Ivy at DAMAC Riverside by DAMAC Properties in DAMAC Riverside project rendering used for the August 2026 construction update showing planned townhouses and landscaped garden gathering spaces in Dubai - Presented by Tohid Fetrat

DAMAC Properties · DAMAC Riverside · Construction Update

Ivy at DAMAC Riverside Construction Update - August 2026

26 August 2026 Inspection Records Ivy at 38.13% Construction Progress in the DLD Register

Superstructure works were progressing at advanced stages across Ivy's 594 townhouses, with internal works and MEP underway, when RERA inspected the site on 26 August 2026.

Direct advisor access. Every message answered personally, never by a call center.

38.13%DLD Register Progress
26 August 2026Inspection Date
Q4 2027Expected Handover
3170DLD Project Number

DLD Register Reading

Ivy at DAMAC Riverside Construction Snapshot

A rise of 16.69 points on the previous inspection reading of 21.44% puts Ivy at 38.13% in the DLD register, inside the superstructure band: the stretch of the build that the 55% construction-stage portion of Ivy's payment plan spans.

Project Name

Ivy at DAMAC Riverside

Project Number

3170

Project Status

Active

Construction Progress

38.13%

Inspection Date

26 August 2026

Construction Start

24 September 2024

Total Units

594 townhouses

Total Built Area

2,948.55 sq m

Expected Completion

31 December 2027

Data source: the DLD project register for project 3170, listed as Damac Riverside - Ivy and registered on 22 July 2024, and the RERA inspection report of 26 August 2026. The RERA report prints no percentage, so 38.13% is the DLD register reading recorded on 26 August 2026; a newer inspection may since have been added to the register. The hero image is a developer rendering of the planned townhouses, not a site photograph. Construction tracking against RERA inspection data runs across the full tohidfetrat.com project portfolio and is reviewed after every published cycle. Last updated: August 2026.

Want each new reading the day it publishes? Message me on WhatsApp and I will send it to you directly: one message per inspection cycle, nothing else. Message me on WhatsApp

This Inspection Cycle

Ivy at DAMAC Riverside Construction Progress Summary

The DLD register moved Ivy from a previous inspection reading of 21.44%, which it lists without a date, to 38.13% at the RERA visit of 26 August 2026. On that visit the RERA report recorded foundation, substructure and superstructure at advanced stages across the 594 G+1+R townhouses, while the external envelope and finishes had only reached early stages.

Completed
  • DLD project registration on 22 July 2024
  • Construction start on 24 September 2024
  • Enabling works, recorded as substantially completed
In Progress at 38.13%
  • Foundation, substructure and superstructure at advanced stages
  • Internal works, infrastructure and MEP at different stages
  • External envelope and finishes at early stages
  • Site mobilisation still ongoing at the inspection
Ahead of Handover
  • Remaining RERA inspection cycles toward 100% in the register
  • Envelope, finishes and infrastructure across the 594 townhouses
  • Handover in Q4 2027, registered completion 31 December 2027
Next inspectionPublished in the DLD project register after the next RERA site visit; no date is announced in advance.
Completion targetQ4 2027 handover, with 31 December 2027 as the registered completion date, 492 days after this inspection.
Remaining distance61.87 percentage points separate the 26 August 2026 reading from 100% in the register.

Payment Linked Progress

What 38.13% Progress Means for Ivy Buyers

Ivy's plan splits the price 20/55/25: 20% on booking, 55% during construction as scheduled in the SPA, and 25% on handover. A register reading of 38.13% sits inside that middle stretch, so it is the point to check where your money goes, what your SPA ties each instalment to, and whether your unit is registered. At this stage of Ivy, four actions matter most.

Before Each Construction-Stage Payment

Verify the escrow account

Payments toward the price should go only to the DLD regulated escrow account registered for project 3170 with First Abu Dhabi Bank. Ivy at DAMAC Riverside escrow account verification sets out the check; the lookup itself takes about two minutes against the official DLD project record.

