment protection and residency planning carry the most weight now. Each resource below is matched to where the project stood at the April 2026 inspection.

Clearpoint Construction Updates
This page: the 21 April 2026 inspection record for Clearpoint, read at the 45.05% register reading.

Clearpoint at Rashid Yachts & Marina Golden Visa: Three G+10+R Buildings
Clearpoint at Rashid Yachts & Marina, 477 Emaar residences in Mina Rashid, starts all four unit types above the threshold.
Read Clearpoint Golden Visa Guide
Clearpoint at Rashid Yachts & Marina: The 478-Unit Emirates NBD Escrow
Emirates NBD keeps Clearpoint at Rashid Yachts & Marina escrow, DLD project 2743, its 478 units 45.05% certified April 2026.
Verify Clearpoint Escrow AccountUpdate Timeline
Other Clearpoint Construction Updates
April 2026 is the first Clearpoint inspection covered in this series; later readings join the hub as each one is recorded in the Dubai Land Department register.
Where This Update Fits
Explore Clearpoint Structure
This April 2026 record is one part of a larger picture: the marina district Clearpoint belongs to, the developer building it, and the apartments competing with it for the same buyers.

Mina Rashid Properties for Sale
Browse waterfront apartments for sale at Rashid Yachts & Marina, with projects, prices and payment plans.
See Mina Rashid Properties for Sale
Mina Rashid Community Overview
Read the Rashid Yachts & Marina guide: Emaar's transformation of historic Port Rashid into a marina lifestyle community.
Explore the Mina Rashid Community
Emaar Properties: Burj Khalifa, Downtown Dubai and Twenty Master Communities
Emaar, founded in 1997, built Burj Khalifa and Downtown Dubai and has delivered over 85,000 homes across twenty master communities.
View the Emaar Properties Developer ProfileFAQs
Clearpoint Construction Progress in April 2026: Frequently Asked Questions
The Dubai Land Department project register recorded Clearpoint, project 2743, at 45.05% construction progress following the inspection of 21 April 2026. The RERA progress report for that inspection describes the works on site but prints no percentage of its own, so 45.05% is a register reading. It is the latest reading in the record supplied for this update, and the register may since show a newer figure.
The register's inspection card shows a previous reading of 32.28% beside the current 45.05%, but it does not display the date of that earlier inspection. Without a date, the gap between the two readings cannot be turned into a monthly pace or a time span, so this page plots 32.28% as a reference point only and draws no conclusion about speed.
The RERA progress report for the 21 April 2026 inspection recorded enabling, piling, foundation and substructure works as completed. Superstructure, internal works, external envelope, MEP, internal finishes and external works were progressing, and the overall status was given as Main Contract, Progressing. The report covers three residential buildings, each ground plus ten floors plus roof, and carries inspection photographs that are not reproduced on this page.
The reading itself carries no handover date: handover remains expected in Q3 2027, and on 21 April 2026 the register showed 54.95 percentage points still to be recorded before 100%. Expected dates can be revised between inspection cycles, so the Q3 2027 expectation is best read alongside each new reading rather than treated as fixed. How readings build toward completion over the life of the project is covered on the Clearpoint construction updates hub.
The Dubai Land Department register records Clearpoint as registered on 5 September 2023, with construction started on 9 November 2023, 65 days later. From that start date to the 21 April 2026 inspection is 894 days, a span given here as calendar arithmetic only, not as a measure of pace or a forecast.
No. The hero image is a developer rendering of the planned landscaped garden and residential buildings, used to illustrate this update; it is not photographic evidence of the site on 21 April 2026. The construction status on this page comes only from the Dubai Land Department register reading and the written notes of the RERA progress report.
A Question the FAQ Can Not Answer?

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is helping you read the April 2026 inspection record for Clearpoint at Rashid Yachts & Marina correctly before your next payment decision. Client identities and transactions are never published or referenced. Message me directly: you will always reach me personally, never a call center or sales team.
Ask your question, get your answer. No obligation and no follow-up unless you ask for it.