Enre Residence by Imtiaz in Dubai South Residential District project rendering used for the July 2026 construction update showing the planned residential building with stacked balconies and a landscaped entrance in Dubai - Presented by Tohid Fetrat

Imtiaz · Dubai South Residential District · Construction Update

Enre Residence Construction Update - July 2026

July 2026 DLD Register Reading Places Enre Residence at 14.63% Construction Progress in Dubai South

Substructure and superstructure works were under way at Enre Residence on 28 July 2026, after enabling and foundation works completed, with 14.63% on the DLD register.

Direct advisor access. Every message answered personally, never by a call center.

14.63%DLD Register Progress
28 July 2026Inspection Date
Q1 2028Expected Handover
4336DLD Project Number

DLD Register Data

Enre Residence Construction Snapshot

14.63% on the DLD register at 28 July 2026 places Enre Residence in the enabling and foundations band, the stage where escrow checks and the dated payment schedule carry more weight for a buyer than anything yet visible on site.

Project Name

Enre Residence by Imtiaz

Project Number

4336

Project Status

Active

Construction Progress

14.63%

Inspection Date

28 July 2026

Construction Start

15 February 2026

Total Units

169 residential units

Total Built Area

15,615.26 sq m

Expected Completion

Q1 2028

Data source: Dubai Land Department project register reading for project 4336 dated 28 July 2026, read with the RERA Independent Progress Monitoring Report of the same date, which records the site notes and prints no percentage of its own. The image at the top of this page is a developer rendering of the planned building, not a site photograph. Construction tracking against RERA inspection data runs across the full tohidfetrat.com project portfolio and is reviewed after every published cycle. Last updated: July 2026.

Want each new reading the day it publishes? Message me on WhatsApp and I will send it to you directly: one message per inspection cycle, nothing else. Message me on WhatsApp

This Inspection Cycle

Enre Residence Construction Progress Summary

At the 28 July 2026 reading the DLD register showed Enre Residence at 14.63%, 7.38 points above the previous inspection figure of 7.25%, which the register displays without a date, so no monthly pace can be drawn from the pair. The RERA report from the same day places the site past its enabling and foundation works, with the substructure and superstructure both being built.

Completed
  • Enabling works, recorded as completed on 28 July 2026
  • Foundation works, recorded as completed in the same RERA report
  • Project registration in the DLD register on 23 February 2026
In Progress at 14.63%
  • Site mobilisation, noted by RERA as ongoing
  • Substructure works for the single residential building
  • Superstructure works rising from the completed foundations
  • Main contract status recorded as Progressing
Ahead of Handover
  • Ground floor, nine residential floors and roof level of the B+G+9+R building
  • First-floor podium amenity deck and the roof-level facilities
  • Interiors for the 169 apartments and the single retail unit
Next inspectionPosted to the DLD project register after the next RERA site visit; no date is announced in advance, and each new reading gets its own record.
Completion datesQ1 2028 expected handover per the developer; 15 August 2028 is the registered completion date in the DLD register as of July 2026.
Remaining distance85.37 percentage points separate the 28 July 2026 reading from 100%.

Dated Payments, Recorded Progress

What 14.63% Progress Means for Enre Residence Buyers

Enre Residence is sold on a dated 60/40 plan rather than on construction milestones, so instalments fall due on the calendar while progress is recorded separately on the DLD register. At the 28 July 2026 reading, 25% of the price had been called against 14.63% recorded progress, with the 15 August 2026 instalment 18 days away; by 21 October 2026, when this page was prepared, 30% had fallen due. At this stage of Enre Residence, four actions matter most.

Before Each Dated Instalment

Verify the escrow account

Every instalment on the dated plan should go only to the DLD regulated escrow account registered for project 4336 with United Bank Limited. The Enre Residence escrow account guide sets out the check before any transfer; the lookup itself takes about two minutes against the official DLD project record.

Before Your Next Instalment

Reread your SPA payment schedule

Check how your sale and purchase agreement sets the remaining dated instalments, the 40% completion payment and the handover notice period, and map those clauses against the Q1 2028 handover. Not sure how your instalments line up with this reading? Send me your SPA schedule and I will map it against the recorded register readings.

After Booking

Confirm your Oqood registration

An off plan sale in a building at this stage is recorded on the Dubai Land Department interim register, known as Oqood, under project 4336. Keep that registration record with your SPA: it is what ties your apartment to the project until a title deed is issued at completion.

Every Cycle

Track the remaining readings

With 85.37 points still to be recorded after July 2026, many register readings lie between this one and completion. The Enre Residence construction updates hub keeps each reading in one place as it is posted.

General framework, not legal advice: instalment dates, notice periods, and fee obligations are set by your individual SPA and the DLD record, and both should be read directly.

Buying at 14.63%?

Entering at an early reading trades a longer wait for the widest choice of layouts: the building is still at substructure and superstructure stage, handover is expected in Q1 2028, and the price is agreed before most of the construction is on record. Every instalment goes to the DLD-registered escrow account for project 4336, released against construction progress recorded by the Dubai Land Department.

