Fairway Villas 2 by Emaar in Emaar South project rendering used for the August 2026 construction update showing a planned modern villa street exterior in Dubai - Presented by Tohid Fetrat

Emaar · Emaar South · Construction Update

Fairway Villas 2 Construction Update - August 2026

August 2026 Inspection Confirms Fairway Villas 2 Reaches 92.16% Construction Progress in Emaar South

Internal finishes, external envelope, MEP, and infrastructure works are progressing at advanced stages across all 309 villas, verified at 92.16 percent in the August 2026 RERA inspection.

Direct advisor access. Every message answered personally, never by a call center.

92.16%Construction Progress
17 August 2026Inspection Date
Q4 2026Expected Completion
2604DLD Project Number

Verified DLD Inspection Data

Fairway Villas 2 Construction Snapshot

A 9.28 point rise to 92.16% puts Fairway Villas 2 into the handover preparation band, the stage where the remaining questions are about acceptance and payment rather than about whether the homes get built. The DLD register carries the earlier 82.88% reading without an inspection date attached, so the interval that gain covers is not stated in the record.

Project Name

Fairway Villas 2 by Emaar

Project Number

2604

Project Status

Active

Construction Progress

92.16%

Inspection Date

17 August 2026

Construction Start

23 July 2023

Total Units

309 villas

Total Built Area

Expected Completion

Q4 2026

Data source: RERA inspection conducted on 17 August 2026, tracked against DLD inspection records; the register lists the previous 82.88% reading with no inspection date beside it, so it is reported here undated. Construction tracking against RERA inspection data runs across the full tohidfetrat.com project portfolio and is reviewed after every published cycle. Last updated: September 2026.

Want each new reading the day it publishes? Message me on WhatsApp and I will send it to you directly: one message per inspection cycle, nothing else. Message me on WhatsApp

This Inspection Cycle

Fairway Villas 2 Construction Progress Summary

The 17 August 2026 inspection moved Fairway Villas 2 from 82.88% to 92.16%, a 9.28 point gain earned in internal finishes, external envelope, MEP, and the infrastructure between the villa rows. Because the register attaches no date to the 82.88% figure, that gain cannot be read as a monthly rate. What the number now describes is a site being finished and prepared for transfer, not one still being built.

Completed
  • Enabling works across the Madinat Al Mataar plot
  • Foundations beneath all 309 villa plots
  • Concrete and block structure on the 187 G+1+R and 122 G+1 homes
In Progress at 92.16%
  • Internal works and internal finishes inside the villas
  • External envelope packages across the villa elevations
  • MEP: mechanical, electrical, and plumbing systems
  • External works and community infrastructure between the rows
Ahead of Handover
  • Closing RERA inspection cycles toward 100%
  • Building completion certificate procedures
  • Handover inside the Q4 2026 window
Next inspectionPublished in the DLD project register after the next RERA site visit; this page updates with each cycle.
Completion targetQ4 2026 handover window, with the 17 August 2026 reading landing inside the final quarter of the programme.
Remaining distance7.84 percentage points separate the August 2026 reading from a fully certified project.

Payment Linked Progress

What 92.16% Progress Means for Fairway Villas 2 Buyers

The Emaar schedule published for this project ties its later instalments to certified construction completion, which makes a verified reading of 92.16% a payment trigger as much as a status line. At this point in the Fairway Villas 2 programme, four actions matter most.

Before Your Final Instalment

Verify the escrow account

Any remaining payment should reach only the DLD regulated escrow account registered for project 2604, held at Dubai Islamic Bank on the August 2026 inspection record. Fairway Villas 2 escrow account verification is the step before any transfer; the lookup itself takes about two minutes against the official DLD project record.

Before the Handover Notice

Map your instalments to certified completion

The published schedule places one instalment at 90% construction completion and the final 15% at 100%, so the 92.16% reading of 17 August 2026 sits between those two triggers. Not sure which instalment your reading has already released? Send me your SPA schedule and I will map it against the certified milestones.

Window Open Now

Book the snagging inspection

Above 90% recorded progress and inside the Q4 2026 window, Fairway Villas 2 sits in the standard booking period for a pre handover inspection. Fairway Villas 2 snagging inspection guide sets out what to document before you sign acceptance.

Every Cycle

Track the closing readings

One or two RERA readings usually remain between 92.16% and completion certification. Fairway Villas 2 construction updates hub carries each one as it reaches the register.

General framework, not legal advice: milestone definitions, notice periods, and fee obligations are set by your individual SPA and the DLD record, and both should be read directly.

Buying at 92.16%?

Buying this late removes the construction question almost entirely: the structure is certified complete, the finishing is at advanced stages, and what is left to decide is which of the remaining villas suits you. Every payment goes to the DLD-registered escrow account for project 2604, released against certified construction progress.

Entering Now at 92.16%
  • Enabling, foundation, and structure works certified complete
  • Handover expected inside the Q4 2026 window
  • The plan's final 15% falls due at 100% construction completion
Typical Launch Entry
  • Delivery risk sits with the buyer from excavation onward
  • Three years or more is the usual wait for a villa community
  • Instalments spread thinly across a long build programme
From AED 3.2M ≈ USD 871KStarting Price
85 / 15 Plan15% Due on Completion
Q4 2026Expected Handover

Limited units were listed as available at the time of this update; availability shifts between cycles.

