Golf Gate at DAMAC Hills Construction Updates
The Closed Inspection Record of a Finished DAMAC Hills Tower
Golf Gate reached 100% construction at its 12 February 2025 RERA inspection, closing the DAMAC Hills tower's build record with its completion certificate already issued.
Construction tracking against RERA inspection data, updated after every recorded inspection.
Direct advisor access. Every message answered personally, never by a call center.
Construction Snapshot
Golf Gate at DAMAC Hills at a Glance
Golf Gate is DAMAC's 351-apartment tower on plot 2128 in Al Hebiah Third, and its Dubai Land Department construction file is now closed: the inspection of 12 February 2025 recorded 100% against a build that started on 03 May 2022. A little over thirty-three months separate those two dates, and the Building Completion Certificate was issued on 23 September 2024, ahead of the 15 December 2024 completion date carried on the register rather than behind it. Because Golf Gate is one of a small group of apartment addresses inside a 42 million square foot community of villas and townhouses, this record doubles as the delivery history for one of the few ways to buy an apartment in DAMAC Hills.
2358
Finished
03 May 2022
351 residential units
78,793.05 sq m
15 December 2024 (DLD)
Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.
Inspection Record
Golf Gate at DAMAC Hills Construction Update Timeline
This record is short because Golf Gate was already near the finish when it entered tracking here: the file carries a previous recorded reading of 90.28% and then the closing inspection of 12 February 2025 at 100%, a final gain of 9.72 points. The Dubai Land Department app publishes that earlier figure without a date of its own, so the track below positions it by percentage rather than by month, and the February 2025 row links the full inspection report with the thirteen photographs filed against it.
| Inspection Month | Construction Progress | Inspection Date | Full Update |
|---|---|---|---|
| February 2025 | 100% | 12 February 2025 | View the February 2025 update |
Reading the dates: project 2358 carries 15 December 2024 as its registered completion date, while the closing inspection was recorded on 12 February 2025 at 100%. The two do not contradict each other. The Building Completion Certificate for the tower was issued by the Dubai Development Authority on 23 September 2024, so the building was finished before the registered date and the February report simply confirmed it in the DLD file.
Pace Analysis
How Fast Golf Gate at DAMAC Hills Has Been Built
Two readings make a short record, so it is worth being precise about what the Golf Gate file can and cannot tell you about pace:
- May 2022 to Feb 2025: whole build, site start to 100%About 3.0 points per month
- 03 May 2022 to 23 September 2024: start to Building Completion CertificateAbout 29 months to certification
- Previous recorded reading to closing inspection, 90.28% to 100%Final 9.72 points
Averaged across the whole programme, 100 points over roughly thirty-three months works out near three points per month, which is an unremarkable rate for a single G plus two podium levels plus twenty-seven floors and a roof: neither a rushed tower nor a stalled one. What the record shows precisely is the shape of the ending rather than the middle. The certificate is dated 23 September 2024 and the closing inspection 12 February 2025, which means the last 9.72 points were not construction in any visible sense but finishes, water and electricity connections, and sign-off. For an investor weighing DAMAC Hills apartment stock that detail carries further than the average, because a tower that cleared its completion certificate ahead of its registered date leaves a buyer with unit-level risk only and no delivery risk at all. For an end user the same figures read more plainly: the building is standing, connected and inspected, and the one item the February report left open was snagging.
Get the Next Inspection Figure First
Tell me you are tracking Golf Gate at DAMAC Hills and I will send you the next recorded figure and site photos directly, ahead of the page update.
Get the Next Update on WhatsAppProject Profile
About Golf Gate at DAMAC Hills
A closed construction file is only half an answer; the other half is what was actually built. The project guide covers the tower behind the 100% reading:

Golf Gate Project Guide
Layouts across 351 one and two bedroom apartments, the leisure podium with its two pools and golf course gym, the position inside the DAMAC Hills masterplan, and entry pricing from AED 900K ≈ USD 245K.
View the Golf Gate at DAMAC Hills Project GuideConsidering a Completed Golf Gate Apartment?
Availability at Golf Gate is limited and moves between viewings now that the tower is complete and units are changing hands individually. If the record on this page is what brought you here, ask what is actually open before the shortlist narrows further.
Ask About Remaining Availability on WhatsAppStage Record
Golf Gate at DAMAC Hills Build Stages, Mapped to the Inspections
Rather than a generic construction sequence, each stage below is anchored to the window it actually occupied in the Golf Gate file, so you can see when the tower passed through it and what the register recorded at each point.
Registration and Site Start
Project 2358 was registered with the Dubai Land Department on 11 February 2022, and construction on plot 2128 in Al Hebiah Third started on 03 May 2022.
Concrete Structure and Block Work
The registered description sets the scope: a G plus two podium levels plus twenty-seven floors plus roof residential tower in concrete structure and block.
Internal and External Finishes
The longest stretch of the file, carrying the tower to the previous recorded reading of 90.28% with internal and external finishes applied to the structure.
Certification and Utility Connection
The Building Completion Certificate arrived from the Dubai Development Authority on 23 September 2024, water and electricity meters were connected, and 15 December 2024 passed as the registered completion date.
Snagging, Rectification, and Handover
The 12 February 2025 report closed construction at 100% and recorded one open item, snagging works ongoing, which is the phase each apartment passes through before acceptance.
What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Golf Gate at DAMAC Hills's own record.
Buyer Position
Tracking Your Position at Golf Gate at DAMAC Hills
This page is one of four project resources that together cover a Golf Gate at DAMAC Hills purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Golf Gate at DAMAC Hills Construction Updates
This page: the closed Dubai Land Department inspection record for Golf Gate, start to 100%.

