DAMAC · DAMAC Hills 2
ELO at DAMAC Hills 2 Construction Updates
The Dated Build Record Behind DAMAC's Two-Wing Project in DAMAC Hills 2
ELO recorded 21.5% construction progress when RERA inspected on 15 April 2026, the first dated reading published for DAMAC's 557-apartment build in DAMAC Hills 2.
Construction tracking against RERA inspection data, updated after every recorded inspection.
Direct advisor access. Every message answered personally, never by a call center.
Construction Snapshot
ELO at DAMAC Hills 2 at a Glance
ELO is a 557-apartment development on plot 777 in Madinat Hind 4, the survey area that carries the DAMAC Hills 2 community. Project 2995 entered the Dubai Land Department register on 12 June 2024 and construction was recorded as started on 03 July 2024, which makes this one of the shorter build records tracked on this site. Because the whole scheme is one registered G+2P+14+R structure of 33,559.08 sq m, two curved wings rising off a shared podium, rather than a phased villa release, the recorded percentage here moves in fewer and larger steps than it does on a multi-plot community project.
2995
Active
03 July 2024
557 residential units
33,559.08 sq m
Q4 2026 (developer stated)
Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.
Inspection Record
ELO at DAMAC Hills 2 Construction Update Timeline
One dated reading exists for ELO so far: the RERA inspection of 15 April 2026, which recorded 21.5%. The register view also carries a previous-inspection figure of 13.44% with no inspection date published beside it, so that number is acknowledged here but is deliberately left off the track, out of the table, and out of every calculation on this page. Until a second dated reading is published, the track below runs from the 03 July 2024 construction start straight to the single April 2026 dot.
| Inspection Month | Construction Progress | Inspection Date | Full Update |
|---|---|---|---|
| April 2026 | 21.5% | 15 April 2026 | View the April 2026 update |
Pace Analysis
How Fast ELO at DAMAC Hills 2 Has Been Built
With a single dated reading in the register, no velocity can be measured between inspections at ELO. Two figures can be derived honestly from the dates that do exist, and the distance between them is the most important thing on this page:
- Jul 2024 to Apr 2026: whole-build average from construction start to the 21.5% readingAbout 1.0 points per month (derived)
- Apr 2026 to a December 2026 completion: rate needed to close the remaining 78.5 pointsAbout 9.2 points per month (schedule-implied)
Neither number is a measured pace. The first spreads 21.5 points across the 21 months and 12 days between the 03 July 2024 start and the 15 April 2026 inspection, so it flattens whatever mobilisation delays and structural bursts sat inside that window. The second is arithmetic against the stated Q4 2026 handover: closing 78.5 points by the end of December 2026 asks for roughly nine times the average this build has posted so far. The notes filed with the 15 April 2026 inspection explain part of that shape: the substructure was effectively complete, the frame stood at uneven heights across the footprint, and mechanical and electrical installation had only just begun. What the record cannot yet show is how quickly the floors above ground are being added, and that is exactly what the next dated inspection will settle. For anyone holding a unit or weighing an entry, the honest position is that ELO's stated handover window and its recorded progress do not currently line up, and the figure to watch is the next percentage RERA publishes.
Get the Next Inspection Figure First
Tell me you are tracking ELO at DAMAC Hills 2 and I will send you the next recorded figure and site photos directly, ahead of the page update.
Get the Next Update on WhatsAppProject Profile
About ELO at DAMAC Hills 2
The build percentage only matters in the context of what is being delivered. The full project guide covers what buyers are tracking toward on this page:

ELO at DAMAC Hills 2: DAMAC Apartments Facing the Parklands
ELO at DAMAC Hills 2 places 557 apartments in two curved wings above a shared podium, facing the parklands.
View the ELO at DAMAC Hills 2 Project GuideConsidering an Entry at Structural Stage?
Availability at ELO shifts as the structure rises and each inspection is recorded. If the record on this page is what brought you here, I can tell you what is currently open before the remaining inventory narrows further.
Ask About Remaining Availability on WhatsAppStage Record
ELO at DAMAC Hills 2 Build Stages, Mapped to the Inspections
Each stage below is tied to a date this project actually carries in the register or the inspection report, so the stages ahead of the 15 April 2026 reading are shown as pending rather than described as progress that has been verified.
Registration and Site Start
Project 2995 was registered with the Dubai Land Department on 12 June 2024, and construction on plot 777 was recorded as started three weeks later on 03 July 2024.
Enabling Works and Foundation
By the 15 April 2026 inspection the substructure on the Madinat Hind 4 plot was recorded as all but finished, while site mobilization was still logged as ongoing.
Structure and Early MEP
That same inspection put the frame at uneven heights across the G+2P+14+R structure, with mechanical and electrical installation logged as barely started.
Blockwork, Facade, and Internal Finishes
The registered project description sets out a concrete structure with block infill and internal and external finishes, none of which has yet appeared in a dated reading for ELO.
Commissioning and Handover
The 80% and 90% building completion milestones in the payment schedule fall inside this stage, followed by final approvals and the handover DAMAC confirms.
What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on ELO at DAMAC Hills 2's own record.
Buyer Position
Tracking Your Position at ELO at DAMAC Hills 2
This page is one of four project resources that together cover a ELO at DAMAC Hills 2 purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

ELO at DAMAC Hills 2 Construction Updates
This page: the dated inspection record for ELO, from the July 2024 start toward handover.

