DAMAC Properties · DAMAC Hills
Ivory at DAMAC Hills Construction Updates
A Townhouse and Villa Build Record, Logged From Its First Register Readings
Ivory at DAMAC Hills stood at 0.56% in the DLD register on 29 June 2026, a reading that places its 57-home townhouse and villa plot at mobilisation.
Construction tracking against RERA inspection data, updated after every recorded inspection.
Direct advisor access. Every message answered personally, never by a call center.
Construction Snapshot
Ivory at DAMAC Hills at a Glance
Ivory at DAMAC Hills by DAMAC is a cluster of 57 townhouses and villas, entered on the DLD project register as DAMAC Hills - Ivory, project 3706, on 03 July 2025. Its record is still short: a construction start on 01 September 2025 and one dated reading of 0.56% on 29 June 2026. What makes it unusual is the contrast of scale, a single small plot being prepared inside a master community whose golf course, parks and schools are already in use, so the anchors below describe the cluster alone, not the district around it.
3706
Active
01 September 2025
57 townhouses and villas
16,006.76 sq m
30 June 2028 (DLD)
Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.
Inspection Record
Ivory at DAMAC Hills Construction Update Timeline
The Ivory record holds one dated reading so far: 0.56% in the DLD register on 29 June 2026, 301 days after the 01 September 2025 construction start. The register also lists a previous inspection at 0.17% but gives it no date, so that figure appears on the track below as an unlabelled dot and has no row in the table. The single row links the June 2026 update, where the reading and the RERA site notes are set out in full.
| Inspection Month | Construction Progress | Inspection Date | Full Update |
|---|---|---|---|
| June 2026 | 0.56% | 29 June 2026 | View the June 2026 update |
Pace Analysis
How Fast Ivory at DAMAC Hills Has Been Built
With a single dated reading, Ivory's record cannot yet show a measured pace between two inspections. What the register dates do allow is plain arithmetic, not a forecast, on a 30-day month:
- Sep 2025 to Jun 2026: mobilisation and enabling, 0.56% over 301 days to 29 June 2026 (arithmetic, not a forecast)About 0.06 points per month
- Jun 2026 to Jun 2028: remaining 99.44 points over 732 days to the 30 June 2028 registered completion date (arithmetic, not a forecast)About 4.08 points per month
Neither figure grades the work. The 0.06 average spreads 0.56 points across the ten months from the September 2025 start to the 29 June 2026 inspection, and the RERA report for that date records Ivory at pre-construction status, so the average reflects mobilisation and enabling works only, before any of the 57 homes is on the record. The 4.08 figure is simply the even rate that would carry the register from 0.56% to 100% across the 732 days to 30 June 2028, a date that sits inside the Q2 2028 handover quarter. The undated 0.17% previous reading adds a 0.39-point difference but no rate, because the register gives it no date. The first measured pace for Ivory arrives with the next dated reading: for an end user it is the number that shows the townhouses and villas moving off the drawings, and for an investor it is the first evidence of the build's own rhythm across the construction years still ahead.
Get the Next Inspection Figure First
Tell me you are tracking Ivory at DAMAC Hills and I will send you the next recorded figure and site photos directly, ahead of the page update.
Get the Next Update on WhatsAppProject Profile
About Ivory at DAMAC Hills
A register percentage only matters against what is being delivered. The full project guide covers the homes this record is tracking toward:

Ivory at DAMAC Hills: A 57-Home Townhouse and Villa Cluster
Ivory at DAMAC Hills is a DAMAC cluster of 57 homes, three and five bedroom townhouses alongside four bedroom villas.
View the Ivory at DAMAC Hills Project GuideConsidering an Early-Stage Entry?
Limited units are available at Ivory, and what remains shifts as DAMAC moves through releases during the build. If the record on this page is what brought you here, ask me for current availability while the cluster is still at its earliest stage.
Ask About Remaining Availability on WhatsAppStage Record
Ivory at DAMAC Hills Build Stages, Mapped to the Inspections
Each stage below is tied to the window it occupies in Ivory's own record, from the July 2025 registration to the Q2 2028 handover, so it is clear which stages the 29 June 2026 reading has reached and which are still ahead of it.
Registration and Construction Start
Project 3706 entered the DLD register on 03 July 2025, and the register records 01 September 2025 as the construction start, 60 days later.
Mobilisation and Enabling Works
The RERA report of 29 June 2026 finds the site still being mobilised and places enabling and infrastructure works at a very early stage, as the register reached 0.56%.
Concrete and Block Construction
Not yet on the record: the RERA report describes the 57 homes as G+2 townhouses and G+1 villas built in concrete and block.
Internal and External Finishes
Also ahead: the internal and external finishes the RERA report lists for every unit, with private gardens and the townhouse roof terraces.
Completion and Handover
The registered completion date of 30 June 2028 falls inside the expected Q2 2028 handover, when the final 25% of the 20/55/25 plan is due.
What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Ivory at DAMAC Hills's own record.
Buyer Position
Tracking Your Position at Ivory at DAMAC Hills
This page is one of four project resources that together cover a Ivory at DAMAC Hills purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Ivory at DAMAC Hills Construction Updates
This page: the DLD register record for Ivory, followed from mobilisation through to Q2 2028 handover.

