Ellington Sands 2 by Ellington in Island A construction updates cover image featuring a project rendering of residential buildings, palm trees and landscaped entrances in Dubai - Presented by Tohid Fetrat

Ellington · Island A, Dubai Islands

Ellington Sands 2 Construction Updates

The Register Record for Two Beachfront Towers on Island A, from Enabling Works to Handover

Ellington Sands 2 reached 0.38% on the DLD register on 5 June 2026, its first reading above zero, as enabling works progressed on its Island A plot.

Construction tracking against RERA inspection data, updated after every recorded inspection.

Direct advisor access. Every message answered personally, never by a call center.

0.38%Construction Progress
05 June 2026Latest RERA Inspection
460 residential unitsTotal Units
Project 4140DLD Registration

Construction Snapshot

Ellington Sands 2 at a Glance

Ellington Sands 2 is Ellington's 456-residence beachfront development on Island A, Dubai Islands, entered in the Dubai Land Department register as Ellington Sands II under project 4140. Its record so far holds more dates than readings: a construction start of 10 October 2025, registration on 31 October 2025, and one dated reading, 0.38% on 5 June 2026, taken while enabling works were progressing at the site. With handover expected in Q4 2028, almost all of the build this page will chart for Tower A and Tower B still lies ahead of that first figure.

DLD Project Number

4140

Project Status

Active

Construction Start

10 October 2025

Total Units

460 residential units

Total Built-Up Area

52,541.01 sq m

Registered Completion Date

31 December 2028 (DLD)

Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.

Inspection Record

Ellington Sands 2 Construction Update Timeline

One dated reading anchors this timeline so far: 0.38% on 5 June 2026, the first figure above zero for Ellington Sands 2, set between a recorded construction start of 10 October 2025 and a registered completion date of 31 December 2028. The DLD app lists 0% as the previous inspection but shows no date for it, so that 0% sits on the track as an unlabelled point rather than a table row. The card under the track carries the developer rendering used on the June 2026 page, an illustration of the planned buildings rather than a photograph of the site, and each new dated reading will add a row to the table.

Inspection MonthConstruction ProgressInspection DateFull Update
June 20260.38%05 June 2026View the June 2026 update

Pace Analysis

How Fast Ellington Sands 2 Has Been Built

A measured pace needs two dated readings, and the Ellington Sands 2 register holds one: 0.38% on 5 June 2026, after an undated 0%. What the record does allow is arithmetic, not a forecast:

  • 10 Oct 2025 to 5 Jun 2026: recorded start to the 0.38% reading, 238 daysAbout 0.05 points per 30-day month
  • 5 Jun 2026 to 31 Dec 2028: 0.38% to 100% by the registered completion date, 940 daysAbout 3.18 points per 30-day month to reach 100%

The gap between those two numbers is the defining feature of this record at its opening, and it is not a verdict on timing. The 0.05 averages a 238-day window that the 5 June 2026 RERA report describes only as enabling works on the Island A plot; the 3.18 is simply the 99.62 points still to go spread across the 940 days left to the registered completion date. Neither figure predicts the next reading, and a true pace between inspections becomes possible only when the register shows a second dated figure for project 4140. For an end user planning around the Q4 2028 handover, the record has barely begun; for an investor, nearly the whole build curve, including the 20% mark that triggers the first construction-linked instalment, is still ahead.

Get the Next Inspection Figure First

Tell me you are tracking Ellington Sands 2 and I will send you the next recorded figure and site photos directly, ahead of the page update.

Get the Next Update on WhatsApp

Project Profile

About Ellington Sands 2 at Island A

A 0.38% reading describes a plot in enabling works; the project guide describes what that plot is meant to become, two beachfront buildings on Dubai Islands:

Ellington Sands 2 by Ellington in Island A project rendering showing a landscaped courtyard between two residential buildings opening toward the sea in Dubai - Presented by Tohid Fetrat

Ellington Sands 2: Beachfront Apartments and Penthouse on Dubai Islands

Ellington Sands 2 by Ellington Properties offers 456 beachfront residences across two low-rise towers on Island A, Dubai Islands.

View the Ellington Sands 2 Project Guide

Considering an Early-Stage Entry?

Ellington Sands 2 is listed with Limited Units Available, and the mix shifts from one cycle to the next. If an early-stage entry ahead of the Q4 2028 handover is what brought you to this record, ask me for current availability before choosing a unit.

Ask About Remaining Availability on WhatsApp

Stage Record

Ellington Sands 2 Build Stages, Mapped to the Inspections

Each stage below is tied to what the Ellington Sands 2 record actually shows: two dated register events in October 2025, one reading in June 2026, and the planned towers the 5 June 2026 RERA report describes but no reading has reached yet.

10 Oct to 31 Oct 2025

Construction Start and Registration

The register records construction starting on 10 October 2025 and the project being registered as Ellington Sands II on 31 October 2025, 21 days later.

Current PhaseSince Oct 2025, 0.38% on 5 Jun 2026

Enabling Works on the Island A Plot

The RERA progress report of 5 June 2026 found enabling works progressing at the site, logged as Enabling Works, Progressing, with the register at 0.38%.

Not yet reached on the register

Basement and Ground Floor

The RERA report describes a basement and ground floor carrying residential, retail and entertainment uses, including a two-floor beach club, beneath both towers.

Ahead, first instalment trigger at 20%

Tower A and Tower B Structure

Tower A with 9 residential floors and Tower B with 6, plus roof, in the RERA report's wording; 20% construction triggers the first construction-linked instalment.

Toward Q4 2028

Finishing, Commissioning, and Handover

Handover is expected in Q4 2028; the registered completion date on the DLD record is 31 December 2028, the closing day of that quarter.

What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Ellington Sands 2's own record.

