DAMAC Properties · DAMAC Riverside · Construction Update
Ivy at DAMAC Riverside Construction Update - August 2026
26 August 2026 Inspection Records Ivy at 38.13% Construction Progress in the DLD Register
Superstructure works were progressing at advanced stages across Ivy's 594 townhouses, with internal works and MEP underway, when RERA inspected the site on 26 August 2026.
Direct advisor access. Every message answered personally, never by a call center.
DLD Register Reading
Ivy at DAMAC Riverside Construction Snapshot
A rise of 16.69 points on the previous inspection reading of 21.44% puts Ivy at 38.13% in the DLD register, inside the superstructure band: the stretch of the build that the 55% construction-stage portion of Ivy's payment plan spans.
Ivy at DAMAC Riverside
3170
Active
38.13%
26 August 2026
24 September 2024
594 townhouses
2,948.55 sq m
31 December 2027
Data source: the DLD project register for project 3170, listed as Damac Riverside - Ivy and registered on 22 July 2024, and the RERA inspection report of 26 August 2026. The RERA report prints no percentage, so 38.13% is the DLD register reading recorded on 26 August 2026; a newer inspection may since have been added to the register. The hero image is a developer rendering of the planned townhouses, not a site photograph. Construction tracking against RERA inspection data runs across the full tohidfetrat.com project portfolio and is reviewed after every published cycle. Last updated: August 2026.
Want each new reading the day it publishes? Message me on WhatsApp and I will send it to you directly: one message per inspection cycle, nothing else. Message me on WhatsApp
This Inspection Cycle
Ivy at DAMAC Riverside Construction Progress Summary
The DLD register moved Ivy from a previous inspection reading of 21.44%, which it lists without a date, to 38.13% at the RERA visit of 26 August 2026. On that visit the RERA report recorded foundation, substructure and superstructure at advanced stages across the 594 G+1+R townhouses, while the external envelope and finishes had only reached early stages.
- DLD project registration on 22 July 2024
- Construction start on 24 September 2024
- Enabling works, recorded as substantially completed
- Foundation, substructure and superstructure at advanced stages
- Internal works, infrastructure and MEP at different stages
- External envelope and finishes at early stages
- Site mobilisation still ongoing at the inspection
- Remaining RERA inspection cycles toward 100% in the register
- Envelope, finishes and infrastructure across the 594 townhouses
- Handover in Q4 2027, registered completion 31 December 2027
Payment Linked Progress
What 38.13% Progress Means for Ivy Buyers
Ivy's plan splits the price 20/55/25: 20% on booking, 55% during construction as scheduled in the SPA, and 25% on handover. A register reading of 38.13% sits inside that middle stretch, so it is the point to check where your money goes, what your SPA ties each instalment to, and whether your unit is registered. At this stage of Ivy, four actions matter most.
Verify the escrow account
Payments toward the price should go only to the DLD regulated escrow account registered for project 3170 with First Abu Dhabi Bank. Ivy at DAMAC Riverside escrow account verification sets out the check; the lookup itself takes about two minutes against the official DLD project record.
Reread your SPA payment schedule
Check whether your sale and purchase agreement ties each part of the 55% construction-stage portion to calendar dates or to progress stages, and how it defines the 25% due on handover in Q4 2027. Not sure how your instalments line up with this reading? Send me your SPA schedule and I will map it against the recorded inspection readings.
Confirm your Oqood registration
An off plan Ivy townhouse is recorded on Oqood, the DLD interim register, until handover allows a title deed to be issued. Confirming that your unit appears there under project 3170 matters most while the construction-stage payments are still building up.
Track the remaining cycles
61.87 points remain between this reading and 100% in the register, with the envelope and finishes still ahead. Ivy at DAMAC Riverside construction updates record each new reading as it is published.
General framework, not legal advice: instalment triggers, notice periods, and fee obligations are set by your individual SPA and the DLD record, and both should be read directly.
Buying at 38.13%?
Entering Ivy mid-construction trades launch-stage runway for a clearer picture: the frame was at advanced stages at the 26 August 2026 inspection, the envelope and finishes are still ahead, and the remaining choice is between the townhouses still released. Every payment toward the price goes to the DLD-registered escrow account for project 3170, released against construction progress recorded in RERA inspections.
- Recorded progress: the 26 August 2026 register reading above is the risk picture
- Handover scheduled for Q4 2027
- 20% on booking and 25% on handover, with 55% as scheduled in your SPA
- Construction risk carried from enabling works to handover
- Two to four years of waiting is the usual delivery horizon
- Longer instalment runway, priced at launch levels
Limited Units Available on the project page as of this update; availability shifts between cycles.
About the Development
Ivy at DAMAC Riverside Project Details