Before Your Next Instalment

Reread your SPA payment schedule

Check whether your sale and purchase agreement ties each part of the 55% construction-stage portion to calendar dates or to progress stages, and how it defines the 25% due on handover in Q4 2027. Not sure how your instalments line up with this reading? Send me your SPA schedule and I will map it against the recorded inspection readings.

Soon After Booking

Confirm your Oqood registration

An off plan Ivy townhouse is recorded on Oqood, the DLD interim register, until handover allows a title deed to be issued. Confirming that your unit appears there under project 3170 matters most while the construction-stage payments are still building up.

Every Cycle

Track the remaining cycles

61.87 points remain between this reading and 100% in the register, with the envelope and finishes still ahead. Ivy at DAMAC Riverside construction updates record each new reading as it is published.

General framework, not legal advice: instalment triggers, notice periods, and fee obligations are set by your individual SPA and the DLD record, and both should be read directly.

Buying at 38.13%?

Entering Ivy mid-construction trades launch-stage runway for a clearer picture: the frame was at advanced stages at the 26 August 2026 inspection, the envelope and finishes are still ahead, and the remaining choice is between the townhouses still released. Every payment toward the price goes to the DLD-registered escrow account for project 3170, released against construction progress recorded in RERA inspections.

Entering Now at 38.13%
  • Recorded progress: the 26 August 2026 register reading above is the risk picture
  • Handover scheduled for Q4 2027
  • 20% on booking and 25% on handover, with 55% as scheduled in your SPA
Typical Launch Entry
  • Construction risk carried from enabling works to handover
  • Two to four years of waiting is the usual delivery horizon
  • Longer instalment runway, priced at launch levels
AED 2.55M ≈ USD 694KStarting Price
20/55/25 Plan25% Due on Handover
Q4 2027Expected Handover
Ask What Is Available at Ivy

Limited Units Available on the project page as of this update; availability shifts between cycles.

About the Development

Ivy at DAMAC Riverside Project Details

Ivy at DAMAC Riverside by DAMAC Properties in DAMAC Riverside aerial project rendering showing a central lagoon surrounded by villas, paths and landscaped recreation areas in Dubai - Presented by Tohid Fetrat
DAMAC Riverside · DAMAC Properties

With its superstructure at advanced stages in the 26 August 2026 RERA report, Ivy is a mid-construction cluster of 594 townhouses in 4 and 5 bedroom formats within DAMAC Riverside. Starting prices: AED 2.55M ≈ USD 694K.

For buyers entering at this stage, the trade off is a defined townhouse at the current release price against an envelope and finishes still at early stages, with handover scheduled for Q4 2027.

Ivy at DAMAC Riverside Project Guide

Site Context This Cycle

Explore Ivy at DAMAC Riverside Location on Dubai Map

Ivy is one townhouse cluster within DAMAC Riverside in Dubai Investment Park 2, built as rows of low-rise G+1+R homes rather than a single tower, so work advances across many homes at once: the RERA report of 26 August 2026 records internal works, infrastructure and MEP progressing at different stages across the cluster.

DAMAC describes the community as having easy access to key roads and major highways, and its brochure places DAMAC Riverside about 12 minutes from Al Maktoum International Airport, an approximate community-level figure. The lagoon, parks and shared amenities are presented as planned facilities of the masterplan, so buyers weighing a Q4 2027 move-in or rental plan should check which of them are scheduled to open alongside Ivy's handover. See the cluster's position on the interactive Dubai real estate map. See the project’s position on the interactive Dubai real estate map.

Interactive Dubai real estate map preview
Click to view Ivy at DAMAC Riverside on Dubai Map

Buyer Resources for This Project

Investing in Ivy at DAMAC Riverside During Active Construction

The superstructure band is where payment protection and residency planning carry the most weight for Ivy buyers. Each resource below is matched to where Ivy stood at the 26 August 2026 inspection.

