
Emaar · Dubai Creek Harbour
Creek Gate at Dubai Creek Harbour Construction Updates
The Closed Build Record of Two Towers Beside Creek Island's Central Park
Creek Gate was recorded at 100% on 18 November 2021, its registered completion date, closing a four-year build of two Creek Island towers now listed Finished.
Construction tracking against RERA inspection data, updated after every recorded inspection.
Direct advisor access. Every message answered personally, never by a call center.
Construction Snapshot
Creek Gate at Dubai Creek Harbour at a Glance
Creek Gate is Emaar's two-tower building of 498 residences on Creek Island, set at the north edge of Dubai Creek Harbour Central Park. Its DLD file opens with registration on 29 September 2016 and a construction start on 06 March 2017, and ends with a 100% reading on 18 November 2021, the very date the register had set for completion. Unlike a record still in motion, this one is closed: the register now lists project 1813 as Finished, no reading has been added since, and at 1,770 days, roughly four years and ten months, that final entry is old enough that project 1813 should be looked up again on Dubai REST before any decision rests on it.
1813
Finished
06 March 2017
498 residential units
55,836.00 sq m
18 November 2021, met on the day
Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.
Inspection Record
Creek Gate at Dubai Creek Harbour Construction Update Timeline
One dated reading makes up the Creek Gate record: 100% on 18 November 2021, logged on the registered completion date itself. The same register entry lists a previous reading of 97.49% but gives it no date, so the track below carries a single dot and the table a single row rather than an invented earlier point. The card and the table row below both open the November 2021 update; the picture on the card is a project rendering, not a site photograph, and the monitor's own photographs from that visit stay in the official report.
| Inspection Month | Construction Progress | Inspection Date | Full Update |
|---|---|---|---|
| November 2021 | 100% | 18 November 2021 | View the November 2021 update |
Reading the dates: Creek Gate's register set 18 November 2021 as its completion date, and the closing 100% entry is stamped with exactly that day, so the date passed as a deadline kept, not one overrun. The register has since moved Creek Gate to Finished and the handover status is Ready; what it does not show is the transfer position of any single apartment.
Pace Analysis
How Fast Creek Gate at Dubai Creek Harbour Has Been Built
A points-per-month figure needs two dated readings, and Creek Gate's register holds only one, so this record is read through its dated anchors instead:
- 29 Sep 2016 to 06 Mar 2017: registration to construction start158 days
- 06 Mar 2017 to 18 Nov 2021: construction start to the 100% reading1,718 days, about 4 years 8 months
- Undated previous reading to 18 Nov 2021: closing movement, 97.49% to 100%+2.51 points, interval not on record
- 18 Nov 2021 reading against the 18 Nov 2021 registered completion dateMet on the registered date
What the anchors show is a build that finished where its registration said it would. Start to 100% took 1,718 days, and the approvals that close out a tower arrived inside the final nine weeks of that span: the monitoring report dated 18 November 2021 records DCD received on 14 September 2021 and the BCC from DDA on 30 September 2021, 65 and 49 days before the closing reading. The last 2.51 points, from 97.49%, therefore sat in close-out territory, with DEWA meters connected and snagging and deep cleaning still going on when the monitor visited. Because the 97.49% entry carries no date, there is no honest way to say how quickly those points came, and this page does not estimate it. For an end user the useful fact is the date match; for an investor, it is one delivered Dubai Creek Harbour data point where the registered completion and the recorded 100% coincide.
Get the Next Inspection Figure First
Tell me you are tracking Creek Gate at Dubai Creek Harbour and I will send you the next recorded figure and site photos directly, ahead of the page update.
Get the Next Update on WhatsAppProject Profile
About Creek Gate at Dubai Creek Harbour
A closed construction record only matters next to what was delivered. The full project guide covers the finished apartments this page tracked to 100%:

Creek Gate at Dubai Creek Harbour: Twin Towers on Creek Island
Creek Gate at Dubai Creek Harbour pairs two Emaar towers of 498 apartments and penthouses on Creek Island, beside Central Park.
View the Creek Gate at Dubai Creek Harbour Project GuideConsidering a Completed Creek Gate Apartment?
With both towers finished since 2021, what is on the market at Creek Gate changes unit by unit rather than by construction phase. If this record is what brought you here, ask me what is available now before you compare it with other ready options.
Ask About Remaining Availability on WhatsAppStage Record
Creek Gate at Dubai Creek Harbour Build Stages, Mapped to the Inspections
Only the first and last of these stages carry register dates for Creek Gate; the middle three are placed by the tower configuration and approvals named in the 18 November 2021 monitoring report, and no reading is invented for them.
Registration and Site Activation
Project 1813 was registered with DLD on 29 September 2016, and construction started 158 days later on 06 March 2017.
Shared Basement and Groundworks
Both towers stand over one shared basement, listed in the monitoring report as 2B+G, the first structure poured on plot 129.
Two Tower Structures
The report gives Tower 1 as G+1M+35F and Tower 2 as G+1M+28F, each topped by two mechanical levels, a roof and an upper roof.
Enclosure, Fit-Out and Completion Approvals
The monitoring report dates the two completion approvals to September 2021: DCD on the 14th, then the BCC from DDA on the 30th.
Completion, Close-Out and Ready Handover
Recorded at 100% on 18 November 2021 with DEWA meters connected and snagging and deep cleaning then under way; the register now reads Finished and the status Ready.
What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Creek Gate at Dubai Creek Harbour's own record.
Buyer Position
Tracking Your Position at Creek Gate at Dubai Creek Harbour
This page is one of four project resources that together cover a Creek Gate at Dubai Creek Harbour purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Creek Gate at Dubai Creek Harbour Construction Updates
This page: the DLD build record for both Creek Gate towers, 2017 start to 100 percent.

