Emaar Properties · Emaar South
Fairway Villas at Emaar South Construction Updates
The Verified Build Record of 49 Golf Course Villas in Emaar South
Fairway Villas reached 100% construction at its 07 October 2025 RERA inspection, closing the record that opened with groundbreaking on its Madinat Al Mataar plot in 2023.
Construction tracking against RERA inspection data, updated after every recorded inspection.
Direct advisor access. Every message answered personally, never by a call center.
Construction Snapshot
Fairway Villas at Emaar South at a Glance
Fairway Villas is Emaar's 49-villa enclave on plot 3066 in Madinat Al Mataar, registered with the Dubai Land Department as project 2519 on 19 December 2022. Twenty-nine months separate the 05 May 2023 construction start from the 100% recorded at the inspection of 07 October 2025, and the cards below are the register entries behind that span. Because the register closed this project at Completed rather than at a percentage still climbing, the page reads as a delivery record: the inspection history is final, and everything still open belongs to handover rather than to construction.
2519
Finished
05 May 2023
49 villas
28,037.86 sq m
30 September 2025 (DLD)
Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.
Inspection Record
Fairway Villas at Emaar South Construction Update Timeline
One dated inspection carries this record. On 07 October 2025 the independent monitoring report placed Fairway Villas at 100% with a Progress Status of Completed, 15.05 points above a previous reading of 84.95%. The register publishes no date against that earlier figure, so the track below holds a single dot and the table a single row: there is no second date to plot against, and none is invented here. The row links the full October 2025 update.
| Inspection Month | Construction Progress | Inspection Date | Full Update |
|---|---|---|---|
| October 2025 | 100% | 07 October 2025 | View the October 2025 update |
Reading the dates: the completion date registered for project 2519 is 30 September 2025, and that date has passed. The inspection seven days later, on 07 October 2025, recorded 100% and a Progress Status of Completed, so the register and the build agree even though the registered date fell first. The handover date on record for the villas is Sep 2026, the month in progress as this record is published, and a registered completion date remains an administrative anchor from project registration, never the date keys change hands.
Pace Analysis
How Fast Fairway Villas at Emaar South Has Been Built
Pace normally comes from the interval between two dated inspections. Fairway Villas publishes one dated reading, so three things can be derived honestly from this record and nothing more:
- 05 May 2023 construction start to 100% on 07 October 2025: whole-build averageAbout 3.4 points per month
- Previous reading of 84.95% to the 07 October 2025 reading of 100%15.05 points, interval undated
- Recorded progress remaining between 07 October 2025 and the 100% ceilingZero points outstanding
About 3.4 points per month across 29 months is a steady figure for a two-storey villa cluster, and it is the whole of what this record supports. No velocity can be attached to the 15.05-point movement, because the register carries no date against the 84.95% reading it started from, and a monthly rate derived from an undated figure would be worse than no rate at all. What the numbers do settle is the part that matters to both audiences on this page: an investor reading delivery consistency is looking at a finished 49-villa phase rather than a projection, and an owner planning a move is no longer waiting on construction. The remaining variable sits in handover scheduling and the snagging close-out the October notes recorded as still running, which is a different kind of risk from an unfinished build. One caution belongs with the figures: the reading is roughly eleven and a half months old at the time of writing, so it describes a certified state rather than this week's site condition.
Get the Next Inspection Figure First
Tell me you are tracking Fairway Villas at Emaar South and I will send you the next recorded figure and site photos directly, ahead of the page update.
Get the Next Update on WhatsAppProject Profile
About Fairway Villas at Emaar South at Emaar South Dubai
A closed build percentage only means something beside what was delivered. The full project guide covers the villas behind this record:

Fairway Villas at Emaar South, a Gated Cluster on the Championship Course
Fairway Villas at Emaar South holds 49 three and four bedroom Emaar villas built along the 18-hole championship golf course.
View the Fairway Villas at Emaar South Project GuideConsidering an Entry After Completion?
The villas exist and the inspection record is closed, so an entry now carries no construction variable at all. Availability at Fairway Villas is limited, and what is left narrows as handover proceeds, so ask me for the current position before you compare it with anything still off-plan.
Ask About Remaining Availability on WhatsAppStage Record
Fairway Villas at Emaar South Build Stages, Mapped to the Inspections
Each stage below is pinned to a dated entry in this project's own register rather than to a generic construction sequence, which is why one of the five windows carries no percentage: the register never published a date for the reading that belongs to it.
Registration and Site Start
Project 2519 was registered with the Dubai Land Department on 19 December 2022, and construction on plot 3066 in Madinat Al Mataar began on 05 May 2023, four and a half months later.
Concrete Structure and Block Work
Every one of the 49 houses is a two-storey concrete shell with blockwork, finished on both faces, and producing that shell across the whole enclave is what the first construction year bought.
External Envelope, MEP and Internal Works
The undocumented stretch of this record. The previous reading of 84.95% belongs somewhere inside it, but the register attaches no date to that figure, so the window is named without a percentage against it.
Civil Defence and Completion Certificates
Two certificates close this window: civil defence clearance dated 12 May 2025 and building completion dated 29 July 2025. Water and electrical meters were fixed before the October inspection was carried out.
Snagging, Deep Cleaning and Handover
The 07 October 2025 report closed the build at 100% and Completed, with an undertaking letter provided and only snagging and deep cleaning left open. Handover is set for Sep 2026.
What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Fairway Villas at Emaar South's own record.
Buyer Position
Tracking Your Position at Fairway Villas at Emaar South
This page is one of four project resources that together cover a Fairway Villas at Emaar South purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Fairway Villas at Emaar South Construction Updates
This page: the whole Fairway Villas inspection record, from the May 2023 start to completion.

