Enre Residence by Imtiaz in Dubai South Residential District construction updates cover image featuring a project rendering of a stepped residential building and landscaped forecourt in Dubai - Presented by Tohid Fetrat

Imtiaz · Dubai South Residential District

Enre Residence Construction Updates

The Dated Register Record for a B+G+9+R Building in Dubai South

Enre Residence stood at 14.63% on the DLD register on 28 July 2026, the first dated reading and the baseline for this Dubai South record.

Construction tracking against RERA inspection data, updated after every recorded inspection.

Direct advisor access. Every message answered personally, never by a call center.

14.63%Construction Progress
28 July 2026Latest RERA Inspection
169 residential unitsTotal Units
Project 4336DLD Registration

Construction Snapshot

Enre Residence at a Glance

Enre Residence is a single Imtiaz building of 169 residences in Dubai South Residential District, entered on the DLD register as project 4336 on 23 February 2026, eight days after its recorded construction start of 15 February 2026. Its record is still young: one dated register reading, 14.63% on 28 July 2026, set against the Q1 2028 handover Imtiaz expects and the registered completion date of 15 August 2028. Because the building is a basement, ground floor, nine residential floors and a roof level rather than a tower, its record runs on a short horizon: the February 2026 start and the expected handover sit roughly two years apart.

DLD Project Number

4336

Project Status

Active

Construction Start

15 February 2026

Total Units

169 residential units

Total Built-Up Area

15,615.26 sq m

Registered Completion Date

15 August 2028 (DLD)

Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.

Inspection Record

Enre Residence Construction Update Timeline

The Enre Residence record holds one dated reading so far: 14.63% on the Dubai Land Department register on 28 July 2026, 163 days after the recorded construction start of 15 February 2026. Alongside it, the register displayed a previous inspection figure of 7.25% with no date attached, 7.38 points below the July reading; it sits on the track as an undated point and has no row in the table. The single row below links the July 2026 monthly update, and every later reading adds its own dot and row.

Inspection MonthConstruction ProgressInspection DateFull Update
July 202614.63%28 July 2026View the July 2026 update

Pace Analysis

How Fast Enre Residence Has Been Built

Enre Residence has one dated reading, so there is no inspection-to-inspection velocity to measure yet. Two figures can still be worked out from the register dates, and both are arithmetic, not a forecast:

  • 15 Feb 2026 start to 28 Jul 2026 reading: 14.63 points over 163 days, arithmetic, not a forecastAbout 2.69 points per month
  • 28 Jul 2026 reading to the 15 Aug 2028 registered completion date: 85.37 points over 749 days, arithmetic, not a forecastAbout 3.42 points per month

The first figure averages everything since the February 2026 start, a span that closes with the RERA report of 28 July 2026 listing enabling works and foundations as finished and the substructure and superstructure in progress. The second is a straight division of the 85.37 points still to be recorded by the 749 days left to the registered completion date, and it says nothing about how fast the building will actually rise. Neither number is a forecast: the handover buyers plan around is the Q1 2028 date Imtiaz expects, and no rate is computed to it here. The undated 7.25% figure cannot be turned into a monthly rate either, so the first measured pace for this B+G+9+R building arrives with the next dated register reading. For an end user, that reading shows whether the frame is climbing toward the nine residential floors; for an investor, it is the first like-for-like data point for comparing Enre Residence with other projects on the same register.

Get the Next Inspection Figure First

Tell me you are tracking Enre Residence and I will send you the next recorded figure and site photos directly, ahead of the page update.

Get the Next Update on WhatsApp

Project Profile

About Enre Residence at Dubai South Residential District

A 14.63% reading on 28 July 2026 means more once you know what the register is measuring. The full project guide covers the building this record follows:

Enre Residence by Imtiaz in Dubai South Residential District project rendering of the illuminated residential building at dusk viewed from the street with palm trees in Dubai - Presented by Tohid Fetrat

Enre Residence: An Imtiaz Building in Dubai South

Enre Residence by Imtiaz holds 169 studio, one and two bedroom apartments over nine floors, plus one retail unit.