With its superstructure at advanced stages in the 26 August 2026 RERA report, Ivy is a mid-construction cluster of 594 townhouses in 4 and 5 bedroom formats within DAMAC Riverside. Starting prices: AED 2.55M ≈ USD 694K.
For buyers entering at this stage, the trade off is a defined townhouse at the current release price against an envelope and finishes still at early stages, with handover scheduled for Q4 2027.
Ivy at DAMAC Riverside Project GuideSite Context This Cycle
Explore Ivy at DAMAC Riverside Location on Dubai Map
Ivy is one townhouse cluster within DAMAC Riverside in Dubai Investment Park 2, built as rows of low-rise G+1+R homes rather than a single tower, so work advances across many homes at once: the RERA report of 26 August 2026 records internal works, infrastructure and MEP progressing at different stages across the cluster.
DAMAC describes the community as having easy access to key roads and major highways, and its brochure places DAMAC Riverside about 12 minutes from Al Maktoum International Airport, an approximate community-level figure. The lagoon, parks and shared amenities are presented as planned facilities of the masterplan, so buyers weighing a Q4 2027 move-in or rental plan should check which of them are scheduled to open alongside Ivy's handover. See the cluster's position on the interactive Dubai real estate map. See the project’s position on the interactive Dubai real estate map.

Buyer Resources for This Project
Investing in Ivy at DAMAC Riverside During Active Construction
The superstructure band is where payment protection and residency planning carry the most weight for Ivy buyers. Each resource below is matched to where Ivy stood at the 26 August 2026 inspection.

Ivy at DAMAC Riverside Construction Updates
This page: the 26 August 2026 DLD register reading for Ivy, set against the RERA report.

Ivy Golden Visa: Both Townhouse Types Above the AED 2M Threshold
Ivy at DAMAC Riverside, DAMAC Properties' townhouse cluster in Dubai Investment Park 2, qualifies at both 4 and 5 bedroom types.
Read the Ivy at DAMAC Riverside Golden Visa Guide
Ivy at DAMAC Riverside Escrow: First Abu Dhabi Bank, Plot 876
Ivy at DAMAC Riverside, DLD project 3170, escrows 594 townhouses with First Abu Dhabi Bank and read 38.13% in August 2026.
Verify the Ivy at DAMAC Riverside Escrow AccountUpdate Timeline
Other Ivy at DAMAC Riverside Construction Updates
The August 2026 record is the first monthly page for Ivy in this series; later readings join the timeline on the construction updates page as each one is published.
Where This Update Fits
Explore Ivy at DAMAC Riverside Structure
This monthly record sits inside a wider picture: the DAMAC Riverside community around the site, the developer building it, and the listings that compete with it.

DAMAC Riverside Properties for Sale
Explore DAMAC Riverside properties for sale, featuring modern apartments, spacious townhouses, luxury villas, flexible payment plans and amenities.
See DAMAC Riverside Properties for Sale
DAMAC Riverside Community Overview
Read the DAMAC Riverside guide: 4 and 5 bedroom townhouses with lagoons and green spaces in the Dubai South growth corridor.
Explore the DAMAC Riverside Community
DAMAC Properties: Lagoon Communities, Golf Villas and Branded Collaborations
Founded in 2002, DAMAC has delivered 48,000 homes and is known for large-scale master communities, luxury residential projects and branded collaborations.
View the DAMAC Developer ProfileFAQs
Ivy at DAMAC Riverside Construction Progress in August 2026: Frequently Asked Questions
The DLD project register shows Ivy at DAMAC Riverside, project 3170, at 38.13% construction progress, recorded at the RERA inspection on 26 August 2026. The RERA report for that visit prints no percentage of its own and gives the progress status as Main Contract, Progressing, so the 38.13% figure is the register reading.
The register lists the previous inspection at 21.44% and the 26 August 2026 inspection at 38.13%. It shows no date for the earlier reading, so the gap between the two shows direction rather than speed and cannot be converted into a monthly pace. Readings across the whole build are compared on the Ivy at DAMAC Riverside construction updates page.
No change appears in the record: the DLD register keeps the registered completion date at 31 December 2027, which falls inside the Q4 2027 handover scheduled for Ivy. Registered completion dates can be revised between inspection cycles, so the date is read again with each new reading rather than carried forward.
The report recorded site mobilisation still ongoing and enabling works substantially completed. Foundation, substructure and superstructure were progressing at advanced stages, internal works, infrastructure and MEP at different stages, and the external envelope and finishes at early stages. It describes the project as 594 G+1+R townhouses, meaning ground floor, first floor and roof level, built with a concrete structure and blockwork.
The image at the top of this page is a developer rendering of the planned townhouses and landscaped gardens, not a picture of the site on 26 August 2026. The photographs RERA takes during each inspection form part of the official record and are not reproduced here, so the construction stage is described from the written report and the register reading instead.
This page is the record for the August 2026 cycle, and its figures are those recorded on 26 August 2026. RERA publishes later inspections to the DLD project register for project 3170, which can be viewed in the Dubai REST app, so a newer reading may already exist there; each one is added to the construction updates timeline as it is published.
A Question the FAQ Can Not Answer?

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is helping you read the August 2026 inspection record for Ivy at DAMAC Riverside correctly before your next payment decision. Client identities and transactions are never published or referenced. Message me directly: you will always reach me personally, never a call center or sales team.
Ask your question, get your answer. No obligation and no follow-up unless you ask for it.