
Imtiaz Developments · Dubai Islands · Construction Update
Cotier House 2 Construction Update - July 2026
July 2026 DLD Register Reading Places Cotier House 2 at 16.06% Construction Progress on Dubai Islands
With enabling and foundation works recorded complete, structure and MEP works were progressing at Cotier House 2 on Dubai Islands when RERA inspected on 20 July 2026.
Direct advisor access. Every message answered personally, never by a call center.
Verified DLD Inspection Data
Cotier House 2 Construction Snapshot
A 16.06% DLD register reading on 20 July 2026 places Cotier House 2 in the enabling and foundations band, the stage where a buyer's protection rests on registration and the escrow account rather than on the building itself.
Cotier House 2 by Imtiaz
3671
Active
16.06%
20 July 2026
15 April 2025
128 residential units
16,499.61 sq m
15 April 2027
Data source: the Dubai Land Department project register reading of 16.06% dated 20 July 2026, and the RERA Independent Progress Monitoring Report for the same inspection, which records the works on site but prints no percentage. Construction tracking against RERA inspection data runs across the full tohidfetrat.com project portfolio and is reviewed after every published cycle. The image at the top of this page is a developer rendering of the planned building, not a site photograph. Last updated: September 2026.
Want each new reading the day it publishes? Message me on WhatsApp and I will send it to you directly: one message per inspection cycle, nothing else. Message me on WhatsApp
This Inspection Cycle
Cotier House 2 Construction Progress Summary
The 20 July 2026 inspection closes out the ground stage at Cotier House 2: enabling and foundation works are recorded as completed, and the main contract is marked progressing on the superstructure and MEP packages. Measured from the recorded start on 15 April 2025, the 16.06% reading averages about 1.05 points per month over 461 days, simple arithmetic rather than a forecast.
- Enabling works on the marina plot
- Foundation works for the residential building
- Structure of the G+2P+10+R residential building
- MEP works: mechanical, electrical, and plumbing
- Main contract works, RERA status Progressing
- Remaining RERA inspection cycles toward 100%
- Envelope, finishes, and building completion procedures
- Handover of the 128 residences, expected Q2 2027
Payment Linked Progress
What 16.06% Progress Means for Cotier House 2 Buyers
Cotier House 2 was launched on a date-based plan, so its instalments follow the calendar rather than the build: by the 20 July 2026 reading, 50% of the price had fallen due on the launch schedule while the register showed 16.06%. That is a comparison, not a verdict, and at this early stage four actions matter most.
Verify the escrow account
Every instalment should go only to the DLD regulated escrow account registered for project 3671 at First Abu Dhabi Bank (FAB). Cotier House 2 escrow account verification is the step before any transfer; the lookup itself takes about two minutes against the official DLD project record.
Map the dated instalments
Check how your sale and purchase agreement lists the instalments already due at signing, the 15 September 2026 payment, and the 40% completion balance, then read them against the 16.06% register figure. Not sure how your installments map to this reading? Send me your SPA schedule and I will map it against the recorded milestones.
Confirm your Oqood registration
Oqood is the Dubai Land Department's interim register for off plan units. Once your booking is processed, confirm that your Cotier House 2 unit appears under project 3671 in your name, because that DLD registration is what ties your payments to the escrow-protected project.
Follow the structure stage
With foundations recorded complete, the next readings will show how quickly the superstructure moves. The Cotier House 2 construction updates hub keeps each dated reading in one place.
General framework, not legal advice: milestone definitions, notice periods, and fee obligations are set by your individual SPA and the DLD record, and both should be read directly.
Buying at 16.06%?
Entering Cotier House 2 during the structure stage trades a longer wait for an earlier position: the ground works are recorded as done, the building above them is still rising, and the purchase is made at today's official prices. Every payment goes to the DLD-registered escrow account for project 3671, released against inspected construction progress.
- Enabling and foundation works recorded complete on 20 July 2026
- Handover expected Q2 2027; registered completion 15 April 2027
- Instalments already due settled at signing, 40% on completion
- Construction risk carried from bare ground onward
- The longest wait between booking and handover
- Instalments spread across the full construction period
Limited Units Available on the project page as of this update; availability shifts between cycles, and buyers entering after launch settle the instalments already due at signing, so confirm the current schedule with the developer.
About the Development
Cotier House 2 Project Details