Ivory at DAMAC Hills Golden Visa: 57 Townhouses and Villas
Ivory at DAMAC Hills, 57 DAMAC Properties townhouses and villas, clears the threshold at every type from the 3 bedroom townhouse.
Read the Ivory at DAMAC Hills Golden Visa Guide
Ivory at DAMAC Hills Escrow Account
Match every Ivory payment to the ADCB trust account that DLD records hold for project 3706.
Verify the Ivory at DAMAC Hills Escrow AccountApproaching Handover
Between 0.56% and Handover: What Ivory at DAMAC Hills Buyers Should Do Now
At the mobilisation and enabling stage recorded on 29 June 2026, almost the whole 20/55/25 plan is still to be paid, with 55% spread across eight instalments during construction and 25% left for handover in Q2 2028. Those instalments fall during the build years, so the three checks below are worth making before the first of them, not after.
First, confirm that each payment goes to the trust account registered for project 3706; the Ivory at DAMAC Hills escrow account page shows how to check it against the DLD record before any transfer.
Second, if residency is part of the plan, read the Ivory at DAMAC Hills Golden Visa guide early, since all three home types sit at or above the property value threshold on price and the guide explains what an off-plan application at Ivory involves.
Third, keep the homes themselves in view: the Ivory at DAMAC Hills project guide sets out the three layouts, prices from AED 2.789M ≈ USD 759K and the Q2 2028 handover that this record is tracking toward.
Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.
The Wider Picture
Explore DAMAC Hills Structure
A build record is only half the picture; the other half is the finished community it is being built into. These three pages put Ivory's early record in its market, community, and developer context:

DAMAC Hills Properties for Sale
Browse villas and townhouses for sale across DAMAC Hills, including golf-course residences and branded collections.
See DAMAC Hills Properties for Sale
DAMAC Hills: Villas, Townhouses and Apartments Around Trump International Golf Club
DAMAC Hills is a Dubailand community wrapping villas, townhouses and apartments around a championship golf course, with an active resale market.
Explore the DAMAC Hills Community
DAMAC Properties: Lagoon Communities, Golf Villas and Branded Collaborations
Founded in 2002, DAMAC has delivered 48,000 homes and is known for large-scale master communities, luxury residential projects and branded collaborations.
View the DAMAC Developer ProfileConstruction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.
FAQs
Ivory at DAMAC Hills Construction Updates Frequently Asked Questions
Ivory at DAMAC Hills by DAMAC is an active project on the DLD project register, number 3706, recorded at 0.56% on 29 June 2026, and the RERA inspection report for that date gives its progress status as Pre-Construction, Progressing. The work on record is limited to mobilising the site and the first, very early enabling and infrastructure works; the reading sits in the inspection timeline above.
The Ivory timeline holds one dated reading so far: 0.56% in the DLD register on 29 June 2026, which is 0.39 points above the previous inspection figure of 0.17% that the register shows without a date. Only the June 2026 reading is dated, so it forms the single row of the table while the earlier figure appears on the track as an undated dot; the dated reading is documented in the Ivory June 2026 inspection record.
Ivory's progress is tracked from two official records for project 3706: the percentage posted to the Dubai Land Department project register after each RERA site inspection, 0.56% as of 29 June 2026, and the RERA inspection report, which gives a progress status and site notes rather than a figure. Each new reading adds a monthly update and a new timeline row, and the general method is explained on the Dubai Construction Updates hub.
The 0.56% figure for Ivory comes from the DLD project register for project 3706, shown in the Dubai REST app against the inspection of 29 June 2026. The RERA inspection report for the same date prints no construction percentage: it records the progress status Pre-Construction, Progressing, with notes on mobilisation and on enabling and infrastructure works, which is why this page labels the figure a DLD register reading.
The DLD register records 30 June 2028 as the registered completion date for Ivory at DAMAC Hills, project 3706, and that date falls inside Q2 2028, the expected handover quarter. As of the 0.56% reading of 29 June 2026 the registered date was still about two years away, so the two dates agree; actual handover is confirmed by DAMAC as the build completes, and this page's record is updated as each new reading is posted.
With one dated reading, Ivory's pace can only be expressed as arithmetic, not a forecast: 0.56% across the 301 days from the 01 September 2025 start to the 29 June 2026 inspection averages about 0.06 points per month, a period the RERA report places at pre-construction status. Reaching 100% by the 30 June 2028 registered completion date would take about 4.08 points per month over the remaining 732 days; the working is in the pace analysis above.

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is keeping the Ivory at DAMAC Hills construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.
Ask your question, get your answer. No obligation and no follow-up unless you ask for it.