Fiji at DAMAC Islands by DAMAC Properties in DAMAC Islands project rendering used for the May 2026 construction update showing planned villas and palms along a turquoise lagoon in Dubai - Presented by Tohid Fetrat

DAMAC Properties · DAMAC Islands · Construction Update

Fiji at DAMAC Islands Construction Update - May 2026

1 May 2026 DLD Reading Recorded Fiji 1 at 1.74% With Enabling Works Progressing

RERA's 1 May 2026 visit to Fiji 1 found mobilisation works ongoing, an infrastructure contractor in place, and enabling and infrastructure packages progressing at different stages.

Direct advisor access. Every message answered personally, never by a call center.

1.74%Fiji 1 DLD Reading
1 May 2026Fiji 1 Inspection
Q4 2028Expected Handover
3505Fiji 1 DLD Project

Recorded DLD Inspection Data

Fiji at DAMAC Islands Construction Snapshot

Up 1.49 points from the 25 July 2025 reading, Fiji 1 (DLD project 3505) stood at 1.74% on 1 May 2026: an enabling works figure, and at that stage the escrow account and the Oqood record tell a buyer more than the percentage does. The DLD registers the Fiji cluster in two phases; the record shown here is Fiji 1, and Fiji 2, registered separately, is not covered by this reading.

Project Name

Damac Islands - Fiji 1

Project Number

3505 (Fiji 1)

Project Status

Active (Fiji 1); IPMR: Enabling Works - Progressing

Construction Progress

1.74% (Fiji 1)

Inspection Date

1 May 2026 (Fiji 1)

Construction Start

21 April 2025 (Fiji 1)

Total Units

798 across the Fiji cluster

Total Built Area

69,228.78 sq m (Fiji 1 DLD register)

Expected Completion

Q4 2028

Data source: the DLD project register entry Damac Islands - Fiji 1 (project 3505, status Active, registered 5 February 2025, construction started 21 April 2025, registered completion date 31 December 2028) and the RERA Independent Progress Monitoring Report for the Fiji 1 inspection of 1 May 2026, Progress Status Enabling Works - Progressing. That report prints no percentage, so 1.74% and the earlier 0.25% of 25 July 2025 are Fiji 1 register readings. This page is the record of the 1 May 2026 Fiji 1 inspection, written as of that date; a newer DLD inspection may have been published since. The hero picture is a DAMAC rendering rather than a photograph of the works. Construction tracking against RERA inspection data runs across the full tohidfetrat.com project portfolio and is reviewed after every published cycle. Last updated: May 2026.

Want each new reading the day it publishes? Message me on WhatsApp and I will send it to you directly: one message per inspection cycle, nothing else. Message me on WhatsApp

This Inspection Cycle

Fiji at DAMAC Islands Construction Progress Summary

Between the 25 July 2025 and 1 May 2026 inspections, Fiji 1 went from 0.25% to 1.74%, a 1.49 point gain over 280 days, and the RERA report on the May visit gave its Progress Status as Enabling Works - Progressing. That report lists Fiji 1 as 398 G+2 and G+1 townhouses and villas to be built with a concrete structure, blockwork, and internal and external finishes; every line of the ledger below is taken from the Fiji 1 register and that report.

Completed
  • Fiji 1 entered in the DLD register on 5 February 2025
  • Fiji 1 construction start recorded on 21 April 2025, 75 days after registration
  • Emirates NBD listed as the Fiji 1 trust account bank
  • First Fiji 1 reading on record: 0.25% on 25 July 2025
In Progress at 1.74% (Fiji 1)
  • Fiji 1 mobilisation works, ongoing at the 1 May 2026 visit
  • An infrastructure contractor, recorded as appointed
  • Enabling works, progressing at different stages
  • Infrastructure works, progressing at different stages
Ahead of Handover
  • Concrete structure and block walls for the 398 Fiji 1 homes, as the report describes them
  • Internal and external finishing of the G+2 and G+1 types
  • More RERA inspection readings on the way to 100%
  • Fiji 1 registered completion date 31 December 2028; expected handover Q4 2028
Next inspectionNo date was published in the register; each further Fiji 1 reading appears on Dubai REST after a RERA site visit, and one newer than 1 May 2026 may now be listed there.
Completion targetThe DLD record for Fiji 1 lists a registered completion date of 31 December 2028, in line with the expected Q4 2028 handover; each phase's contractual completion date is the one in its SPA.
Remaining distance98.26 percentage points separated the 1 May 2026 Fiji 1 reading from 100%. Arithmetic, not a forecast: measured between the two register readings, Fiji 1 moved about 0.16 points per 30-day month (1.49 points in 280 days), and about 0.14 averaged across the 375 days from its registered start; to reach 100% by the registered completion date, Fiji 1 would need about 3.02 points per 30-day month across the 975 days after the reading. The registered date is the developer's filing for Fiji 1, not a promise, and no figure here forecasts the handover.

