DAMAC Properties · DAMAC Hills
DAMAC District Construction Updates
Tracking Three Towers From Enabling Works to the 2029 Handover Window
DAMAC District recorded 0.12% construction progress at its 04 March 2026 RERA inspection, the first dated reading on a build that runs toward 2029.
Construction tracking against RERA inspection data, updated after every recorded inspection.
Direct advisor access. Every message answered personally, never by a call center.
Construction Snapshot
DAMAC District at a Glance
Project 4064 entered the Dubai Land Department register on 03 September 2025 and carried no construction start until 14 February 2026, which is why the first dated inspection eighteen days later reads 0.12%. The anchors below are the registered values behind that reading. What sets this record apart from most early-stage builds is its setting: the three towers will rise inside a DAMAC Hills that was finished and occupied years ago, so the four-year wait attaches to the buildings alone, never to the schools, retail, and golf frontage already trading around the plot.
4064
Active
14 February 2026
1,090 residential units
30 March 2029 (DLD)
Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.
Inspection Record
DAMAC District Construction Update Timeline
One dated inspection sits on this record so far: 0.12% on 04 March 2026, taken while enabling works were still progressing across the Al Hebiah Third plot. The register also holds an earlier zero value with no inspection date attached to it, so that figure is acknowledged here but never plotted or tabled, and March 2026 stands as the baseline every future delta is measured from. Each new reading joins the track and the table below as it is recorded.
| Inspection Month | Construction Progress | Inspection Date | Full Update |
|---|---|---|---|
| March 2026 | 0.12% | 04 March 2026 | View the March 2026 update |
Pace Analysis
How Fast DAMAC District Has Been Built
Velocity between inspections needs two dated readings, and project 4064 has one. What the record does support is the distance still to cover and the rates the registered dates imply:
- 14 Feb 2026 start to the 04 Mar 2026 inspection: enabling works, 0.12% recordedDerived: about 0.2 points per month
- 04 Mar 2026 to the 30 Mar 2029 registered completion date: 99.88 points outstandingSchedule-implied: about 2.7 points per month
- 04 Mar 2026 to the close of the Q3 2029 handover window DAMAC statesSchedule-implied: about 2.3 points per month
All three figures are arithmetic from dates rather than observed pace, and the first is derived from one reading instead of measured between two. Read that way, the useful signal is the spread between the two anchors: the register puts completion at the end of the first quarter of 2029, while the window quoted at launch runs from July to September, three to six months later. That gap is slack the schedule already carries before anything on site slips. Nor should the 0.12% be mistaken for slow work. Clearing, levelling, and contractor mobilization move almost nothing in the certified quantities that drive the percentage, so the first genuine test of pace arrives with piling and foundations, when three separate tower footprints start converting into measurable structure. For a buyer on a long installment schedule, the reading to watch is not this one but the first cycle that posts a whole point.
Get the Next Inspection Figure First
Tell me you are tracking DAMAC District and I will send you the next recorded figure and site photos directly, ahead of the page update.
Get the Next Update on WhatsAppProject Profile
About DAMAC District at DAMAC Hills
A percentage carries no weight without the scheme behind it. The project guide covers what these three towers are being built into:

DAMAC District: Homes and Offices Linked to DAMAC Mall
DAMAC District places two residential towers and an office building on one plot in DAMAC Hills, with direct DAMAC Mall access.
View the DAMAC District Project GuideConsidering an Entry at the Enabling Stage?
Inventory and release terms at DAMAC District shift as the record advances, and the earliest cycles are the ones that price the longest wait. If the inspection record is what brought you to project 4064, get the live unit list before the next cycle moves the picture.
Ask About Remaining Availability on WhatsAppStage Record
DAMAC District Build Stages, Mapped to the Inspections
Only the first two stages below carry recorded dates so far; the rest are the sequence project 4064 has to move through before the 30 March 2029 registered date, and each will gain its window here as inspections attach to it.
Registration and Pre-Construction
Project 4064 was registered on 03 September 2025 with a trust account at Mashreq Bank PSC, five months before the construction start date of 14 February 2026 was recorded.
Enabling Works on the Al Hebiah Third Plot
The 04 March 2026 inspection found enabling works progressing: ground clearance and levelling across the plot, ahead of excavation for three separate tower footprints.
Excavation, Piling, and Foundations
The first movement of substance on this record: substructure for Towers A, B, and C, and the point where the percentage starts posting whole points rather than fractions.
Concrete Structure Across Three Towers
Frames to G+2P+26+R and G+2P+29+R on the residential towers and G+2P+10+R on the commercial building, the phase that will carry most of the 99.88 points outstanding.
Finishes, Commissioning, and Delivery
Blockwork and interior finishing follow the frames on all three buildings, then systems commissioning and closing approvals ahead of the 30 March 2029 registered date.
What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on DAMAC District's own record.
Buyer Position
Tracking Your Position at DAMAC District
This page is one of four project resources that together cover a DAMAC District purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

DAMAC District Construction Updates
This page: the dated inspection record for DAMAC District, from the 0.12% enabling reading onward.

