Greenspoint by Emaar in Emaar South project rendering used for the July 2026 construction update showing the planned children’s playground with climbing structures shaded play areas and surrounding homes in Dubai - Presented by Tohid Fetrat

Emaar · Emaar South · Construction Update

Greenspoint Construction Update - July 2026

July 2026 Inspection Confirms Greenspoint Reaches 42.9% Construction Progress in Emaar South

Substructure and superstructure works are at an advanced stage across the Greenspoint townhouse clusters, with envelope, MEP, and finishes underway, verified at 42.9 percent in July 2026.

Direct advisor access. Every message answered personally, never by a call center.

42.9%Construction Progress
21 July 2026Inspection Date
Q1 2029Expected Completion
3514DLD Project Number

Verified DLD Inspection Data

Greenspoint Construction Snapshot

A 16.63 point rise since the previous recorded reading places Greenspoint in the superstructure band, the stage where construction linked installments start falling due against certified percentages rather than calendar dates.

Project Name

Greenspoint by Emaar

Project Number

3514

Project Status

Active

Construction Progress

42.9%

Inspection Date

21 July 2026

Construction Start

30 January 2025

Total Units

196 townhouses

Total Built Area

46,600.81 sq m

Expected Completion

Q1 2029

Data source: RERA inspection conducted on 21 July 2026, tracked against DLD inspection records. Construction tracking against RERA inspection data runs across the full tohidfetrat.com project portfolio and is reviewed after every published cycle. Last updated: August 2026.

Want each new reading the day it publishes? Message me on WhatsApp and I will send it to you directly: one message per inspection cycle, nothing else. Message me on WhatsApp

This Inspection Cycle

Greenspoint Construction Progress Summary

Greenspoint stood at 26.27% at its previous recorded reading and reaches 42.9% on 21 July 2026, a gain of 16.63 points. The register carries no date against that earlier figure, so the gain cannot be attributed to a fixed number of months and no rate of progress is claimed here. What the July inspection does confirm is a site that has left the ground works phase: enabling and foundation packages are substantially complete and the townhouse blocks are rising.

Completed
  • Enabling and foundation works substantially completed across plot 7049
  • Project 3514 registered on 28 January 2025, construction started two days later
  • Main contract mobilized by Emaar Dubai South under independent RERA monitoring
In Progress at 42.9%
  • Substructure and superstructure at an advanced stage across the townhouse blocks
  • Internal and external envelope packages across the four plex rows
  • MEP and finishes works at different stages across the 196 homes
  • Community infrastructure advancing across the gated four plex cluster
Ahead of Handover
  • Remaining envelope, MEP, and finishes across all 196 townhouses toward 100%
  • Amenity delivery along the central spine: community centre, nursery, sport courts, pool
  • Building completion certificate procedures ahead of the Q1 2029 window
Next inspectionPublished in the DLD project register after the next RERA site visit; this page updates with each cycle.
Completion targetQ1 2029, roughly two and a half years beyond the 21 July 2026 inspection date.
Remaining distance57.1 percentage points separate the July 2026 reading from handover readiness.

Payment Linked Progress

What 42.9% Progress Means for Greenspoint Buyers

The published Greenspoint plan ties five of its installment triggers to certified construction completion rather than to dates alone, so a verified reading of 42.9% is not just a status line: it tells you which trigger the project has already passed and which one it is walking toward. At this stage of Greenspoint, four actions matter most.

Before Every Installment

Verify the escrow account

Every payment on a project this far from handover should go only to the DLD regulated escrow account registered for project 3514. Greenspoint escrow account verification is the step before any transfer; the lookup itself takes about two minutes against the official DLD project record.

Before the Next Milestone Trigger

Reread your SPA milestone schedule

The published plan places a 10% installment at 50% certified construction; at 42.9% that is the next trigger in sequence, and your own agreement decides how it is invoiced. Not sure how your installments map to this reading? Send me your SPA schedule and I will map it against the certified milestones.

Well Before Handover

Confirm your Oqood registration

Interim off plan registration records your Greenspoint unit against project 3514 in the DLD system years before a title deed is issued at completion. Confirm the registration exists and that the unit reference on it matches your agreement while the project is still mid construction.

Every Cycle

Track the remaining cycles

Several inspection readings still separate 42.9% from completion certification. The Greenspoint construction updates hub keeps each certified percentage next to the trigger it affects.

General framework, not legal advice: milestone definitions, notice periods, and fee obligations are set by your individual SPA and the DLD record, and both should be read directly.

Buying at 42.9%?

Entering at the midpoint trades part of the launch payment runway for a structure you can already verify: foundations are behind the project, the blocks are up, and the remaining installments are tied to percentages an independent inspector certifies rather than to promises. Every payment goes to the DLD-registered escrow account for project 3514, released against certified construction progress.

Entering Now at 42.9%
  • Certified structure: 42.9% on record, foundations and frame already behind you
  • The 30% construction trigger already sits behind the certified 42.9% reading
  • Roughly two and a half years to the Q1 2029 completion window
Typical Launch Entry
  • Construction risk carried from excavation all the way to handover
  • Four or more years of waiting is the usual delivery horizon
  • Longer installment runway, priced at launch levels
AED 3.36M ≈ USD 915KStarting Price
80/20 Plan20% Due on Completion
From Q1 2029Expected Handover

Limited units listed available on the project page as of this update; availability shifts between cycles.