Time-Linked Instalments

What 1.74% Progress at Fiji 1 Means for Fiji Buyers

DAMAC's DAMAC Islands payment plan dates its instalments by months from sale, not by construction milestones, so the 1.74% Fiji 1 reading neither called a payment due nor moved one: it showed where the build stood while the schedule ran. At this enabling stage of the Fiji cluster, four actions matter most.

Before Any Instalment

Verify the escrow account

Each Fiji phase is its own DLD project, and each holds a separate escrow account. For Fiji 1 (Damac Islands - Fiji 1, project 3505) the trust account bank is Emirates NBD; a buyer in Fiji 2 takes the account from their own SPA or Oqood and verifies it on Dubai REST, never this one. Fiji at DAMAC Islands escrow account verification walks through the check, and the lookup itself takes about two minutes against the official DLD project record.

Before the Next Due Date

Reread your SPA instalment schedule

DAMAC's DAMAC Islands payment plan (launch sheet, November 2024) sets 20% plus the 4% DLD registration fee on booking, 55% in 39 instalments after booking and 25% on completion; compare the date your SPA gives each instalment, and the way it defines completion, with the Q4 2028 handover. Not sure how your installments map to this reading? Send me your SPA schedule and I will map it against the recorded milestones.

After Booking

Confirm your Oqood registration

Oqood is the DLD's interim register entry for an off-plan home, standing in until a title deed can be issued at completion. Check that yours names your Fiji phase, townhouse and price exactly as the SPA does; the 4% DLD registration fee paid at booking goes to the DLD rather than into escrow.

Every Cycle

Follow each new reading

The two Fiji 1 readings on record, 25 July 2025 and 1 May 2026, sit about nine months apart, and a newer one may have been filed since. The Fiji at DAMAC Islands construction updates hub adds each reading as it is supplied, and the Fiji 2 record once it is available.

General framework, not legal advice: instalment dates, notice periods, and fee obligations are set by your individual SPA and the DLD record, and both should be read directly. This is the plan DAMAC issued at the DAMAC Islands launch in November 2024; confirm the current schedule for your Fiji phase with DAMAC and in the SPA.

Buying at Fiji 1's 1.74% Stage?

An entry at the enabling stage swaps certainty for runway: the schedule stretches over the build years, the price is locked well ahead of handover, and the inspection record runs to only two readings. Every instalment goes to the DLD-registered escrow account of your phase (project 3505 for Fiji 1), released against construction progress.

Entering at Fiji 1's 1.74% Reading
  • Two dated Fiji 1 register readings: 0.25% and 1.74%
  • Expected handover for the cluster in Q4 2028
  • 55% over 39 instalments after booking, 25% on completion (launch sheet)
Typical Near-Handover Entry
  • Construction risk largely settled before you sign
  • Keys within months rather than years, with little runway
  • More of the price falling due close to handover
AED 2.251M ≈ USD 613KStarting Price
75/25 Plan25% Due on Completion
Q4 2028Expected Handover
Ask What Is Available at Fiji at DAMAC Islands

Limited units available at the time of writing; no unit count is given, and availability shifts between cycles.

About the Development

Fiji at DAMAC Islands Project Details

Fiji at DAMAC Islands by DAMAC Properties in DAMAC Islands project rendering of modern villas with illuminated windows, landscaped gardens and residents at dusk in Dubai - Presented by Tohid Fetrat
DAMAC Islands · DAMAC Properties

Fiji at DAMAC Islands is a cluster of 798 townhouses registered with the DLD in two phases, the first of which, Fiji 1, was at the enabling works stage in May 2026. The 4 bedroom townhouse of 2,208 sq ft opens the range at AED 2.251M ≈ USD 613K.

The 5 bedroom townhouse of 3,178 sq ft starts from AED 3.07M ≈ USD 836K, so both types sit above the AED 2M ≈ USD 545K Golden Visa threshold at the listed prices. Entering this early means the longest wait to the expected Q4 2028 handover and the full instalment runway; the image is a DAMAC rendering.

Fiji at DAMAC Islands Project Guide

Site Context This Cycle

Explore Fiji at DAMAC Islands Location on Dubai Map

DAMAC's cluster map draws Fiji as two phases, and the reading on this page belongs to the first of them, Fiji 1. Because Fiji 1 is a low-rise phase of G+1 and G+2 homes spread over many plots rather than a single building, its early works are distributed across a wide site, which is why the 1 May 2026 report for Fiji 1 found enabling and infrastructure works progressing at different stages rather than on one front.

DAMAC's community figures put the Expo 2020 Venue about 20 minutes from DAMAC Islands, Al Maktoum International Airport about 23 and Dubai International Airport about 28, timings for the masterplan as a whole rather than measured from a Fiji plot. Its lagoons, waterfalls and amenity zones were planned rather than built when Fiji 1 was inspected, so anyone planning to live in or let a Fiji townhouse from Q4 2028 is committing to a district that is still taking shape. See the cluster's position on the interactive Dubai real estate map. See the project’s position on the interactive Dubai real estate map.