DAMAC District Golden Visa: A Freehold Three Tower DAMAC Hills Development
DAMAC District is DAMAC's freehold three tower development in DAMAC Hills, open to all nationalities, with Oqood registration now.
Read the DAMAC District Golden Visa Guide
DAMAC District Escrow Account: The Mall-Linked Homes at Mashreq
DAMAC District enters the DLD register as project 4064 with 1090 units, Mashreq holding escrow, certified 0.12% in March 2026.
Verify the DAMAC District Escrow AccountApproaching Handover
Between 0.12% and Handover: What DAMAC District Buyers Should Do Now
The distance from this reading to a building you can stand in front of is measured in years, while the booking deposit and the early installments fall due within months. Money first, structure later is the order every enabling-stage purchase runs on, and it is why the three checks below belong to the weeks after booking rather than to some later cycle.
First, confirm that every transfer is landing in the regulated trust account rather than a developer operating account; the DAMAC District escrow account page carries the project 4064 lookup and the bank it is held with.
Second, put your own installment dates beside the registered completion date of 30 March 2029 and the Q3 2029 window quoted at launch, so you know which of the two your schedule was actually written against and when the completion balance falls due.
Third, follow the record from the baseline rather than picking it up halfway: the March 2026 baseline reading for DAMAC District is the first dated cycle, and every later reading is added to the timeline on this page as it is recorded.
Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.
The Wider Picture
Explore DAMAC Hills Structure
This page covers one plot; what already stands around it carries just as much of the decision at 0.12%. Three pages hold that context:

DAMAC Hills Properties for Sale
Browse villas and townhouses for sale across DAMAC Hills, including golf-course residences and branded collections.
See DAMAC Hills Properties for Sale
DAMAC Hills: Villas, Townhouses and Apartments Around Trump International Golf Club
DAMAC Hills is a Dubailand community wrapping villas, townhouses and apartments around a championship golf course, with an active resale market.
Explore the DAMAC Hills Community
DAMAC Properties: Lagoon Communities, Golf Villas and Branded Collaborations
Founded in 2002, DAMAC has delivered 48,000 homes and is known for large-scale master communities, luxury residential projects and branded collaborations.
View the DAMAC Developer ProfileConstruction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.
FAQs
DAMAC District Construction Updates Frequently Asked Questions
Project 4064 is registered as active with the Dubai Land Department and stands at the enabling works stage, recorded at 0.12% construction progress on 04 March 2026. The full dated sequence sits in the inspection timeline above.
The inspection of 04 March 2026 recorded 0.12% and noted enabling works progressing on the plot. No point delta can be stated against a prior cycle, because the earlier zero value on the register carries no inspection date, so March 2026 is treated as the baseline. The site report for that cycle is in the March 2026 construction update.
The Dubai Land Department register carries a completion date of 30 March 2029 for project 4064, while the handover window stated at launch is Q3 2029. Neither date has lapsed, both are anchors rather than guarantees, and this page records which one the inspection record tracks toward as cycles accumulate.
Project materials count 1,090 residences split between the two residential buildings, which rise to G+2P+26+R and G+2P+29+R, while the third structure on the plot carries commercial floors to G+2P+10+R. The DLD register records 1,139 units in total for project 4064, a count spanning the full three-tower scheme rather than the residences alone.
The registered construction start date is 14 February 2026, five months after the project entered the DLD register on 03 September 2025. The first dated inspection followed eighteen days later, on 04 March 2026, at 0.12%.
At the 04 March 2026 inspection the plot was being cleared and levelled, with contractor mobilization underway and no structure above ground. What the register describes ahead of that reading is a concrete-framed scheme finished inside and out, repeated across three separate buildings.
Inspection cycles begin once a project has a recorded construction start, which for project 4064 was 14 February 2026. The register also holds a zero value with no date attached to it, and undated readings are not plotted or tabled on this page, so the 04 March 2026 cycle stands alone as the first dated entry.
The plot sits in Al Hebiah Third, at the western boundary of the DAMAC Hills masterplan, with golf frontage along one flank and undeveloped ground on the DAMAC Lagoons approach along the other. The wider community context is in the DAMAC Hills community guide.

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is keeping the DAMAC District construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.
Ask your question, get your answer. No obligation and no follow-up unless you ask for it.