Buyer Position

Tracking Your Position at Ellington Sands 2

This page is one of four project resources that together cover a Ellington Sands 2 purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Ellington Sands 2 by Ellington in Island A construction updates cover image featuring a project rendering of residential buildings, palm trees and landscaped entrances in Dubai - Presented by Tohid Fetrat
You Are Here

Ellington Sands 2 Construction Updates

This page: every dated Ellington Sands 2 register reading, from the 0.38% of June 2026 onward.

Ellington Sands 2 by Ellington in Island A Golden Visa concept graphic featuring a gold visa card beside a rendered residential building with balconies in Dubai - Presented by Tohid Fetrat

Ellington Sands 2 Golden Visa: All Six Unit Types Qualify

At Ellington Sands 2 by Ellington Properties on Island A, all six apartment and penthouse types meet the Golden Visa threshold.

Read the Ellington Sands 2 Golden Visa Guide
Ellington Sands 2 by Ellington in Island A escrow concept graphic with a shield and padlock over a rendered courtyard between residential buildings in Dubai - Presented by Tohid Fetrat

Ellington Sands 2 Escrow Account at ADCB, DLD Project 4140

Ellington Sands 2, DLD project 4140, holds its escrow account at Abu Dhabi Commercial Bank for 456 residences on Island A.

Verify the Ellington Sands 2 Escrow Account

Approaching Handover

Between 0.38% and Handover: What Ellington Sands 2 Buyers Should Do Now

At 0.38% on 5 June 2026, Ellington Sands 2 stood 19.62 points short of the 20% construction mark that triggers the first construction-linked instalment of its 70/30 plan, while the instalments counted from each buyer's reservation date keep their own calendar. Those reservation-date payments do not wait for the register, so the three steps below belong before your next transfer, not after it.

First, check where each payment is going: the Ellington Sands 2 escrow account page names Abu Dhabi Commercial Bank as the trust bank on record for project 4140 and walks through matching it to the DLD register.

Second, if residency is part of your plan, read the Ellington Sands 2 Golden Visa guide early; every unit type starts at AED 2.20M ≈ USD 599K or more, and the guide sets out how an off-plan holding is treated before a title deed exists.

Third, follow the record rather than the calendar: this hub adds each new dated register reading as it appears, and the Ellington Sands 2 June 2026 inspection record holds the full detail behind the 0.38% figure.

Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.

The Wider Picture

Explore Island A Structure

A build record at 0.38% says little on its own; what gives it weight is the island and the developer around it. These three pages put the Ellington Sands 2 record in its market, community, and developer context:

Aerial masterplan view of Island A properties for sale with waterfront residences, marinas, green spaces, and connected roadways in Dubai. Presented by Tohid Fetrat

Island A: Four Imtiaz Projects, From Furnished Apartments to Marina-Front Penthouses

Island A is the urban waterfront core of Dubai Islands, with furnished apartments, duplexes and penthouses across four Imtiaz projects.

See Island A Properties for Sale
Aerial masterplan view highlighting Island A at Dubai Islands in Dubai, Presented by Tohid Fetrat

Island A Community Overview

Read the full Island A guide: the island's role in the Dubai Islands masterplan, property types, connectivity and pricing.

Explore the Island A Community
Exterior view of Ocean House by Ellington featuring sculptural architecture, curved balconies, lush landscaping, and luxury waterfront residences in Dubai. Presented by Tohid Fetrat.

Ellington Properties: Design-Led Boutique Residences With Curated Interiors

Ellington Properties, founded in 2014, is a design-led developer of apartments, villas and waterfront homes, with 30 developments launched and delivered.

View the Ellington Developer Profile

Construction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.

FAQs

Ellington Sands 2 Construction Updates Frequently Asked Questions

Ellington Sands 2 is an active project on the Dubai Land Department register, recorded as Ellington Sands II under project number 4140, and its latest reading is 0.38%, recorded on 5 June 2026 while enabling works were progressing at the site. Handover is expected in Q4 2028. Every dated reading is plotted in the Ellington Sands 2 inspection timeline above.

One dated reading: 0.38% on 5 June 2026, which is 0.38 points above the 0% the DLD app lists as the previous inspection. That earlier 0% carries no date, so the timeline shows it as a point on the track rather than as a row, and no pace is measured from it. The full detail of the dated reading is in the Ellington Sands 2 construction update for June 2026.

The Dubai Land Department register records construction starting on 10 October 2025 and the project being registered on 31 October 2025, so the recorded start comes 21 days before registration; both dates are shown here exactly as the register prints them. The first dated reading followed 238 days after the recorded start: 0.38% on 5 June 2026.

Each figure comes from the Dubai Land Department project register for project 4140, read alongside the RERA progress report of the same date. The report for 5 June 2026 notes enabling works progressing at the site and prints no percentage, so 0.38% is the register's reading. That reading was 148 days old on 31 October 2026, when this page was prepared, and a newer one may already appear in the Dubai REST app. The general method is set out on the Dubai Construction Updates hub.

They fall in the same quarter. The DLD register gives 31 December 2028 as the registered completion date for project 4140, the last day of Q4 2028, and handover of Ellington Sands 2 is expected in Q4 2028. From the 5 June 2026 reading of 0.38%, 940 days remain to the registered date. Actual handover is confirmed by Ellington as the build completes, and this page's record is updated as each new inspection is recorded.

No measured pace exists yet, because the only reading before 5 June 2026 is an undated 0%. As arithmetic, not a forecast: 0.38 points over the 238 days from the 10 October 2025 start averages about 0.05 points per 30-day month, and reaching 100% by the 31 December 2028 registered completion date would take about 3.18 points per 30-day month. The working is laid out in the Ellington Sands 2 pace analysis above.

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is keeping the Ellington Sands 2 construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.