Interactive Dubai real estate map preview
Click to view Fiji at DAMAC Islands on Dubai Map

Buyer Resources for This Project

Investing in Fiji at DAMAC Islands in the Early Build Stage

Early in the build, the useful work for a buyer is paperwork rather than site watching: escrow, Oqood and residency eligibility. Each resource below is matched to where the Fiji cluster stood when Fiji 1 was inspected in May 2026.

Fiji at DAMAC Islands by DAMAC Properties in DAMAC Islands construction updates cover image featuring a project rendering of modern villas with garages, palm trees and a branded construction updates logo in Dubai - Presented by Tohid Fetrat
You Are Here

Fiji at DAMAC Islands Construction Updates

This page: the 1 May 2026 Fiji 1 record, 1.74% with enabling and infrastructure works progressing.

Fiji at DAMAC Islands by DAMAC Properties in DAMAC Islands Golden Visa concept graphic with a gold visa card over a landscaped lagoon with cascading waterfalls and palm trees in Dubai - Presented by Tohid Fetrat

Fiji Golden Visa: Both Townhouse Layouts Start Above the Threshold

Both townhouse layouts at Fiji at DAMAC Islands by DAMAC Properties reach the AED 2M Golden Visa threshold on their own.

Read the Fiji at DAMAC Islands Golden Visa Guide
Fiji at DAMAC Islands by DAMAC Properties in DAMAC Islands escrow account concept graphic featuring a shield and padlock over villas beside a turquoise lagoon in Dubai - Presented by Tohid Fetrat

Fiji 1 Escrow Account at Emirates NBD, Separate From Fiji 2

Fiji 1, DLD project 3505, escrows 398 registered units at Emirates NBD and read 1.74% in May 2026.

Verify the Fiji at DAMAC Islands Escrow Account

Update Timeline

Other Fiji at DAMAC Islands Construction Updates

No earlier monthly page exists for Fiji: May 2026 opens the series, and the hub gathers each further reading as it is supplied, beginning with Fiji 1.

All Fiji at DAMAC Islands Construction Updates

FAQs

Fiji at DAMAC Islands Construction Progress in May 2026: Frequently Asked Questions

The DLD register reading for Fiji 1 (project 3505), the first of the cluster's two registered phases, was 1.74% at the inspection recorded on 1 May 2026, up 1.49 points from 0.25% on 25 July 2025. The RERA progress report for that Fiji 1 visit gives its Progress Status as Enabling Works - Progressing without stating a percentage, which makes both numbers Fiji 1 register readings. Fiji 2 has a separate DLD record that this reading does not cover.

Yes. The 31 December 2028 date in the DLD record for Fiji 1 is the developer's registered filing, and the register allows that filing to be amended between inspections. When Fiji 1 was read on 1 May 2026, the date sat inside the cluster's expected Q4 2028 handover quarter; what binds a buyer is the completion date in their own SPA, and an amended Fiji 1 date would surface in a following monthly update.

The Independent Progress Monitoring Report for the 1 May 2026 Fiji 1 inspection recorded mobilisation works as ongoing, an infrastructure contractor as appointed, and enabling and infrastructure works as progressing at different stages. The same report describes Fiji 1 as 398 G+2 and G+1 townhouses and villas (ground plus two floors and ground plus one floor), designed with a concrete structure and blockwork and with internal and external finishes, which sets out the building work still to come in that phase.

Enabling works are the preparatory packages that generally come before the homes themselves rise: mobilising the contractor and site facilities, preparing ground and access, and routing the roads and services the following works rely on. A status of Enabling Works - Progressing, as recorded for Fiji 1 at 1.74% on 1 May 2026, means that preparatory stage was under way rather than finished, and the report's notes for Fiji 1 covered mobilisation, the infrastructure contractor and enabling and infrastructure works only.

Fiji 1 rose from 0.25% on 25 July 2025 to 1.74% on 1 May 2026, a gain of 1.49 points over 280 days, or about 0.16 points per 30-day month. That figure comes from the two Fiji 1 register readings alone and is not a forecast; one interval at the enabling stage says little about the pace of the building works that follow. The full Fiji 1 timeline is kept on the Fiji at DAMAC Islands construction updates hub.

Because the DLD treats each Fiji phase as its own project. Fiji 1 (project 3505) and Fiji 2 each carry a separate register entry, escrow account and inspection history, and the May 2026 figures on this page come from the Fiji 1 entry alone. They say nothing about the progress, dates or account of Fiji 2; a Fiji 2 buyer reads that phase's record on Dubai REST and takes the escrow details from their own SPA. Between them, the two phases hold the 798 homes of the Fiji cluster.

A Question the FAQ Can Not Answer?

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is helping you read the May 2026 inspection record for Fiji at DAMAC Islands correctly before your next payment decision. Client identities and transactions are never published or referenced. Message me directly: you will always reach me personally, never a call center or sales team.

Ask your question, get your answer. No obligation and no follow-up unless you ask for it.

Get Progress Alerts