About the Development

Fairway Villas 2 Project Details

Fairway Villas 2 by Emaar in Emaar South detached villas with illuminated windows and landscaped gardens at dusk in Dubai - Presented by Tohid Fetrat
Emaar South · Emaar

With structure works certified complete, Fairway Villas 2 is a handover stage community of 309 three and four bedroom villas set beside the Emaar South golf course. Published starting prices: AED 3.2M ≈ USD 871K.

Buying at this point trades a long instalment runway for a short wait: the build risk is largely retired, and the balance of the plan lands close to the Q4 2026 handover window.

Site Context This Cycle

Explore Fairway Villas 2 Location on Dubai Map

Fairway Villas 2 sits on plot 3633 in Madinat Al Mataar, wrapped around the southern edge of the Emaar South championship golf course, with 187 G+1+R and 122 G+1 homes threaded along internal sikkas rather than stacked in a tower. That low rise, horizontal layout is why this cycle reads as parallel work: envelope, internal finishes, and external infrastructure advance street by street instead of floor by floor, which is also why a single percentage covers 309 separate buildings.

Emaar South is still filling in around its golf course, so Fairway Villas 2 is completing into a district where the clubhouse, community park, and the earlier Fairway Villas phase are the established anchors while outer plots remain under construction. For anyone weighing a Q4 2026 move in against holding the villa for rent, that half-finished district is the variable to price, not the villa specification. Its exact footprint against the fairways is plotted on the interactive Dubai real estate map. See the project’s position on the interactive Dubai real estate map.

Interactive Dubai real estate map preview

Buyer Resources for This Project

Investing in Fairway Villas 2 Ahead of Q4 2026 Handover

Above 90%, residency planning, payment protection, and defect documentation all come due at once. Each resource below is pinned to the position the August 2026 record puts this project in.

Fairway Villas 2 by Emaar in Emaar South construction updates cover image featuring a project rendering of detached villas and landscaped gardens in Dubai - Presented by Tohid Fetrat
You Are Here

Fairway Villas 2 Construction Updates

This page: the verified August 2026 inspection record for Fairway Villas 2 in Emaar South.

Fairway Villas 2 by Emaar in Emaar South Golden Visa concept with a golden card above a modern villa street exterior in Dubai - Presented by Tohid Fetrat

Fairway Villas 2 Golden Visa Through One Golf-Front Villa

Fairway Villas 2, Emaar's villas wrapped around the Emaar South golf course, qualifies at both 3 and 4 bedroom detached tiers.

Read Fairway Villas 2 Golden Visa Guide
Fairway Villas 2 by Emaar in Emaar South escrow account protection concept with shield and padlock icons above a modern villa street exterior in Dubai - Presented by Tohid Fetrat

Fairway Villas 2 Escrow: Emaar South's Late-Stage Villa Account

Fairway Villas 2 at Emaar South, DLD project 2604, has 309 villas paying Dubai Islamic Bank escrow, 92.16% certified August 2026.

Verify Fairway Villas 2 Escrow Account
Fairway Villas 2 by Emaar in Emaar South snagging inspection concept with an inspection checklist icon beside a furnished dining room in Dubai - Presented by Tohid Fetrat

Fairway Villas 2 Snagging: Astra and Nova Villas on the Golf Course

Fairway Villas 2 is Emaar's cluster of 309 detached villas around the 18-hole golf course, inspected from boundary wall to roof.

Book Fairway Villas 2 Snagging Inspection

Update Timeline

Other Fairway Villas 2 Construction Updates

This is the first inspection cycle published on this page set, so the record starts at 92.16% and grows with every RERA reading that follows it.

All UpdatesFairway Villas 2 Construction Updates Hub
Next Update · One Message Per CycleGet notified the day it publishes
All Fairway Villas 2 Construction Updates

FAQs

Fairway Villas 2 Construction Progress in August 2026: Frequently Asked Questions

As of the RERA inspection conducted on 17 August 2026, Fairway Villas 2 stands at 92.16% construction progress in the DLD project register.

The register moved from 82.88% to 92.16% at the 17 August 2026 inspection, a gain of 9.28 points. No inspection date is attached to that earlier 82.88% reading in the DLD record, so the number of months the gain covers is not published.

Handover is expected within the Q4 2026 window. At the 92.16% recorded on 17 August 2026, 7.84 percentage points separate the project from full certification. What happens between a closing RERA reading and a completion certificate is set out on the Fairway Villas 2 construction updates hub.

Yes. Completion timing in the DLD project register is revised between inspection cycles when site conditions change. The window shown here reflects the position recorded on 17 August 2026; a revised date would surface in the next cycle published on this hub.

The 17 August 2026 inspection notes record enabling, foundation, and structure works as completed, with internal works, external envelope, MEP, internal finishes, external works, and infrastructure all progressing at advanced stages across the 309 villas.

Yes. Above 90% recorded progress and inside the Q4 2026 window, the villas are close enough to completion that independent defect documentation belongs before the handover notice rather than after acceptance, when responsibility for remedial work is harder to place.

A Question the FAQ Can Not Answer?

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is helping you read the August 2026 inspection record for Fairway Villas 2 correctly before your next payment decision. Client identities and transactions are never published or referenced. Message me directly: you will always reach me personally, never a call center or sales team.