Ivy at DAMAC Riverside by DAMAC Properties in DAMAC Riverside construction updates cover image featuring a project rendering of modern townhouses facing a landscaped garden and gathering area in Dubai - Presented by Tohid Fetrat
You Are Here

Ivy at DAMAC Riverside Construction Updates

This page: the 26 August 2026 DLD register reading for Ivy, set against the RERA report.

Ivy at DAMAC Riverside by DAMAC Properties in DAMAC Riverside Golden Visa concept graphic with a gold card above a rendered waterfront pool and illuminated cabanas in Dubai - Presented by Tohid Fetrat

Ivy Golden Visa: Both Townhouse Types Above the AED 2M Threshold

Ivy at DAMAC Riverside, DAMAC Properties' townhouse cluster in Dubai Investment Park 2, qualifies at both 4 and 5 bedroom types.

Read the Ivy at DAMAC Riverside Golden Visa Guide
Ivy at DAMAC Riverside by DAMAC Properties in DAMAC Riverside escrow account concept graphic featuring a shield and padlock above a rendered landscaped swimming pool and villas in Dubai - Presented by Tohid Fetrat

Ivy at DAMAC Riverside Escrow: First Abu Dhabi Bank, Plot 876

Ivy at DAMAC Riverside, DLD project 3170, escrows 594 townhouses with First Abu Dhabi Bank and read 38.13% in August 2026.

Verify the Ivy at DAMAC Riverside Escrow Account

Update Timeline

Other Ivy at DAMAC Riverside Construction Updates

The August 2026 record is the first monthly page for Ivy in this series; later readings join the timeline on the construction updates page as each one is published.

All Ivy at DAMAC Riverside Construction Updates

FAQs

Ivy at DAMAC Riverside Construction Progress in August 2026: Frequently Asked Questions

The DLD project register shows Ivy at DAMAC Riverside, project 3170, at 38.13% construction progress, recorded at the RERA inspection on 26 August 2026. The RERA report for that visit prints no percentage of its own and gives the progress status as Main Contract, Progressing, so the 38.13% figure is the register reading.

The register lists the previous inspection at 21.44% and the 26 August 2026 inspection at 38.13%. It shows no date for the earlier reading, so the gap between the two shows direction rather than speed and cannot be converted into a monthly pace. Readings across the whole build are compared on the Ivy at DAMAC Riverside construction updates page.

No change appears in the record: the DLD register keeps the registered completion date at 31 December 2027, which falls inside the Q4 2027 handover scheduled for Ivy. Registered completion dates can be revised between inspection cycles, so the date is read again with each new reading rather than carried forward.

The report recorded site mobilisation still ongoing and enabling works substantially completed. Foundation, substructure and superstructure were progressing at advanced stages, internal works, infrastructure and MEP at different stages, and the external envelope and finishes at early stages. It describes the project as 594 G+1+R townhouses, meaning ground floor, first floor and roof level, built with a concrete structure and blockwork.

The image at the top of this page is a developer rendering of the planned townhouses and landscaped gardens, not a picture of the site on 26 August 2026. The photographs RERA takes during each inspection form part of the official record and are not reproduced here, so the construction stage is described from the written report and the register reading instead.

This page is the record for the August 2026 cycle, and its figures are those recorded on 26 August 2026. RERA publishes later inspections to the DLD project register for project 3170, which can be viewed in the Dubai REST app, so a newer reading may already exist there; each one is added to the construction updates timeline as it is published.

A Question the FAQ Can Not Answer?

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is helping you read the August 2026 inspection record for Ivy at DAMAC Riverside correctly before your next payment decision. Client identities and transactions are never published or referenced. Message me directly: you will always reach me personally, never a call center or sales team.

Ask your question, get your answer. No obligation and no follow-up unless you ask for it.

Get Progress Alerts