Creek Gate at Dubai Creek Harbour Golden Visa on Finished Creek Island
Creek Gate at Dubai Creek Harbour, 498 Emaar residences on Creek Island, qualifies at its 2, 3 and 4 bedroom tiers.
Read the Creek Gate at Dubai Creek Harbour Golden Visa Guide
Creek Gate at Dubai Creek Harbour Escrow: A Finished Creek Account
Creek Gate at Dubai Creek Harbour read 100% certified November 2021; DLD project 1813 escrowed 498 units at Dubai Islamic Bank.
Verify the Creek Gate at Dubai Creek Harbour Escrow Account
Creek Gate at Dubai Creek Harbour Snagging on Creek Island
Creek Gate at Dubai Creek Harbour pairs two Emaar towers along Central Park, 498 freehold residences of 1 to 4 bedrooms.
Book Creek Gate at Dubai Creek Harbour SnaggingApproaching Handover
Between 100% and Handover: What Creek Gate at Dubai Creek Harbour Buyers Should Do Now
With the towers recorded at 100% since 18 November 2021 and the handover status Ready, nothing on the construction side is left to wait for; what remains sits between you, the seller and the DLD transfer. The transfer date in a ready purchase is set by the sale agreement rather than by a site milestone, so the three checks below belong before that appointment is fixed, not after it.
First, have the specific apartment inspected, since the 2021 close-out work covered the building rather than your unit; the Creek Gate snagging page explains what a ready or resale unit check covers and when to schedule it.
Second, confirm how your own payment is routed under your contract; the Creek Gate escrow account page sets out the DLD-registered account that held buyer payments while project 1813 was under construction.
Third, if residency matters, match your apartment to the threshold before you commit: the 1 bedroom at AED 1.56M ≈ USD 425K sits below the AED 2M ≈ USD 545K line, and the Creek Gate Golden Visa guide covers the larger tiers and the title deed step.
Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.
The Wider Picture
Explore Dubai Creek Harbour Structure
A closed build record reads differently once you see what has risen around it. These three pages put Creek Gate's completion in its market, community and developer context:

Dubai Creek Harbour Properties for Sale
Browse waterfront apartments, branded residences and penthouses for sale in Dubai Creek Harbour.
See Dubai Creek Harbour Properties for Sale
Dubai Creek Harbour: Emaar's Waterfront City With a Marina and Urban Beach
Dubai Creek Harbour is Emaar's waterfront city between Downtown Dubai and the Creek, planned for 48,500 homes with skyline views.
Explore the Dubai Creek Harbour Community
Emaar Properties: Burj Khalifa, Downtown Dubai and Twenty Master Communities
Emaar, founded in 1997, built Burj Khalifa and Downtown Dubai and has delivered over 85,000 homes across twenty master communities.
View the Emaar Properties Developer ProfileConstruction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.
FAQs
Creek Gate at Dubai Creek Harbour Construction Updates Frequently Asked Questions
Creek Gate, DLD project 1813, is complete: the register lists it as Finished, its last reading was 100% on 18 November 2021, and its handover status is Ready. That reading was 1,770 days old in September 2026, so the live record on Dubai REST is the check to run before relying on it; the full record is in the inspection timeline above.
The Creek Gate record holds one dated reading: 100% on 18 November 2021. The same register entry shows a previous reading of 97.49%, a gap of 2.51 points, but gives that earlier figure no date, so it is stated here without being plotted as a separate inspection. The dated inspection is covered in the Creek Gate November 2021 construction update.
They fall on the same day. Creek Gate's registration fixed completion for 18 November 2021, and the register logged 100% on 18 November 2021, so the planned and the recorded finish of project 1813 are one date. With that date now almost five years in the past and the register reading Finished, no revised or extended completion date is on file.
Creek Gate took 1,718 days from its 06 March 2017 construction start to the 100% reading of 18 November 2021, about four years and eight months. Counting from DLD registration on 29 September 2016, the project ran 1,876 days, with 158 of those falling between registration and the start of works.
According to the Independent Progress Monitoring Report dated 18 November 2021, Creek Gate received DCD on 14 September 2021 and the BCC from DDA on 30 September 2021. Both approvals were therefore in place 65 and 49 days before the 100% reading, which is why the report's remaining site work was limited to close-out items.
The monitoring report dated 18 November 2021 lists Tower 1 as G+1M+35F+2MECH+R+1UR and Tower 2 as G+1M+28F+2MECH+R+1UR, both over a shared 2B+G basement. Together the two towers hold 498 residential units, the figure on the DLD register for project 1813.

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is keeping the Creek Gate at Dubai Creek Harbour construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.
Ask your question, get your answer. No obligation and no follow-up unless you ask for it.