Emaar · Emaar South · Construction Update
Greenway 2 Construction Update - July 2026
July 2026 Inspection Confirms Greenway 2 Reaches 34.37% Construction Progress in Emaar South
Structure, external envelope, MEP, and internal works are all progressing across the 492 townhouses at Greenway 2, verified at 34.37 percent in the July 2026 RERA inspection.
Direct advisor access. Every message answered personally, never by a call center.
Verified DLD Inspection Data
Greenway 2 Construction Snapshot
A 10.40 point rise from the previous recorded reading puts Greenway 2 into the superstructure band, the stage where certified percentages start pulling milestone linked instalments forward on a townhouse programme of this size.
Greenway 2 by Emaar
3121
Active
34.37%
29 July 2026
23 October 2024
492 townhouses
113,658.95 sq m
Q2 2028
Data source: RERA Independent Progress Monitoring Report for inspection date 29 July 2026, tracked against DLD project register records for project 3121. Construction tracking against RERA inspection data runs across the full tohidfetrat.com project portfolio and is reviewed after every published cycle. Last updated: August 2026.
Want each new reading the day it publishes? Message me on WhatsApp and I will send it to you directly: one message per inspection cycle, nothing else. Message me on WhatsApp
This Inspection Cycle
Greenway 2 Construction Progress Summary
The 29 July 2026 report records Greenway 2 at 34.37%, against a previous inspection figure of 23.97%. The register carries that earlier reading without an inspection date, so the 10.40 point gain is exact but the interval it covers is not stated, and this page will not estimate one. What the report does confirm is that every work package on the project, from piling through internal finishes, is now running concurrently across the 492 townhouse plots.
- DLD project registration recorded 13 June 2024
- Construction commencement recorded 23 October 2024
- The 10% and 20% construction completion instalment triggers
- Enabling, piling, and foundation works on plot 6430
- Concrete structure and block work on the G+1 townhouses
- External envelope, MEP, and internal finishing packages
- External works and infrastructure inside the cluster
- The 40%, 60%, 80%, and 100% completion instalment triggers
- Remaining RERA inspection cycles from 34.37% toward 100%
- Building completion certificate procedures before handover
Payment Linked Progress
What 34.37% Progress Means for Greenway 2 Buyers
On the published Greenway 2 schedule, six of the ten instalments are tied to certified construction completion rather than to calendar dates, which makes each RERA reading a payment event as well as a status report. At 34.37%, four actions matter most.
Verify the escrow account
Each instalment ahead of you should go only to the DLD regulated escrow account registered for project 3121. Greenway 2 escrow account verification is the step before any transfer; the lookup itself takes about two minutes against the official DLD project record.
Map your instalments to the certified reading
With 5.63 points between this reading and the 40% completion milestone, the next demand is close enough to plan for rather than react to. Not sure how your instalments map to this reading? Send me your SPA schedule and I will map it against the certified milestones.
Confirm your Oqood registration
Oqood is the interim registration that records an off plan sale against project 3121 in the DLD system before title exists. Buyers entering mid construction should confirm the certificate was issued in their name rather than assume the developer completed the filing.
Track the remaining cycles
Several inspection readings separate 34.37% from completion certification, and four of them carry payment consequences. The Greenway 2 construction updates hub keeps that sequence in one place.
General framework, not legal advice: milestone definitions, notice periods, and fee obligations are set by your individual SPA and the DLD record, and both should be read directly.
Buying at 34.37%?
Entering a townhouse project a third of the way through trades launch pricing for a shorter and better documented wait: the structure is certified rather than promised, and two of the ten instalment triggers are already behind the schedule. Every payment goes to the DLD-registered escrow account for project 3121, released against certified construction progress.
- Certified structure: the July 2026 inspection record is the risk picture
- The 10% and 20% completion triggers sit behind you, not ahead
- Roughly 21 to 23 months to the Q2 2028 handover target
- Every work package still ahead, from enabling upward
- Three to four years is the usual wait on a townhouse launch
- Instalments spread thinner across a longer unverified stretch
Limited units listed available on the project page as of this update; availability shifts between cycles.
About the Development
Greenway 2 Project Details