View the Enre Residence Project Guide

Considering an Early-Stage Entry?

Availability at Enre Residence keeps moving while the building is still at its early register readings. If the record on this page is what brought you here, ask me what is currently available before the choice of layouts narrows further.

Ask About Remaining Availability on WhatsApp

Stage Record

Enre Residence Build Stages, Mapped to the Inspections

Each stage below is pinned to what the Enre Residence record actually shows: the first two are anchored to the 15 February 2026 start and the 14.63% reading of 28 July 2026, and the last three stay marked as not yet recorded until register readings reach them.

Feb 2026 to Jul 2026

Mobilisation, Enabling Works and Foundations

From the recorded construction start on 15 February 2026 to the RERA report of 28 July 2026, which lists enabling and foundation works as finished and mobilisation still continuing.

Current PhaseJul 2026, 14.63% at last reading

Substructure and Superstructure

At the 28 July 2026 reading of 14.63%, substructure and superstructure works were both under way for the B+G+9+R building, with the main contract recorded as progressing.

Not yet recorded

Frame Through Nine Residential Floors and Roof

The rise from the ground floor to the roof level, including the first-floor podium slab, has no register reading yet; the next dated readings will place it.

Not yet recorded

Envelope, Fit-Out and the Podium Amenity Deck

The facade, interiors for the 169 apartments, and the pool deck, gym and roof facilities follow the frame and carry no reading yet.

Toward Q1 2028

Finishing, Commissioning and Handover

Final works close toward the Q1 2028 handover Imtiaz expects; the registered completion date the register carries for project 4336 is 15 August 2028.

What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Enre Residence's own record.

Buyer Position

Tracking Your Position at Enre Residence

This page is one of four project resources that together cover a Enre Residence purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Enre Residence by Imtiaz in Dubai South Residential District construction updates cover image featuring a project rendering of a stepped residential building and landscaped forecourt in Dubai - Presented by Tohid Fetrat
You Are Here

Enre Residence Construction Updates

This page: the DLD register record for Enre Residence, from the February 2026 start to handover.

Enre Residence by Imtiaz in Dubai South Residential District Golden Visa concept graphic with a gold card next to an aerial rendering of the residential building in Dubai - Presented by Tohid Fetrat

Enre Residence by Imtiaz Golden Visa: An Honest Unit-by-Unit Check

Enre Residence is Imtiaz's 169-residence freehold building in Dubai South Residential District, open to all nationalities, under Oqood now.

Read the Enre Residence Golden Visa Guide
Enre Residence by Imtiaz in Dubai South Residential District escrow account concept graphic featuring a shield and padlock above an aerial residential building rendering in Dubai - Presented by Tohid Fetrat

Enre Residence Escrow: Imtiaz in Dubai South Residential District

Imtiaz's Enre Residence is DLD project 4336, 170 units escrowed with United Bank Limited, certified 14.63% in July 2026.

Verify the Enre Residence Escrow Account

Approaching Handover

Between 14.63% and Handover: What Enre Residence Buyers Should Do Now

At 14.63% on 28 July 2026, Enre Residence is a building whose structure is still rising, so the useful work for a buyer sits on the payment and paperwork side rather than in handover preparation. The dated plan sets the timetable here, not the site: the next 10% instalment falls due on 15 December 2026 whatever the register shows by then, so the three steps below are worth settling before that date.

First, check that every instalment goes to the escrow account registered for project 4336 with United Bank Limited; the Enre Residence escrow account page walks through the register lookup.

Second, if residency is part of the plan, read the Enre Residence Golden Visa guide before committing further: at current prices no single apartment reaches AED 2M ≈ USD 545K, and that shapes which route is open to you.

