Elea at The Valley by Emaar in The Valley construction updates cover image featuring a project rendering of a contemporary two-storey villa with landscaped street frontage in Dubai - Presented by Tohid Fetrat

Emaar · The Valley

Elea at The Valley Construction Updates

The Verified Build Record for 128 Townhouses on The Valley's Eastern Edge

Elea at The Valley recorded 22.02% construction progress at its 15 July 2026 RERA inspection, the first dated reading in a townhouse cluster tracked toward 2028 handover.

Construction tracking against RERA inspection data, updated after every recorded inspection.

Direct advisor access. Every message answered personally, never by a call center.

22.02%Construction Progress
15 July 2026Latest RERA Inspection
128 townhousesTotal Units
Project 3406DLD Registration

Construction Snapshot

Elea at The Valley at a Glance

Elea is Emaar's 128-home townhouse cluster on plot 5031 in Al Yufrah 1, at the eastern edge of The Valley masterplan. Sixteen and a half months separate the 28 February 2025 construction start from the 22.02% recorded on 15 July 2026, and the cards below are the DLD-registered anchors behind that reading. Because the homes are grouped into four-plex blocks strung along one curving spine rather than stacked into a single building, the percentage in the register is an average across plots that are visibly at different stages on the same day.

DLD Project Number

3406

Project Status

Active

Construction Start

28 February 2025

Total Units

128 townhouses

Total Built-Up Area

32,378.05 sq m

Registered Completion Date

30 June 2028 (DLD)

Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.

Inspection Record

Elea at The Valley Construction Update Timeline

One dated inspection stands in this record so far: 22.02% on 15 July 2026. The reading it replaced, 15.83%, is carried in the register without a published inspection date, so it belongs in the narrative but not on the track or in the table, where every figure appears with the day it was taken. Each future cycle adds a row here, and every row links the full monthly update behind it.

Inspection MonthConstruction ProgressInspection DateFull Update
July 202622.02%15 July 2026View the July 2026 update

Pace Analysis

How Fast Elea at The Valley Has Been Built

With a single dated inspection in the register, Elea has no measured velocity between readings yet. What can be computed honestly is the ground covered since the recorded start, and the rate the remaining record has to hold to reach the registered completion date:

  • 28 Feb 2025 start to 15 Jul 2026: 0% to 22.02% across 16.5 monthsAbout 1.3 points per month, derived
  • 15 Jul 2026 to the 30 Jun 2028 registered completion: 22.02% to 100% across 23.5 monthsAbout 3.3 points per month, schedule-implied

The two figures are different in kind, which is exactly why both belong here. The first is an average dragged down by the enabling and foundation months, where a townhouse cluster consumes a great deal of site activity and records very few certified points. The second is what 30 June 2028 demands from here, and it runs at roughly two and a half times the average behind it. At 22.02% that gap reads as normal rather than alarming: structure, envelope, and finishes on 32 four-plex blocks convert into percentage far faster than groundworks ever do, and the July file already found those packages live on the leading plots. The honest caveat is that the 6.19 point rise from the previous register reading of 15.83% cannot be converted into a monthly rate, because that earlier figure is published without a date. For a buyer, the practical reading is that the next few cycles should record faster than the average so far; for an investor judging the schedule, the implied rate is achievable on an Emaar townhouse programme but leaves little slack if the leading blocks set the tempo for the rest.

Get the Next Inspection Figure First

Tell me you are tracking Elea at The Valley and I will send you the next recorded figure and site photos directly, ahead of the page update.

Get the Next Update on WhatsApp

Project Profile

About Elea at The Valley at The Valley by Emaar

A percentage is only meaningful against what it is building toward. The project guide sets out the homes behind the 22.02% figure carried on this page:

Elea at The Valley by Emaar in The Valley contemporary two-storey villa with landscaped street frontage pedestrians and parked cars in Dubai - Presented by Tohid Fetrat

Elea at The Valley: Emaar Townhouses in Four-Plex Blocks

Elea at The Valley is a 128-home townhouse cluster on the eastern edge, built as four-plex blocks in two facade styles.

View the Elea at The Valley Project Guide

Considering an Early-Construction Entry?

Availability at Elea moves between inspection cycles as Emaar sells through both layouts and both facade treatments. If the register is what led you to the project, I can confirm what remains before the 30% threshold certifies.

Ask About Remaining Availability on WhatsApp

Stage Record

Elea at The Valley Build Stages, Mapped to the Inspections

Each stage below carries the window it actually occupied in Elea's own register, from DLD registration through to the work packages the July 2026 inspection found running, so the sequence reads as this project's history rather than as a generic build cycle.

Nov 2024 to Feb 2025

Registration and Site Mobilisation

Project 3406 was registered with the DLD on 19 November 2024, and the register records construction starting on plot 5031 on 28 February 2025.

Feb 2025 into 2026

Enabling Works and Foundations

The months that produce the least percentage for the most effort: enabling works and foundations to the first four-plex blocks across the 32,378.05 sq m built-up programme.

Current PhaseTo 15 Jul 2026, 22.02% recorded

Structure Across the Four-Plex Blocks

By 15 July 2026 the leading blocks had risen through both storeys while later plots were still at foundation level, with envelope and services work trailing one step behind the structure front.

Toward the 50% and 70% certified milestones

Envelope, MEP, and Internal Finishes

The band where percentage moves quickest: facades, joinery, and finishes rolling through all 128 townhouses behind the structure front, block by block.

Toward 100% and Q2 2028

Community Facilities, Infrastructure, and Handover

Sport court, kids play area, flexible lawn, mosque, guardhouse, and community centre remain programme items ahead of the 128 homes, alongside spine road infrastructure and the closing inspections.