ELO at DAMAC Hills 2 Golden Visa: Two Apartments Combined
ELO at DAMAC Hills 2, a 557-apartment DAMAC tower, qualifies only through combined ownership, one 1 bedroom plus one 2 bedroom.
Read the ELO at DAMAC Hills 2 Golden Visa Guide
ELO at DAMAC Hills 2 Escrow: DAMAC's First Elo Phase on Record
ELO at DAMAC Hills 2 takes funds into Emirates NBD escrow, DLD project 2995, 557 units 21.5% certified by April 2026.
Verify the ELO at DAMAC Hills 2 Escrow AccountApproaching Handover
Between 21.5% and Handover: What ELO at DAMAC Hills 2 Buyers Should Do Now
At structural stage the useful buyer work is administrative rather than physical, and it is worth doing while the record is still short. Three things are worth settling before the next dated reading rather than after it.
First, separate the installments that fall on calendar dates from the two that fall on construction milestones. On ELO's published schedule most payments run against months from the sale date, but the 80% and 90% building completion milestones are triggered by verified progress, which is the figure this page tracks; the ELO DAMAC Hills 2 escrow account page covers how those releases are certified.
Second, follow the record itself rather than the launch material. With one dated reading at 21.5% and a stated Q4 2026 window, the next RERA percentage is the only thing that will confirm or move the delivery picture, and every reading published for project 2995 is added to the timeline above.
Third, if your purchase may support residency, check the eligibility path early rather than near completion, since the title deed timing shapes the application; the ELO DAMAC Hills 2 Golden Visa guide sets out where an off-plan purchase stands.
Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.
The Wider Picture
Explore DAMAC Hills 2 Structure
A build record is only half the picture; the other half is what is already standing around it. These three pages put ELO's progress in its community, market, and developer context:

DAMAC Hills 2 Properties for Sale
Browse villas, townhouses and selected apartments for sale in DAMAC Hills 2, with prices and payment plans.
See DAMAC Hills 2 Properties for Sale
DAMAC Hills 2 Community Overview
Read the DAMAC Hills 2 guide: a self-contained villa community with themed clusters, lifestyle zones and family amenities.
Explore the DAMAC Hills 2 Community
DAMAC Properties: Lagoon Communities, Golf Villas and Branded Collaborations
Founded in 2002, DAMAC has delivered 48,000 homes and is known for large-scale master communities, luxury residential projects and branded collaborations.
View the DAMAC Developer ProfileConstruction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.
FAQs
ELO at DAMAC Hills 2 Construction Updates Frequently Asked Questions
ELO carries DLD project number 2995 with an active status, and its most recent dated reading is 21.5%, taken at the RERA inspection on 15 April 2026, which places it in structural phase. Every dated percentage sits in the inspection timeline further up this page.
The 15 April 2026 inspection recorded 21.5% construction progress. Its notes describe a substructure essentially complete, a frame standing at uneven heights across the plot, and mechanical and electrical work only just begun. The register lists a previous-inspection figure of 13.44%, which is 8.06 points lower, but publishes no date beside it, so no interval and no pace can be calculated from that pair. The site report is in the April 2026 ELO construction update.
Only one RERA inspection date has been published for project 2995 so far, on 15 April 2026, which is 21 months after the 03 July 2024 construction start. The earlier 13.44% figure carried in the register has no published inspection date, and this site does not plot, date, or calculate from undated readings. Each new dated percentage is added to the timeline as RERA records it.
DAMAC states a Q4 2026 handover window for ELO. Measured against the 21.5% recorded on 15 April 2026, closing the remaining 78.5 points by the end of December 2026 would require roughly 9.2 percentage points per month, against a whole-build average of about 1.0 points per month since the July 2024 start. Actual handover is confirmed by DAMAC, and this page's record is updated when the next inspection is recorded.
DLD registration records show 557 residential units and a built-up area totalling 33,559.08 sq m. The mix is one and two bedroom apartments spread across fourteen residential levels, and layouts are set out in the ELO DAMAC Hills 2 project guide.
Project 2995 was registered with the Dubai Land Department on 12 June 2024 and construction was recorded as started on 03 July 2024. The first tracked inspection, dated 15 April 2026, recorded 21.5% progress.
As of 15 April 2026 the foundation on plot 777 was recorded as effectively finished and the frame had risen to varying heights, with mechanical and electrical installation barely started. Blockwork, facade, and internal and external finishes had not yet reached a dated reading at 21.5%.
The registered project description for 2995 sets out G+2P+14+R floors: ground level, two podium levels, fourteen residential floors, and a roof level. The 557 apartments sit across those fourteen levels, split between two curved wings above the shared podium.
ELO occupies plot 777 in Madinat Hind 4, the survey area covering DAMAC Hills 2, facing the community parklands rather than sitting inside the villa clusters. Community amenities and the wider layout are covered on the DAMAC Hills 2 community page.
Most installments on ELO's published schedule fall on months counted from the sale date, but two are tied to verified construction: one at the 80% building completion milestone and one at 90%, with the balance due on completion. Since the last dated reading was 21.5% on 15 April 2026, neither milestone has been reached. How milestone releases are certified is covered on the ELO escrow account guide.

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is keeping the ELO at DAMAC Hills 2 construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.
Ask your question, get your answer. No obligation and no follow-up unless you ask for it.