Ellington Sands 2 by Ellington in Island A project rendering used for the June 2026 construction update showing the planned low-rise residential buildings, tiered balconies and palm-lined landscaping in Dubai - Presented by Tohid Fetrat

Ellington · Island A, Dubai Islands · Construction Update

Ellington Sands 2 Construction Update - June 2026

June 2026 Inspection Records Ellington Sands 2 at 0.38% on the DLD Register as Enabling Works Progress on Island A

Enabling works were progressing on the Island A beachfront plot when RERA inspected Ellington Sands 2 on 5 June 2026, and the DLD register recorded 0.38 percent.

Direct advisor access. Every message answered personally, never by a call center.

0.38%DLD Register Reading
5 June 2026Inspection Date
Q4 2028Expected Handover
4140DLD Project Number

DLD Register Inspection Data

Ellington Sands 2 Construction Snapshot

A 0.38 point move off an undated 0% previous reading is the first positive figure the Dubai Land Department register shows for Ellington Sands 2, placing the project in the earliest stage band, where site preparation rather than building work defines each reading.

Project Name

Ellington Sands II

Project Number

4140

Project Status

Active

Construction Progress

0.38%

Inspection Date

5 June 2026

Construction Start

10 October 2025

Total Units

460 units

Total Built Area

52,541.01 sq m

Expected Completion

31 December 2028

Data source: Dubai Land Department register reading recorded on 5 June 2026 for project 4140, with the RERA progress report of the same date noting enabling works progressing at the site; the report prints no percentage of its own. This reading was 148 days old when this page was prepared, so re-check project 4140 on the DLD's Dubai REST app for a newer inspection. The image at the top of this page is a June 2026 developer rendering of the planned buildings, not a photograph of site progress. Construction tracking against RERA inspection data runs across the full tohidfetrat.com project portfolio and is reviewed after every published cycle. Last updated: June 2026.

Want each new reading the day it publishes? Message me on WhatsApp and I will send it to you directly: one message per inspection cycle, nothing else. Message me on WhatsApp

This Inspection Cycle

Ellington Sands 2 Construction Progress Summary

The RERA progress report dated 5 June 2026 records a single activity on the Ellington Sands 2 plot: enabling works progressing at the site. Because that report carries no percentage, the 0.38% on this page is the Dubai Land Department project register's figure for the same date, and it reflects groundwork for the project rather than any part of Tower A or Tower B.

Completed
  • Construction start recorded in the DLD register on 10 October 2025
  • Project registration as Ellington Sands II on 31 October 2025
  • Escrow trust account bank on record: Abu Dhabi Commercial Bank
In Progress at 0.38%
  • Enabling works progressing at the site, per the RERA report of 5 June 2026
  • Progress status logged as Enabling Works, Progressing
  • Inspection photographs held on the register record for this date
Ahead of Handover
  • Basement and ground floor with residential, retail and entertainment uses, including a two-floor beach club, as the RERA report describes them
  • Tower A with 9 residential floors and Tower B with 6 residential floors, plus roof, in the report's wording
  • Handover expected in Q4 2028, against a registered completion date of 31 December 2028
Next inspectionAppears in the DLD project register after the next RERA site visit; no date for it has been published, and this page sets none.
Completion targetHandover expected in Q4 2028; the register's registered completion date is 31 December 2028, 940 days after the 5 June 2026 reading.
Remaining distance99.62 percentage points separate the 5 June 2026 reading from 100%.
Pace arithmetic0.38 points over the 238 days since the recorded start averages about 0.05 points per 30-day month; reaching 100% by the registered completion date would take about 3.18 points per 30-day month. Arithmetic, not a forecast.

Payment Linked Progress

What 0.38% Progress Means for Ellington Sands 2 Buyers

The Ellington Sands 2 70/30 plan ties four 5% instalments to construction stages, the first at 20% construction, so a 0.38% reading triggers none of them; the instalments running now are the ones counted from each buyer's own reservation date. At this stage of Ellington Sands 2, four actions matter most.

