The Dated Register Record for 594 Townhouses in Dubai Investment Park 2

Ivy at DAMAC Riverside reached 38.13% on the DLD register at its 26 August 2026 inspection, a climb that took superstructure to advanced stages across 594 townhouses.

Construction tracking against RERA inspection data, updated after every recorded inspection.

Direct advisor access. Every message answered personally, never by a call center.

38.13%Construction Progress
26 August 2026Latest RERA Inspection
594 townhouses, G+1+RTotal Units
Project 3170DLD Registration

Construction Snapshot

Ivy at DAMAC Riverside at a Glance

Ivy at DAMAC Riverside is the DAMAC Properties cluster of 594 townhouses inside DAMAC Riverside in Dubai Investment Park 2, entered in the DLD register as project 3170 on 22 July 2024. Construction started 64 days later, on 24 September 2024, and the inspection of 26 August 2026 put the build at 38.13%. Because Ivy rises as rows of G+1+R homes rather than one tower, each register percentage averages hundreds of low-rise units at different stages, which is why every reading below is tied to its registered dates.

DLD Project Number

3170

Project Status

Active

Construction Start

24 September 2024

Total Units

594 townhouses, G+1+R

Total Built-Up Area

2,948.55 sq m

Registered Completion Date

31 December 2027 (DLD)

Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.

Inspection Record

Ivy at DAMAC Riverside Construction Update Timeline

Ivy's record so far holds one dated reading: 38.13% at the RERA inspection of 26 August 2026, 701 days after the 24 September 2024 start. The register also lists an earlier inspection at 21.44% but gives it no date, so it sits on the track as a previous-inspection dot without a month and has no table row. The single row below links the full August 2026 update, and each later inspection will add a dated row above it.

Inspection MonthConstruction ProgressInspection DateFull Update
August 202638.13%26 August 2026View the August 2026 update

Pace Analysis

How Fast Ivy at DAMAC Riverside Has Been Built

With one dated inspection, Ivy has no measured pace between two readings yet. What its registered dates do support is plain arithmetic, shown below on 30-day months and labelled as arithmetic, not a forecast:

  • Sep 2024 to Aug 2026: whole-build average, from the 24 September 2024 start to 38.13% on 26 August 2026 (701 days)About 1.63 points per month
  • Aug 2026 to Dec 2027: the remaining 61.87 points spread evenly over the 492 days to the 31 December 2027 registered completion dateAbout 3.77 points per month

Neither figure is a verdict on the build. The first averages everything since the start, including the enabling works that the 26 August 2026 RERA report described as substantially completed and the foundations it placed at advanced stages; the second only shows what an even spread of the outstanding points would look like across the 492 days to 31 December 2027, the registered completion date that closes Ivy's Q4 2027 handover quarter. The earlier 21.44% reading carries no date in the register, so the step from it to 38.13% cannot be turned into a monthly rate either. For an end user timing a Q4 2027 move, and for an investor planning around the 25% handover payment, the number worth waiting for is the next dated reading: it will give Ivy its first measured pace between two inspections.

Get the Next Inspection Figure First

Tell me you are tracking Ivy at DAMAC Riverside and I will send you the next recorded figure and site photos directly, ahead of the page update.

Get the Next Update on WhatsApp

Project Profile

About Ivy at DAMAC Riverside

A 38.13% reading from 26 August 2026 only means something next to what is being built. The project guide sets out the townhouses this record is tracking toward:

Ivy at DAMAC Riverside by DAMAC Properties in DAMAC Riverside aerial project rendering showing a central lagoon surrounded by villas, paths and landscaped recreation areas in Dubai - Presented by Tohid Fetrat

Ivy at DAMAC Riverside: 594 Townhouses With Large Windows Facing Green Spaces

Ivy at DAMAC Riverside is a DAMAC Properties cluster of 594 four and five bedroom townhouses in Dubai Investment Park 2.

View the Ivy at DAMAC Riverside Project Guide

Considering a Mid-Construction Entry?

DAMAC releases Ivy's townhouses in stages, and what is on offer changes between inspection cycles. If the record on this page is what brought you here, ask me which 4 and 5 bedroom townhouses are released today.

Ask About Remaining Availability on WhatsApp

Stage Record

Ivy at DAMAC Riverside Build Stages, Mapped to the Inspections

Each stage below is pinned to Ivy's register dates and to the RERA report of 26 August 2026 rather than to a generic sequence, so the 38.13% reading sits between work that report lists as largely done and work it lists as only just begun.

22 Jul 2024 to 24 Sep 2024

Registration and Construction Start

Project 3170 entered the DLD register on 22 July 2024, and construction started on 24 September 2024, 64 days later.

Sep 2024 to the undated 21.44% reading

Enabling Works and Foundations

The opening works across Ivy's townhouse rows. The register's previous reading of 21.44% falls in this window but carries no date; by 26 August 2026 the report listed enabling works as substantially completed.

Current Phase26 Aug 2026, 38.13% at last reading

Substructure and Superstructure

At 38.13% on 26 August 2026, foundation, substructure and superstructure were at advanced stages, with internal works, infrastructure and MEP at different stages across the cluster.

After Aug 2026, no dated reading yet

Envelope, Finishes and Infrastructure

External envelope and finishes were at early stages in the 26 August 2026 report; later dated readings will show when this phase starts to lead the register.

To 31 Dec 2027, handover Q4 2027

Completion and Handover

Handover is scheduled for Q4 2027, with 31 December 2027 as the registered completion date; both still lay in the future at the 26 August 2026 reading.