With its foundations recorded complete in July 2026, Cotier House 2 is now a structure stage build: one G+2P+10+R building of 128 residences on the Dubai Islands Marina, from 1 bedroom apartments to townhouses and duplexes. Starting prices: AED 2.10M ≈ USD 572K.
Buying at this point means the longest remaining wait to the Q2 2027 handover, in exchange for choosing from the full layout range before the building is closed in.
Cotier House 2 by Imtiaz Project GuideSite Context This Cycle
Explore Cotier House 2 Location on Dubai Map
Cotier House 2 occupies a quayside plot on the east side of the Dubai Islands Marina on Island A, directly beside its sibling Cotier House, with marina berths in front of it. Building at the water's edge makes the ground stage the most demanding part of the programme, which is why the July 2026 record of enabling and foundation works completed marks the point where site activity turns to the structure rising above the quay.
Dubai Islands is still an emerging district: the developer brochure cites 86 resorts and hotels across Islands A, B, C and D and lists six marinas and a mall on Island A, so Cotier House 2 is being built alongside its neighbourhood rather than into a finished one. For buyers at 16.06%, that means judging the Q2 2027 handover together with how far the island around it has come. See the project’s position on the interactive Dubai real estate map.

Buyer Resources for This Project
Investing in Cotier House 2 During Early Construction Progress
At the start of the structure stage, residency planning and payment protection come before any thought of handover. Each resource below is matched to where Cotier House 2 stands at 16.06%.

Cotier House 2 Construction Updates
This page: the 20 July 2026 register reading for Cotier House 2, foundations recorded complete.

Cotier House 2 Golden Visa: Every Marina Layout Clears Alone
All five layouts at Cotier House 2, Imtiaz's 128-residence building on Island A of Dubai Islands, clear the threshold individually.
Read Cotier House 2 Golden Visa Guide
Cotier House 2: The Second Cotier Escrow at First Abu Dhabi Bank
Imtiaz's Cotier House 2 is DLD project 3671: 128 units, First Abu Dhabi Bank escrow, 16.06% certified in July 2026.
Verify Cotier House 2 Escrow AccountUpdate Timeline
Other Cotier House 2 Construction Updates
July 2026 opens the monthly record for Cotier House 2; each later reading will be added to the hub as the building moves from structure toward handover.
Where This Update Fits
Explore Cotier House 2 Structure
This July 2026 reading is one part of a wider picture: the island taking shape around the marina plot, the developer building it, and the homes competing with it for the same buyers.

Island A: Four Imtiaz Projects, From Furnished Apartments to Marina-Front Penthouses
Island A is the urban waterfront core of Dubai Islands, with furnished apartments, duplexes and penthouses across four Imtiaz projects.
See Island A Properties for Sale
Island A Community Overview
Read the full Island A guide: the island's role in the Dubai Islands masterplan, property types, connectivity and pricing.
Explore the Island A Community
Imtiaz Developments: Fully Furnished Residences in Dubai Islands, JVC and Meydan
Imtiaz Developments, founded in 2011, has completed and under-construction design led residential projects in Meydan, JVC and Dubai Islands.
View the Imtiaz Developments Developer ProfileFAQs
Cotier House 2 Construction Progress in July 2026: Frequently Asked Questions
Cotier House 2 stands at 16.06% construction progress on the Dubai Land Department project register, in the reading dated 20 July 2026 for project 3671. The RERA inspection report for the same date describes the works but prints no percentage, so the 16.06% figure is the register reading. That reading was 71 days old when this page was built on 29 September 2026.
No. As of the 20 July 2026 reading, the DLD register still shows a registered completion date of 15 April 2027 for Cotier House 2, and handover is expected in Q2 2027. Registered dates can be revised between inspection cycles, so the date should be read again on the register before any payment that depends on it.
The DLD app lists 8.86% as the Cotier House 2 previous inspection reading but shows no date for it. Against the 16.06% dated 20 July 2026 that is a difference of 7.20 percentage points, and because the earlier reading is undated, no monthly pace can be measured from the pair.
The RERA Independent Progress Monitoring Report dated 20 July 2026 records that enabling and foundation works at Cotier House 2 were completed and that structure and MEP works were progressing at the site. It describes the building as a G+2P+10+R residential building and gives the RERA progress status as Main Contract, Progressing.
As of the 20 July 2026 reading, the register records a construction start of 15 April 2025, a registration date of 24 April 2025, and a registered completion date of 15 April 2027. The recorded start precedes the registration date by nine days; both dates are shown here exactly as the register prints them.
Cotier House 2 was launched on a date-based plan, so by 20 July 2026 the booking payment and the four instalments dated June 2025 to May 2026 had fallen due, 50% of the price in total, while the register read 16.06%. That comparison is arithmetic only: the next dated instalment was 10% on 15 September 2026, and the final 40% is due on completion in April 2027.
A Question the FAQ Can Not Answer?

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is helping you read the July 2026 inspection record for Cotier House 2 correctly before your next payment decision. Client identities and transactions are never published or referenced. Message me directly: you will always reach me personally, never a call center or sales team.
Ask your question, get your answer. No obligation and no follow-up unless you ask for it.