Ellington Properties · Jumeirah Islands · Construction Update

Eltiera Heights Construction Update - July 2026

July 2026 Inspection Records Eltiera Heights at 3.01% on the DLD Register in Jumeirah Islands

Enabling works and piling were progressing at the Eltiera Heights site when RERA inspected on 20 July 2026, with the DLD register recording 3.01 percent.

Direct advisor access. Every message answered personally, never by a call center.

3.01%DLD Register Reading
20 July 2026Inspection Date
Q4 2028Expected Completion
3852DLD Project Number

DLD Register Inspection Data

Eltiera Heights Construction Snapshot

A 2.68 point rise on the previous DLD reading of 0.33%, a reading the register shows without a date, puts Eltiera Heights at 3.01% and at the very start of the build, the stage where the payment schedule and the escrow account deserve more attention than the percentage itself.

Project Name

Eltiera Heights by Ellington Properties

Project Number

3852

Project Status

Active

Construction Progress

3.01%

Inspection Date

20 July 2026

Construction Start

19 June 2025

Total Units

355 residential units

Total Built Area

38,016.53 sq m

Expected Completion

Q4 2028

Data source: DLD project register reading for project 3852 on the inspection report card dated 20-07-2026, read alongside the RERA Independent Progress Monitoring Report of the same date, which records a progress status rather than a percentage. The reading was recorded on 20 July 2026 and the register changes after each RERA visit, so check it for a newer figure before acting. The image at the top of this page is a developer rendering, not site photography. Construction tracking against RERA inspection data runs across the full tohidfetrat.com project portfolio and is reviewed after every published cycle. Last updated: July 2026.

Want each new reading the day it publishes? Message me on WhatsApp and I will send it to you directly: one message per inspection cycle, nothing else. Message me on WhatsApp

This Inspection Cycle

Eltiera Heights Construction Progress Summary

Construction on the Eltiera Heights plot was recorded as starting on 19 June 2025, and on 20 July 2026, 396 days on, the register stood at 3.01%: about 0.23 points per month across the whole build so far, which is arithmetic, not a forecast. Early readings commonly sit low while enabling works and piling are underway, and the RERA report places the tower at exactly that point.

On the Register
  • Construction start recorded on 19 June 2025
  • Project 3852 registered with the DLD on 11 September 2025
  • Trust account bank: National Bank of Ras Al Khaimah, per the RERA report
In Progress at 3.01%
  • Enabling works at the site, per the 20 July 2026 RERA report
  • Piling works at the site, per the same report
  • RERA progress status: Enabling Works, Progressing
Ahead of Handover
  • Basement, ground and three podium levels (B+G+3P+37+R in the RERA report)
  • 37 residential floors and the roof, holding the 355 residences
  • The four instalments tied to 20%, 30%, 40% and 50% construction
  • Handover expected in Q4 2028
Next inspectionPublished in the DLD project register after the next RERA site visit; a figure newer than the 20 July 2026 reading may be on the register by the time you read this.
Completion targetQ4 2028 expected handover; the DLD register records a registered completion date of 31-12-2028. Confirm the current construction timetable with the developer in writing.
Remaining distance96.99 percentage points separate the 20 July 2026 reading of 3.01% from 100%.

Payment Linked Progress

What 3.01% Progress Means for Eltiera Heights Buyers

On the Eltiera Heights 70/30 plan, six instalments worth 50% of the price fall due on fixed dates within 360 days of each buyer's own reservation, independent of construction, while four 5% instalments wait for the 20%, 30%, 40% and 50% construction stages. At the 3.01% reading of 20 July 2026, none of those four had been triggered. At this stage, four actions matter most.

Before Each Instalment

Verify the escrow account

Every instalment ahead of handover should go only to the DLD regulated escrow account registered for project 3852 with National Bank of Ras Al Khaimah. Eltiera Heights escrow account verification is the step before any transfer; the lookup itself takes about two minutes against the official DLD project record.

Within 360 Days of Reservation

Reread your SPA payment schedule

Check how your sale and purchase agreement dates the six reservation-linked instalments and defines the construction stages that trigger the next four, then map both against the Q4 2028 handover. Not sure how your instalments map to this reading? Send me your SPA schedule and I will map it against the recorded milestones.

After Booking

Confirm your Oqood registration

Oqood is the DLD register of off plan sales, and once your booking is processed the unit should be recorded in your name against project 3852. Ask the developer for written confirmation of the Oqood registration and keep it with your SPA before the next reservation-dated instalment.

Every Cycle

Track the construction-linked stages

The four construction-linked instalments fall due on completion of 20%, 30%, 40% and 50% construction, as your SPA defines it, so each new reading shows how close the next one is. Eltiera Heights construction updates hub records every published cycle.

General framework, not legal advice: milestone definitions, notice periods, and fee obligations are set by your individual SPA and the DLD record, and both should be read directly.

Buying at 3.01%?

Entering at the start of the build trades time for runway: the 70/30 plan runs its full course from your reservation, and capital stays committed until the expected Q4 2028 handover. Every payment goes to the DLD-registered escrow account for project 3852, released against verified construction progress.

Entering Now at 3.01%
  • Enabling works and piling progressing, per the 20 July 2026 RERA report
  • Expected Q4 2028 handover, with the full payment runway ahead
  • Four 5% instalments still tied to the 20% to 50% construction stages
Typical Near-Completion Entry
  • Most construction risk carried by earlier buyers
  • Months rather than years to the handover date
  • A larger share of the price due within a short window
AED 1.80M ≈ USD 490KStarting Price
70/30 Plan30% Due on Completion
Q4 2028Expected Handover
Ask What Is Available at Eltiera Heights

Limited Units Available, per the project page as of this update; availability shifts between cycles.