With structure, envelope, and finishing packages all recorded as active, Greenway 2 is a superstructure stage cluster of 492 freehold G+1 townhouses, split evenly between 246 three bedroom and 246 four bedroom homes across two facade styles. Starting prices: AED 2.72M ≈ USD 741K.
Buying at this point means the concrete is verified and the wait is measured in months rather than years, against a payment schedule that front loads nothing and settles the balance in milestone steps to Q2 2028.
Site Context This Cycle
Explore Greenway 2 Location on Dubai Map
Greenway 2 occupies plot 6430 in Madinat Al Mataar, on the southern edge of the Emaar South masterplan directly below the original Greenway cluster. Because this is a horizontal G+1 programme rather than a tower, the plot works as one continuous site: piling, structure, and finishing crews operate on different 4-plex rows at the same time, which is why the July 2026 report lists nearly every package as progressing rather than showing a single dominant trade.
The surrounding infrastructure is part built rather than complete, with delivered Emaar South phases and the golf clubhouse already operating while roads and community works extend south toward this cluster, so the external and infra items inside plot 6430 are the ones that will decide how finished the address feels on day one rather than the townhouses alone. See the project's position on the interactive Dubai real estate map. See the project’s position on the interactive Dubai real estate map.

Buyer Resources for This Project
Investing in Greenway 2 During Active Construction Progress
Mid construction is where payment protection and residency planning matter more than handover preparation. Each resource below is matched to where Greenway 2 stands right now.

Greenway 2 Construction Updates
This page: the verified July 2026 inspection record for Greenway 2, from enabling works onward.

Greenway 2 at Emaar South Golden Visa: Entry Tier Clears by 36%
Greenway 2 at Emaar South, Emaar's 492-townhouse community, qualifies at both 3 and 4 bedroom tiers with no combining of properties.
Read Greenway 2 Golden Visa Guide
Greenway 2 at Emaar South: The Townhouse Escrow on the DLD Register
Greenway 2 at Emaar South is DLD project 3121: 492 units, Abu Dhabi Commercial Bank escrow, 34.37% certified in July 2026.
Verify Greenway 2 Escrow AccountUpdate Timeline
Other Greenway 2 Construction Updates
This is the first published reading in the Greenway 2 record. Each following inspection is added here so the full progression stays in one place, cycle by cycle.
Where This Update Fits
Explore Greenway 2 Structure
This monthly report is one node in the wider record: the community that surrounds the site, the developer delivering it, and the listings competing with it.

Emaar South Dubai Properties for Sale
Browse apartments, townhouses and villas for sale in Emaar South, with prices, payment plans and availability.
See Emaar South Dubai Properties for Sale
Emaar South Dubai Community Overview
Read the Emaar South guide: a golf community of apartments, townhouses and villas beside Al Maktoum International Airport.
Explore the Emaar South Dubai Community
Emaar Properties: Burj Khalifa, Downtown Dubai and Twenty Master Communities
Emaar, founded in 1997, built Burj Khalifa and Downtown Dubai and has delivered over 85,000 homes across twenty master communities.
View the Emaar Properties Developer ProfileFAQs
Greenway 2 Construction Progress in July 2026: Frequently Asked Questions
As of the RERA inspection dated 29 July 2026, Greenway 2 stands at 34.37% construction progress in the DLD project register for project 3121, with the progress status recorded as main contract progressing.
The July 2026 report shows 34.37% against a previous inspection reading of 23.97%, a gain of 10.40 points. The register publishes that earlier figure without an inspection date, so the length of the interval it covers cannot be stated from the record.
The inspection notes record enabling, piling, foundation, structure, internal works, external envelope, MEP, internal finishes, external works, and infrastructure works all progressing simultaneously. On a horizontal G+1 townhouse programme, different 4-plex rows sit at different stages at the same moment, which is why so many packages appear concurrently.
Handover is targeted for Q2 2028, which leaves 65.63 percentage points between the 29 July 2026 reading and full certification. How inspection cycles progress toward completion certification is covered on the Greenway 2 construction updates hub.
Yes. Completion targets in the DLD project register can be revised between inspection cycles, in either direction. The target shown here reflects the position as of the July 2026 reading; any revision would appear in a later update on this cluster.
On the published Greenway 2 schedule the instalment triggers sit at 10%, 20%, 40%, 60%, 80%, and 100% construction completion. The 34.37% reading of 29 July 2026 places the project past the 20% trigger and 5.63 points below the 40% trigger. Your own SPA is the document that governs which of these applies to you and when it becomes payable.
A Question the FAQ Can Not Answer?

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is helping you read the July 2026 inspection record for Greenway 2 at Emaar South correctly before your next payment decision. Client identities and transactions are never published or referenced. Message me directly: you will always reach me personally, never a call center or sales team.
Ask your question, get your answer. No obligation and no follow-up unless you ask for it.