Before Each Instalment

Verify the escrow account

Every instalment, including those counted from your reservation date, should go only to the DLD regulated escrow account registered for project 4140 with Abu Dhabi Commercial Bank. Ellington Sands 2 escrow account verification is the step before any transfer; the lookup itself takes about two minutes against the official DLD project record.

Before the 20% Construction Trigger

Reread your SPA milestone schedule

Check how your sale and purchase agreement defines the four construction-linked instalments and the 30% due on completion, and map those clauses against the 0.38% reading and the Q4 2028 handover. Not sure how your installments map to this reading? Send me your SPA schedule and I will map it against the recorded milestones.

After Your Reservation

Confirm your Oqood registration

Your purchase should appear against project 4140 in the Dubai Land Department register through Oqood, the off-plan registration that records you as the buyer long before a title deed exists. Ask for the Oqood confirmation once your booking is processed and keep it with your SPA.

Every Cycle

Track the reading toward 20%

The first construction-linked instalment waits for 20% construction, far from the 0.38% recorded on 5 June 2026. Ellington Sands 2 construction updates hub logs each new register reading as it appears.

General framework, not legal advice: milestone definitions, notice periods, and fee obligations are set by your individual SPA and the DLD record, and both should be read directly.

Buying at 0.38%?

Entering a project at the start of its build trades certainty for runway: the plot is in enabling works, handover is expected in Q4 2028, and the full length of the payment plan lies ahead of you. Every payment goes to the DLD-registered escrow account for project 4140, released against construction progress.

Entering Now at 0.38%
  • Register reading of 0.38% with enabling works progressing at the site
  • Handover expected in Q4 2028
  • None of the four construction-linked instalments triggered at this reading
Typical Near-Handover Entry
  • Structure standing on site before you commit
  • Months rather than years left to the handover date
  • Shorter instalment runway, with larger sums due close to completion
AED 2.20M ≈ USD 599KStarting Price
70/30 Plan30% Due on Completion
Q4 2028Expected Handover
Ask What Is Available at Ellington Sands 2

Limited Units Available on the project page as of this update; availability shifts between cycles.

About the Development

Ellington Sands 2 Project Details

Ellington Sands 2 by Ellington in Island A project rendering showing a landscaped courtyard between two residential buildings opening toward the sea in Dubai - Presented by Tohid Fetrat
Island A, Dubai Islands · Ellington

With enabling works progressing on its plot, Ellington Sands 2 is at the first stage of a two-tower beachfront development of 456 residences on Island A, from 1 Bedroom Apartments to a 4 Bedroom Penthouse. Starting prices: AED 2.20M ≈ USD 599K.

For buyers entering at this stage, the trade off is the longest wait in the build against the full length of the 70/30 plan, with handover expected in Q4 2028.

Ellington Sands 2 by Ellington Project Guide

Site Context This Cycle

Explore Ellington Sands 2 Location on Dubai Map

Ellington Sands 2 holds a beachfront plot on Island A that the developer pairs with a private beach, and its renderings set the two buildings around a courtyard opening toward the sea. On a coastal plot like this one, enabling works are the groundwork every later package depends on, and that is the stage the 5 June 2026 RERA report records: enabling works progressing at the site.

Island A is the mixed-use island of Dubai Islands, which the developer describes as home to a mall, hotels and resorts, and a marina, with Dubai Islands Mall about 5 minutes' drive away per its location guide. For a buyer at the 0.38% stage, that island setting matters as much as the build itself, because it shapes how the home will be lived in or let once handover arrives, expected in Q4 2028. See the project's position on the interactive Dubai real estate map. See the project’s position on the interactive Dubai real estate map.

Interactive Dubai real estate map preview
Click to view Ellington Sands 2 by Ellington on Dubai Map

Buyer Resources for This Project

Investing in Ellington Sands 2 at the Start of Construction

While the plot is still in enabling works, residency planning and payment protection are the questions that come first. Each resource below is matched to where Ellington Sands 2 stands right now.