Golf Gate at DAMAC Hills Golden Visa
See how Golf Gate entry pricing measures against the Golden Visa property investment threshold in Dubai.
Read the Golf Gate at DAMAC Hills Golden Visa Guide
Golf Gate at DAMAC Hills Escrow Account
Verify the project 2358 trust account at Abu Dhabi Commercial Bank before any Golf Gate payment.
Verify the Golf Gate at DAMAC Hills Escrow Account
Golf Gate at DAMAC Hills Snagging Inspection
With snagging recorded ongoing at the 100% reading, document defects before you accept your keys.
Book Golf Gate at DAMAC Hills SnaggingApproaching Handover
Between 100% and Handover: What Golf Gate at DAMAC Hills Buyers Should Do Now
At 100% recorded progress the construction question is settled, and everything left sits between the handover notice and your signature on the acceptance form. Handover appointments generally allow a short window to be completed, so the three steps below belong in the diary now rather than on the day the notice lands.
First, arrange independent snagging while the defect rectification period is still open; the Golf Gate snagging inspection guide sets out what gets documented and when it has to happen.
Second, confirm that any remaining balance goes to the registered trust account and nowhere else; the Golf Gate escrow account page names the bank holding project 2358 and how releases against certified progress worked.
Third, if residency is part of the plan, settle eligibility before the title deed is issued through the Golf Gate Golden Visa guide, which sets the AED 2M ≈ USD 545K property route against this tower's entry pricing.
Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.
The Wider Picture
Explore DAMAC Hills Structure
A construction file closes; the community around it does not. These three pages put the Golf Gate record into the context that sets its resale and rental value:

DAMAC Hills Properties for Sale
Browse villas and townhouses for sale across DAMAC Hills, including golf-course residences and branded collections.
See DAMAC Hills Properties for Sale
DAMAC Hills Community Overview
Read the DAMAC Hills guide: a golf-centred community of villas, townhouses and apartments, with property types and prices explained.
Explore the DAMAC Hills Community
DAMAC Developer Profile
Explore DAMAC Properties - large-scale master communities and branded luxury towers across Dubai and beyond.
View the DAMAC Developer ProfileConstruction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.
FAQs
Golf Gate at DAMAC Hills Construction Updates Frequently Asked Questions
Golf Gate is recorded as Finished in the Dubai Land Department register for project 2358, at 100% construction progress as of the RERA inspection of 12 February 2025. That report is the closing entry in the construction file, and the full record sits in the inspection timeline above.
The inspection of 12 February 2025 recorded 100% construction progress, a gain of 9.72 points on the previous recorded reading of 90.28%. The inspector noted all construction activities complete, water and electricity meters connected, and snagging works ongoing. The report and its thirteen photographs are covered in the Golf Gate February 2025 construction update.
The Dubai Land Department register carries 15 December 2024 as the completion date for project 2358. The Building Completion Certificate was issued earlier, on 23 September 2024 by the Dubai Development Authority, and the inspection of 12 February 2025 confirmed 100% in the file. In practice the tower was finished ahead of its registered date, and apartment handovers follow individually rather than on a single project-wide date.
Dubai Land Department records show 351 residential units in project 2358, delivered as one and two bedroom apartments in a G plus two podium levels plus twenty-seven floors plus roof tower. Layouts and sizes, from roughly 626 sq ft for a one bedroom, are set out in the Golf Gate project guide.
Construction started on 03 May 2022 and the closing inspection was recorded on 12 February 2025, a little over thirty-three months, which averages near three percentage points of recorded progress per month. The Building Completion Certificate came at about twenty-nine months, on 23 September 2024, so the final stretch was finishing and connection work rather than building. The computed breakdown is in the pace analysis above.
Golf Gate occupies plot 2128 in Al Hebiah Third, inside the DAMAC Hills master community, which spans 42 million square feet and is built largely as villas and townhouses around a golf course. The tower is therefore one of a small number of apartment addresses in the community, and it completed into an established neighbourhood rather than an active construction site.

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is keeping the Golf Gate at DAMAC Hills construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.
Ask your question, get your answer. No obligation and no follow-up unless you ask for it.