About the Development

Greenspoint Project Details

Greenspoint by Emaar in Emaar South modern two-storey townhouse corner exterior with landscaped frontage residents and parked cars in Dubai - Presented by Tohid Fetrat
Emaar South · Emaar

With foundations behind it and superstructure works at an advanced stage, Greenspoint is a mid construction gated cluster of 196 townhouses, split evenly between 98 three bedroom and 98 four bedroom homes in four plex format. Starting prices: AED 3.36M ≈ USD 915K.

For buyers entering at this stage, the trade off is a shorter remaining installment runway against a structure already certified at 42.9%, with handover expected from Q1 2029.

Site Context This Cycle

Explore Greenspoint Location on Dubai Map

Greenspoint occupies plot 7049 in Madinat Al Mataar, the Emaar South district that wraps around Al Maktoum International Airport, and is laid out as gated rows of four plex townhouses folded around a central amenity spine rather than stacked into a single core. That horizontal geometry is why the July 2026 record describes envelope, MEP, and finishes works running at different stages at the same time: dozens of blocks each sit at their own point in the sequence, and the certified 42.9% is the weighted average across all of them.

Emaar South is still filling in around its championship golf course, schools, and neighbourhood retail, so Greenspoint is being built into a district maturing alongside it rather than into a finished address, which is the practical difference for buyers weighing occupancy timing and rental planning against the Q1 2029 completion window. See the project's position on the interactive Dubai real estate map. See the project’s position on the interactive Dubai real estate map.

Interactive Dubai real estate map preview

Buyer Resources for This Project

Investing in Greenspoint During Active Construction Progress

The superstructure band is where payment protection, registration, and residency planning carry the most weight. Each resource below is matched to where Greenspoint stands right now.

Greenspoint by Emaar in Emaar South construction updates cover image featuring a project rendering of a landscaped community lawn with families shaded seating and surrounding townhouses in Dubai - Presented by Tohid Fetrat
You Are Here

Greenspoint Construction Updates

This page: the verified July 2026 inspection record for Greenspoint, from enabling works through superstructure.

Greenspoint by Emaar in Emaar South Golden Visa concept graphic with a gold visa card above a landscaped community park and water feature in Dubai - Presented by Tohid Fetrat

Greenspoint by Emaar at Emaar South Golden Visa, No Combining Needed

No tier at Greenspoint by Emaar at Emaar South sits below the threshold: its 3 and 4 bedroom townhouses both qualify.

Read Greenspoint Golden Visa Guide
Greenspoint by Emaar in Emaar South escrow account protection graphic with shield and padlock icons above an outdoor swimming pool and landscaped townhouses in Dubai - Presented by Tohid Fetrat

Greenspoint by Emaar at Emaar South: First Abu Dhabi Bank Escrow

Greenspoint by Emaar at Emaar South is DLD project 3514, escrowed at First Abu Dhabi Bank, 42.9% certified July 2026.

Verify Greenspoint Escrow Account

Update Timeline

Other Greenspoint Construction Updates

Follow the full inspection history to see how Greenspoint moves through each construction phase, reading by reading.

All UpdatesGreenspoint Construction Updates Hub
Next Update · One Message Per CycleGet notified the day it publishes
All Greenspoint Construction Updates

FAQs

Greenspoint Construction Progress in July 2026: Frequently Asked Questions

As of the RERA inspection conducted on 21 July 2026, Greenspoint stands at 42.9% construction progress in the DLD project register, with the project status recorded as active.

Greenspoint moved from 26.27% at its previous recorded reading to 42.9% on 21 July 2026, a gain of 16.63 points. The register carries no date against that earlier reading, so the gain cannot be tied to a fixed number of months and no monthly rate should be inferred from it.

The 21 July 2026 inspection records enabling and foundation works substantially completed, substructure and superstructure works at an advanced stage, and internal and external envelope, MEP, and finishes packages progressing at different stages across the townhouse blocks, with community infrastructure advancing alongside them.

The published Greenspoint plan attaches a 10% installment to 50% certified construction completion. At 42.9% on 21 July 2026 the 30% trigger already sits behind the reading and the 50% trigger is the next one in sequence. What each buyer actually owes and when is governed by the individual sale and purchase agreement, not by the published schedule alone.

The DLD register records 196 units for project 3514, delivered as townhouses in gated four plex arrangements, split evenly between 98 three bedroom and 98 four bedroom homes. The total built area on record is 46,600.81 sq m.

The 21 July 2026 record shows the project active and the main contract progressing, with 57.1 percentage points still between the certified reading and full completion and roughly two and a half years to the Q1 2029 window. Expected completion timing can be revised between inspection cycles, and any revision would appear in a later reading on the Greenspoint construction updates hub.

A Question the FAQ Can Not Answer?

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is helping you read the July 2026 inspection record for Greenspoint by Emaar at Emaar South correctly before your next payment decision. Client identities and transactions are never published or referenced. Message me directly: you will always reach me personally, never a call center or sales team.

Ask your question, get your answer. No obligation and no follow-up unless you ask for it.

Get Progress Alerts