Fairway Villas at Emaar South Golden Visa, a Wide Margin
Fairway Villas at Emaar South is a 49-villa Emaar enclave whose 3 and 4 bedroom layouts both clear the threshold.
Read the Fairway Villas at Emaar South Golden Visa Guide
Fairway Villas at Emaar South Escrow: The First Fairway Release at 100%
Fairway Villas at Emaar South read 100% certified October 2025, 49 villas escrowed at Dubai Islamic Bank, DLD project 2519.
Verify the Fairway Villas at Emaar South Escrow Account
Fairway Villas at Emaar South Snagging Alongside the Championship Golf Course
Fairway Villas at Emaar South is a community of 49 two storey villas by Emaar, in 3 and 4 bedroom layouts.
Book Fairway Villas at Emaar South SnaggingApproaching Handover
Between 100% and Handover: What Fairway Villas at Emaar South Buyers Should Do Now
With the build recorded at 100% since 07 October 2025, nothing between this page and your keys is construction any more. It is documentation, inspection and acceptance, and all three run on the developer's timetable rather than yours. Handover notices typically give buyers a short window to complete their appointment, so the three steps below belong in the diary now rather than on the day the notice lands.
First, arrange independent snagging so the defects in your villa are on paper before you accept it; the Fairway Villas snagging inspection page covers timing and the extra ground a two-storey house adds to the list.
Second, check your remaining balance against the certified milestones on the Fairway Villas escrow account page, because a project certified complete has no construction triggers left to release funds against.
Third, if your purchase may support residency, settle eligibility before the title deed is issued through the Fairway Villas Golden Visa page, since both villa tiers price above the AED 2M property threshold.
Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.
The Wider Picture
Explore Emaar South Dubai Structure
A build record is one measurement; the ground it sits on is another. These three guides place the Fairway Villas record inside its market, its community and its developer's wider output:

Emaar South Dubai Properties for Sale
Browse apartments, townhouses and villas for sale in Emaar South, with prices, payment plans and availability.
See Emaar South Dubai Properties for Sale
Emaar South Dubai Community Overview
Read the Emaar South guide: a golf community of apartments, townhouses and villas beside Al Maktoum International Airport.
Explore the Emaar South Dubai Community
Emaar Properties: Burj Khalifa, Downtown Dubai and Twenty Master Communities
Emaar, founded in 1997, built Burj Khalifa and Downtown Dubai and has delivered over 85,000 homes across twenty master communities.
View the Emaar Properties Developer ProfileConstruction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.
FAQs
Fairway Villas at Emaar South Construction Updates Frequently Asked Questions
Fairway Villas is recorded as Finished on the Dubai Land Department register for project 2519. The last dated inspection, on 07 October 2025, put the build at 100% with a Progress Status of Completed, and no later reading has been published against the project since. The whole record is in the inspection timeline above.
The reading rose 15.05 points to reach 100% on 07 October 2025, from 84.95% before it. Because the register attaches no date to that 84.95% entry, the 15.05-point gain has no measurable interval behind it, which is why this page publishes an average across the whole build instead of a between-inspection velocity. The working is in the pace analysis above.
Construction is already complete. The 07 October 2025 inspection recorded 100% and a Progress Status of Completed, seven days after the 30 September 2025 completion date registered for project 2519. The handover date on record for the villas is Sep 2026, and that is the date an owner plans around; the registered date is an administrative anchor from project registration rather than a delivery promise.
Forty-nine. The Dubai Land Department register for project 2519 and the October 2025 inspection report agree on the count: 49 houses of two storeys each, in three and four bedroom layouts, built as concrete shells with blockwork and finished on both faces. No project-level built-up area is published in a form this page can verify, so none is stated.
Construction started on 05 May 2023 and reached 100% at the inspection of 07 October 2025, a span of roughly 29 months, which averages about 3.4 percentage points per month across the entire build. That figure is an average and not a phase velocity: only one reading on this record carries a date, so no acceleration or taper between inspections can be read from it.
Construction started on 05 May 2023 on plot 3066 in Madinat Al Mataar, about four and a half months after project 2519 was registered with the Dubai Land Department on 19 December 2022. The first and only dated inspection published on the record came on 07 October 2025 at 100%, documented in the Fairway Villas October 2025 construction update.

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is keeping the Fairway Villas at Emaar South construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.
Ask your question, get your answer. No obligation and no follow-up unless you ask for it.