Entering Now at 14.63%
  • Enabling and foundation works recorded as completed on 28 July 2026
  • 40% of the price held until completion, expected in Q1 2028
  • Instalments already due settled at signing, then dated payments to December 2027
Typical Late Stage Entry
  • More of the structure visible before signing
  • A shorter wait between purchase and handover
  • Less instalment runway left before the completion payment
AED 600K ≈ USD 163KStarting Price
60/40 Plan40% Due on Completion
Q1 2028Expected Handover
Ask What Is Available at Enre Residence

5 Units Available per the project page as of this update; availability shifts between cycles.

About the Development

Enre Residence Project Details

Enre Residence by Imtiaz in Dubai South Residential District project rendering of the illuminated residential building at dusk viewed from the street with palm trees in Dubai - Presented by Tohid Fetrat
Dubai South Residential District · Imtiaz

With enabling and foundation works completed by 28 July 2026, Enre Residence is an early-stage B+G+9+R building in Dubai South Residential District with 169 apartments (studio, one and two bedroom) and one retail unit. Starting prices: AED 600K ≈ USD 163K.

For buyers entering at this stage, the trade off is a longer wait to handover against a price agreed now, with 40% of it held back until completion, expected in Q1 2028 per the developer.

Enre Residence by Imtiaz Project Guide

Site Context This Cycle

Explore Enre Residence Location on Dubai Map

Enre Residence occupies a corner plot in Dubai South Residential District, with its lobby and single retail unit planned along a curved road frontage and the apartments set above a first-floor podium deck. At this reading the works recorded by RERA were still at foundation and substructure level, so the street frontage, the podium deck and the roof facilities that will define the finished address all remain ahead.

The district around the plot is already established, with residential buildings, landscaped areas and a central lake in place, and Imtiaz places the site within minutes of Al Maktoum International Airport and Expo City. For a buyer at the foundations stage, the neighbourhood question is largely answered today, while the building itself stays the open variable until handover in Q1 2028. See the project's position on the interactive Dubai real estate map. See the project’s position on the interactive Dubai real estate map.

Interactive Dubai real estate map preview
Click to view Enre Residence by Imtiaz on Dubai Map

Buyer Resources for This Project

Investing in Enre Residence During Early Construction Progress

At the enabling and foundations stage, payment protection and residency planning come well before any handover preparation. Each resource below is matched to where Enre Residence stood at the July 2026 reading.

Enre Residence by Imtiaz in Dubai South Residential District construction updates cover image featuring a project rendering of a stepped residential building and landscaped forecourt in Dubai - Presented by Tohid Fetrat
You Are Here

Enre Residence Construction Updates

This page: the July 2026 DLD register reading and RERA site notes for Enre Residence.

Enre Residence by Imtiaz in Dubai South Residential District Golden Visa concept graphic with a gold card next to an aerial rendering of the residential building in Dubai - Presented by Tohid Fetrat

Enre Residence by Imtiaz Golden Visa: An Honest Unit-by-Unit Check

Enre Residence is Imtiaz's 169-residence freehold building in Dubai South Residential District, open to all nationalities, under Oqood now.

Read Enre Residence Golden Visa Guide
Enre Residence by Imtiaz in Dubai South Residential District escrow account concept graphic featuring a shield and padlock above an aerial residential building rendering in Dubai - Presented by Tohid Fetrat

Enre Residence Escrow: Imtiaz in Dubai South Residential District

Imtiaz's Enre Residence is DLD project 4336, 170 units escrowed with United Bank Limited, certified 14.63% in July 2026.

Verify Enre Residence Escrow Account

Update Timeline

Other Enre Residence Construction Updates

July 2026 is the first monthly record published for Enre Residence; later readings join this timeline as the DLD register moves past 14.63%.

All Enre Residence Construction Updates

FAQs

Enre Residence Construction Progress in July 2026: Frequently Asked Questions

Enre Residence stood at 14.63% on the Dubai Land Department project register at the reading dated 28 July 2026, for project 4336. The RERA Independent Progress Monitoring Report of the same date prints no percentage of its own: it records the site activity and a progress status of Main Contract, Progressing, so 14.63% is the register's figure rather than one taken from the report.

The register showed 7.25% as the previous inspection reading alongside the 28 July 2026 figure, but it does not display the date of that earlier reading. Without a date, the two readings cannot be turned into a monthly rate of progress, so 7.25% is recorded here as an undated earlier point only.

Handover remains expected in Q1 2028 per the developer, which is also when the final 40% of the price falls due under the dated plan. The DLD register separately lists 15 August 2028 as the registered completion date for project 4336 as of the July 2026 record. Either date can be revised in a later record, and any revision would appear in a later reading on the Enre Residence construction updates hub.

The RERA report of 28 July 2026 notes that mobilisation was ongoing, that enabling and foundation works had been completed, and that substructure and superstructure works were under way. It describes the project as a B+G+9 residential building, and the report carries inspection photographs as part of the record.

The DLD register records construction as started on 15 February 2026 and the project as registered on 23 February 2026, eight days later. Both dates are shown here exactly as recorded, and the 14.63% reading of 28 July 2026 came 163 days after the recorded start.

No. The hero image is a developer rendering of the planned Enre Residence building, used to illustrate this update, and it is not evidence of construction progress. The evidence for July 2026 is the DLD register reading of 14.63% and the RERA report dated 28 July 2026.

A Question the FAQ Can Not Answer?

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is helping you read the July 2026 inspection record for Enre Residence correctly before your next payment decision. Client identities and transactions are never published or referenced. Message me directly: you will always reach me personally, never a call center or sales team.

Ask your question, get your answer. No obligation and no follow-up unless you ask for it.

Get Progress Alerts