About the Development

Eltiera Heights Project Details

Eltiera Heights by Ellington Properties in Jumeirah Islands project rendering of residential towers with a landscaped street and surrounding city skyline in Dubai - Presented by Tohid Fetrat
Jumeirah Islands · Ellington Properties

With enabling works and piling progressing at the July 2026 inspection, Eltiera Heights is an early-stage single tower of 355 residences, 1 to 3 bedroom apartments and 4 bedroom penthouses, on the Jumeirah Lakes Towers side of Jumeirah Islands. Starting prices: AED 1.80M ≈ USD 490K.

For buyers entering at this stage, the trade off is the longest wait to the expected Q4 2028 handover against first pick of the remaining layouts and the full span of the 70/30 plan.

Eltiera Heights by Ellington Properties Project Guide

Site Context This Cycle

Explore Eltiera Heights Location on Dubai Map

Eltiera Heights takes a plot on the Jumeirah Lakes Towers side of Jumeirah Islands, east of Sheikh Zayed Road, rather than among the community's lake-ringed clusters, and the RERA report describes a tower planned to rise from a basement and three podium levels; the July 2026 cycle is therefore about preparing the ground, with enabling works and piling recorded in progress.

Around the plot, the district is established: the developer's location guide puts Jumeirah Islands Pavilion and Jumeirah Lakes Towers about a minute's drive away, and the developer's location map shows the Dubai Metro line along Sheikh Zayed Road beside Jumeirah Lakes Towers. For buyers at this stage, the wait until the expected Q4 2028 handover is for the tower, not for the neighbourhood around it. See the plot's position on the interactive Dubai real estate map. See the project’s position on the interactive Dubai real estate map.

Interactive Dubai real estate map preview
Click to view Eltiera Heights by Ellington Properties on Dubai Map

Buyer Resources for This Project

Investing in Eltiera Heights During Early Construction

At the enabling stage, protecting each instalment and planning residency matter more than handover logistics. Each resource below is matched to where Eltiera Heights stood at the 20 July 2026 reading.

Eltiera Heights by Ellington Properties in Jumeirah Islands construction updates cover image featuring a project rendering of a residential tower and surrounding high-rise skyline in Dubai - Presented by Tohid Fetrat
You Are Here

Eltiera Heights Construction Updates

This page: the July 2026 register reading and RERA notes for Eltiera Heights at enabling stage.

Eltiera Heights by Ellington Properties in Jumeirah Islands Golden Visa concept graphic with a gold card over a rendering of residential towers in Dubai - Presented by Tohid Fetrat

Eltiera Heights Golden Visa: 2 and 3 Bedroom Apartments and Penthouses Qualify

At Eltiera Heights, Ellington Properties' Jumeirah Islands tower, every unit from the 2 bedroom apartment upward clears the AED 2M threshold.

Read Eltiera Heights Golden Visa Guide
Eltiera Heights by Ellington Properties in Jumeirah Islands escrow account concept graphic featuring a shield and padlock over a rendering of a tower exterior in Dubai - Presented by Tohid Fetrat

Eltiera Heights Escrow Account at National Bank of Ras Al Khaimah

Eltiera Heights, DLD project 3852, escrows 355 residences at National Bank of Ras Al Khaimah and read 3.01% in July 2026.

Verify Eltiera Heights Escrow Account

Update Timeline

Other Eltiera Heights Construction Updates

July 2026 is the first monthly record for Eltiera Heights on this site; each new inspection cycle joins the construction updates hub as it publishes, reading by reading.

All Eltiera Heights Construction Updates

FAQs

Eltiera Heights Construction Progress in July 2026: Frequently Asked Questions

The DLD project register recorded 3.01% for Eltiera Heights, project 3852, on the inspection report dated 20 July 2026, with a previous reading of 0.33% whose date the register does not show. The RERA report of the same date prints no percentage and records the progress status as Enabling Works, Progressing.

Yes. Q4 2028 is the developer's anticipated handover, and the DLD register showed a registered completion date of 31-12-2028 in the 20 July 2026 record; both can be revised between inspection cycles, so buyers should confirm the current construction timetable with the developer in writing. How registered dates and inspection cycles work is covered on the Eltiera Heights construction updates hub.

The RERA Independent Progress Monitoring Report for 20 July 2026 notes that enabling works and piling were progressing at the site, with the progress status recorded as Enabling Works, Progressing. The report describes the project as a mixed-use residential tower with retail, configured B+G+3P+37+R, and it carries inspection photographs.

At 3.01% on 20 July 2026, none of the four 5% instalments that the 70/30 plan links to the completion of 20%, 30%, 40% and 50% construction had been triggered. The six instalments dated from each buyer's own reservation, 50% of the price in total, follow their own calendar within 360 days of reservation whatever the reading, and each SPA defines how a construction stage is confirmed.

The DLD app's inspection report card for 20 July 2026 lists 0.33% as the previous inspection but does not display the date it was taken. Without that date no pace can be measured between the two readings, so this page marks 0.33% as an undated point and measures its whole-build arithmetic from the 19 June 2025 construction start instead.

No. It is a developer rendering of the planned tower beside the Jumeirah Islands lakes, used to illustrate this update. It shows the design intent, not the condition of the site on 20 July 2026, when the RERA report recorded enabling works and piling in progress; the RERA inspection photographs are not reproduced on this page.

A Question the FAQ Can Not Answer?

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is helping you read the July 2026 inspection record for Eltiera Heights correctly before your next payment decision. Client identities and transactions are never published or referenced. Message me directly: you will always reach me personally, never a call center or sales team.

Ask your question, get your answer. No obligation and no follow-up unless you ask for it.

Get Progress Alerts