What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Elea at The Valley's own record.

Buyer Position

Tracking Your Position at Elea at The Valley

This page is one of four project resources that together cover a Elea at The Valley purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Elea at The Valley by Emaar in The Valley construction updates cover image featuring a project rendering of a contemporary two-storey villa with landscaped street frontage in Dubai - Presented by Tohid Fetrat
You Are Here

Elea at The Valley Construction Updates

This page: the verified inspection record for Elea at The Valley, from the 2025 groundbreaking onward.

Elea at The Valley by Emaar in The Valley Golden Visa card graphic above contemporary villas and landscaped residential surroundings in Dubai - Presented by Tohid Fetrat

Elea at The Valley Golden Visa, Comfortably Above the Threshold

Emaar's 128-townhouse Elea at The Valley has no tier below the threshold; each 3 or 4 bedroom townhouse qualifies alone.

Read the Elea at The Valley Golden Visa Guide
Elea at The Valley by Emaar in The Valley escrow account protection concept with shield and padlock icons above a contemporary villa exterior at dusk in Dubai - Presented by Tohid Fetrat

Elea at The Valley Townhouse Escrow with Emirates NBD

Elea at The Valley, DLD project 3406, puts 128 townhouses' instalments into Emirates NBD escrow, 22.02% certified in July 2026.

Verify the Elea at The Valley Escrow Account

Approaching Handover

Between 22.02% and Handover: What Elea at The Valley Buyers Should Do Now

Money moves at Elea against certified construction completion at 30%, 50%, 70%, 90%, and 100%, so the register rather than the calendar decides what falls due. The 22.02% recorded on 15 July 2026 sits below the first of those thresholds, and a threshold can certify between cycles without advance warning, which is why the three steps below belong in this window rather than closer to handover.

First, check that every transfer lands in the DLD-regulated escrow account held for project 3406, with Emirates NBD named as trust account bank on the inspection record; the Elea at The Valley escrow account page covers how a certified milestone releases funds and what to verify beforehand.

Second, if a three or four bedroom purchase here may support residency, settle eligibility early through the Elea at The Valley residency eligibility guide, since the application path differs before and after a title deed exists.

Third, follow each cycle as it publishes rather than reconstructing the history later; the July 2026 inspection report for Elea at The Valley is the first dated entry, and every reading after it lands on this page.

Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.

The Wider Picture

Explore The Valley by Emaar Structure

An inspection record answers how fast, not what surrounds the plot. These three pages set Elea's 22.02% against the live inventory, the masterplan around it, and the developer delivering it:

Modern townhouses and villas with contemporary architecture landscaped surroundings and private parking along a residential street at The Valley Dubai Presented by Tohid Fetrat

The Valley by Emaar Properties for Sale

Browse townhouses and villas for sale in The Valley, comparing phases, prices and payment plans.

See The Valley by Emaar Properties for Sale
Evening view of The Valley by Emaar community clubhouse with swimming pool palm trees sun loungers and modern leisure facilities in Dubai Presented by Tohid Fetrat

The Valley by Emaar: Nature-Inspired Villas and Townhouses on Dubai-Al Ain Road

Launched in 2019, The Valley has villa and townhouse clusters with a central Town Centre, Golden Beach and parks.

Explore the The Valley by Emaar Community
Emaar Properties developer showcasing Downtown Dubai skyline with Burj Khalifa and surrounding residential and commercial towers at dusk Presented by Tohid Fetrat

Emaar Properties: Burj Khalifa, Downtown Dubai and Twenty Master Communities

Emaar, founded in 1997, built Burj Khalifa and Downtown Dubai and has delivered over 85,000 homes across twenty master communities.

View the Emaar Properties Developer Profile

Construction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.

FAQs

Elea at The Valley Construction Updates Frequently Asked Questions

Elea at The Valley is an active DLD-registered project (number 3406) in its structural phase, recorded at 22.02% at the RERA inspection of 15 July 2026. The dated record sits in the inspection timeline above.

The 15 July 2026 inspection recorded 22.02%, which is 6.19 points above the previous register reading of 15.83%. That earlier figure carries no published inspection date, so the size of the movement is known but the period it covers is not. The full report is in the July 2026 construction update.

The DLD-registered completion date for project 3406 is 30 June 2028, matching the Q2 2028 handover window Emaar states for the cluster. From the 22.02% recorded on 15 July 2026, 77.98 percentage points remain to be certified, and this page's record is updated as each inspection publishes.

DLD registration records show 128 residential units with a total built-up area of 32,378.05 sq m, arranged as three and four bedroom townhouses in four-plex blocks across two facade treatments.

The project was registered on 19 November 2024 and construction started on 28 February 2025. The first dated reading in the register is the 22.02% recorded on 15 July 2026, roughly 16.5 months later.

At 22.02% on 15 July 2026 the inspection recorded enabling and foundation work, structure on the leading four-plex blocks, external envelope, MEP first fix, internal finishes, and infrastructure all advancing at once across different plots. The stage-by-stage position is in the stage record above.

The cluster is 128 G+1 townhouses laid out as four-plex blocks on plot 5031 in Al Yufrah 1, offered as three and four bedroom homes in the Oakley and Slate facade treatments. Layouts are covered in the Elea at The Valley project guide.

Elea sits on the eastern boundary of the masterplan, on a long angled plot immediately south of the Kaia cluster rather than inside the interior phases. Its sport court, kids play area, flexible lawn, mosque, guardhouse, and community centre all fall inside the gate. The wider masterplan is covered in the The Valley community guide.

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is keeping the Elea at The Valley construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.

Ask your question, get your answer. No obligation and no follow-up unless you ask for it.

WhatsApp +971543443597
Get the Latest Status