Third, match your layout and remaining instalments against the Enre Residence project guide, which sets out the 60/40 schedule with 40% due on completion, expected in Q1 2028.

Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.

The Wider Picture

Explore Dubai South Residential District Structure

A build record is only half the picture; the other half is the district it is rising into. These three pages put the Enre Residence record in its market, community and developer context:

Aerial view of Dubai South Residential District properties for sale showing landscaped community spaces and a large central pool, Presented by Tohid Fetrat

Dubai South Residential District: Inara Residence in the Freehold Core

Dubai South Residential District, the established freehold core of Dubai South, lists Inara Residence apartments on a 60/40 payment plan.

See Dubai South Residential District Properties for Sale
Aerial view of Dubai South Residential District showing villas, residential buildings, landscaped areas and a central lake, Presented by Tohid Fetrat

Dubai South Residential District: A Freehold Zone Beside Expo City Dubai

Dubai South Residential District has gated villa, townhouse and apartment communities, a lagoon beachfront and freehold title for all nationalities.

Explore the Dubai South Residential District Community
Exterior view of INARA by Imtiaz featuring a contemporary luxury residential tower with elegant balconies, refined façade design, and landscaped surroundings in Dubai, Presented by Tohid Fetrat

Imtiaz Developments: Fully Furnished Residences in Dubai Islands, JVC and Meydan

Imtiaz Developments, founded in 2011, has completed and under-construction design led residential projects in Meydan, JVC and Dubai Islands.

View the Imtiaz Developments Developer Profile

Construction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.

FAQs

Enre Residence Construction Updates Frequently Asked Questions

Enre Residence is under construction as DLD project 4336, with an Active status, and the Dubai Land Department project register showed it at 14.63% on 28 July 2026. The RERA report of that date records the main contract as progressing, with substructure and superstructure works under way on the single B+G+9+R building. The full record sits in the Enre Residence inspection timeline above.

Progress at Enre Residence is tracked through the Dubai Land Department project register for project 4336, which showed 14.63% on 28 July 2026, read together with the RERA progress monitoring report of the same date. That report records site notes and a progress status but prints no percentage of its own, so every figure on this page is a register reading rather than a figure taken from the report. The tracking approach used across the site is set out in the Dubai Construction Updates guide.

Imtiaz expects to hand over Enre Residence in Q1 2028, which is also when the final 40% of the price falls due under the dated 60/40 plan. The DLD register separately carries 15 August 2028 as the registered completion date for project 4336, a date that has not yet passed. The latest register reading, 14.63% on 28 July 2026, sits early in that span, and this page's record is updated as each new reading is posted.

Enre Residence holds 169 residential units, all of them studio, one bedroom and two bedroom apartments, with a single retail unit at ground level alongside them. They sit in one B+G+9+R building that the register showed at 14.63% on 28 July 2026; layouts and prices are covered in the Enre Residence by Imtiaz project guide.

B+G+9+R describes the Enre Residence building as a basement, a ground floor, nine residential floors and a roof level. On the developer's floor plans the ground floor holds the lobby and the retail unit, the first floor combines apartments with the podium amenity deck and pool, floors two to nine are residential, and the roof carries a BBQ area and an outdoor cinema. The RERA report of 28 July 2026 lists the project as a B+G+9 residential building, and the register reading that day was 14.63%.

Across the 163 days from the recorded construction start on 15 February 2026 to the 28 July 2026 reading of 14.63%, Enre Residence averaged about 2.69 points per month. Reaching 100% by the registered completion date of 15 August 2028 would take about 3.42 points per month over the remaining 749 days. Both figures are arithmetic, not a forecast, and a measured pace between readings needs a second dated reading; the working is in the Enre Residence pace analysis above.

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is keeping the Enre Residence construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.

Ask your question, get your answer. No obligation and no follow-up unless you ask for it.

WhatsApp +971543443597
Get the Latest Status