Ellington Sands 2 by Ellington in Island A construction updates cover image featuring a project rendering of residential buildings, palm trees and landscaped entrances in Dubai - Presented by Tohid Fetrat
You Are Here

Ellington Sands 2 Construction Updates

This page: the 5 June 2026 register reading for Ellington Sands 2, with enabling works progressing.

Ellington Sands 2 by Ellington in Island A Golden Visa concept graphic featuring a gold visa card beside a rendered residential building with balconies in Dubai - Presented by Tohid Fetrat

Ellington Sands 2 Golden Visa: All Six Unit Types Qualify

At Ellington Sands 2 by Ellington Properties on Island A, all six apartment and penthouse types meet the Golden Visa threshold.

Read Ellington Sands 2 Golden Visa Guide
Ellington Sands 2 by Ellington in Island A escrow concept graphic with a shield and padlock over a rendered courtyard between residential buildings in Dubai - Presented by Tohid Fetrat

Ellington Sands 2 Escrow Account at ADCB, DLD Project 4140

Ellington Sands 2, DLD project 4140, holds its escrow account at Abu Dhabi Commercial Bank for 456 residences on Island A.

Verify Ellington Sands 2 Escrow Account

Update Timeline

Other Ellington Sands 2 Construction Updates

June 2026 is the first monthly record published for Ellington Sands 2; the hub collects every later register reading for the two towers as it is added.

All Ellington Sands 2 Construction Updates

FAQs

Ellington Sands 2 Construction Progress in June 2026: Frequently Asked Questions

The Dubai Land Department register recorded Ellington Sands 2, registered as Ellington Sands II under project number 4140, at 0.38% on 5 June 2026, the first figure above the 0% shown as its previous inspection. The RERA progress report dated the same day notes that enabling works were progressing at the site and prints no percentage of its own, so 0.38% is the register's reading rather than a figure taken from the report.

Next to the 5 June 2026 reading, the DLD app lists 0% as the Previous Inspection for project 4140 but shows no date for it. Without a date there is no measurable span between the two readings, so this page plots that 0% as an unlabelled point on the progress bar and derives no pace from it. The next dated reading will be the first that can be compared directly with 5 June 2026.

It places Ellington Sands 2 just above zero on the register at the enabling stage, the only activity the 5 June 2026 RERA report describes for the plot. 99.62 percentage points separate the reading from 100%, and nothing in the record ties the 0.38% to any built part of Tower A or Tower B.

The RERA progress report for project 4140 found enabling works progressing at the site and gives the progress status as Enabling Works, Progressing. It describes the planned project as a basement and ground floor with residential, retail and entertainment uses including a two-floor beach club, Tower A with 9 residential floors and Tower B with 6 residential floors, plus roof. The register record also carries inspection photographs for that date, which are not reproduced on this page.

No. Under the developer's 70/30 payment plan, four instalments of 5% each are tied to completion of 20%, 30%, 40% and 50% construction, and the register stood at 0.38% on 5 June 2026, so none had been triggered by that reading. Instalments counted from a buyer's own reservation date follow a separate calendar, and the sale and purchase agreement for each unit is the document that fixes them.

The 0.38% reading was recorded on 5 June 2026 and was 148 days old when this page was prepared on 31 October 2026, so a newer inspection may already exist. Search project 4140, Ellington Sands II, in the Dubai Land Department's Dubai REST app for the latest figure, and see the Ellington Sands 2 construction updates hub for every published reading.

A Question the FAQ Can Not Answer?

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is helping you read the June 2026 inspection record for Ellington Sands 2 correctly before your next payment decision. Client identities and transactions are never published or referenced. Message me directly: you will always reach me personally, never a call center or sales team.

Ask your question, get your answer. No obligation and no follow-up unless you ask for it.

Get Progress Alerts