What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Ivy at DAMAC Riverside's own record.

Buyer Position

Tracking Your Position at Ivy at DAMAC Riverside

This page is one of four project resources that together cover a Ivy at DAMAC Riverside purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Ivy at DAMAC Riverside by DAMAC Properties in DAMAC Riverside construction updates cover image featuring a project rendering of modern townhouses facing a landscaped garden and gathering area in Dubai - Presented by Tohid Fetrat
You Are Here

Ivy at DAMAC Riverside Construction Updates

This page: Ivy's dated DLD register record, from 22 July 2024 registration toward Q4 2027 handover.

Ivy at DAMAC Riverside by DAMAC Properties in DAMAC Riverside Golden Visa concept graphic with a gold card above a rendered waterfront pool and illuminated cabanas in Dubai - Presented by Tohid Fetrat

Ivy Golden Visa: Both Townhouse Types Above the AED 2M Threshold

Ivy at DAMAC Riverside, DAMAC Properties' townhouse cluster in Dubai Investment Park 2, qualifies at both 4 and 5 bedroom types.

Read the Ivy at DAMAC Riverside Golden Visa Guide
Ivy at DAMAC Riverside by DAMAC Properties in DAMAC Riverside escrow account concept graphic featuring a shield and padlock above a rendered landscaped swimming pool and villas in Dubai - Presented by Tohid Fetrat

Ivy at DAMAC Riverside Escrow: First Abu Dhabi Bank, Plot 876

Ivy at DAMAC Riverside, DLD project 3170, escrows 594 townhouses with First Abu Dhabi Bank and read 38.13% in August 2026.

Verify the Ivy at DAMAC Riverside Escrow Account

Approaching Handover

Between 38.13% and Handover: What Ivy at DAMAC Riverside Buyers Should Do Now

At the 26 August 2026 reading, Ivy's frame was at advanced stages while the envelope and finishes were only at early stages, so most of the visible change across the townhouse rows still lies before the Q4 2027 handover. The 55% construction-stage share of the price falls due during this stretch as scheduled in each SPA, which makes the three checks below worth doing before the next instalment, not when the handover notice arrives.

First, before each instalment, confirm that the payee is the escrow account registered for project 3170; the Ivy at DAMAC Riverside escrow account page shows how to match it against the DLD record.

Second, if residency is part of your plan, decide early whether to apply while your townhouse is off plan or after the title deed; the Ivy at DAMAC Riverside Golden Visa guide sets out both paths for homes from AED 2.55M ≈ USD 694K.

Third, read each new register reading as it is published rather than relying on marketing updates; the August 2026 Ivy construction update sets out the full detail of the 38.13% reading taken on 26 August 2026.

Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.

The Wider Picture

Explore DAMAC Riverside Structure

Ivy's register entry covers one cluster; the community, the listings and the developer around it complete the picture. These three pages place the 594-townhouse build in its wider DAMAC Riverside context:

Aerial view of DAMAC Riverside properties for sale in Dubai showing modern residences, landscaped green spaces and community water features, Presented by Tohid Fetrat

DAMAC Riverside Properties for Sale

Explore DAMAC Riverside properties for sale, featuring modern apartments, spacious townhouses, luxury villas, flexible payment plans and amenities.

See DAMAC Riverside Properties for Sale
DAMAC Riverside by DAMAC Properties aerial masterplan with central lagoon landscaped parks and residential villas illuminated at night in Dubai - Presented by Tohid Fetrat

DAMAC Riverside Community Overview

Read the DAMAC Riverside guide: 4 and 5 bedroom townhouses with lagoons and green spaces in the Dubai South growth corridor.

Explore the DAMAC Riverside Community
DAMAC Properties development overlooking Dubai skyline and waterfront with modern architecture at sunset in Dubai Presented by Tohid Fetrat

DAMAC Properties: Lagoon Communities, Golf Villas and Branded Collaborations

Founded in 2002, DAMAC has delivered 48,000 homes and is known for large-scale master communities, luxury residential projects and branded collaborations.

View the DAMAC Developer Profile

Construction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.

FAQs

Ivy at DAMAC Riverside Construction Updates Frequently Asked Questions

Ivy at DAMAC Riverside is an active project in the DLD register, number 3170, recorded at 38.13% construction progress for the RERA inspection of 26 August 2026, when the RERA report gave its status as Main Contract, Progressing. At that reading the build was in its substructure and superstructure stage; the full record is in the inspection timeline above.

The latest dated reading for Ivy at DAMAC Riverside is 38.13%, entered in the DLD register for the RERA inspection of 26 August 2026 and 16.69 points above the previous register reading of 21.44%, which is listed without a date. It is the only dated reading on Ivy's record so far, and the Ivy at DAMAC Riverside August 2026 construction update covers that inspection in full.

Construction at Ivy at DAMAC Riverside started on 24 September 2024, according to the DLD register, 64 days after the project was registered on 22 July 2024. The first dated progress reading on the record followed on 26 August 2026 at 38.13%, 701 days after the start.

Progress at Ivy at DAMAC Riverside is tracked through the DLD project register for project 3170, which carries the percentage recorded after each RERA site inspection; the latest is 38.13% from 26 August 2026. The RERA report itself prints no percentage, and the register entry, listed as Damac Riverside - Ivy, covers Ivy's 594 townhouses only, not the whole DAMAC Riverside community. The general method is set out in the Dubai Construction Updates methodology.

Averaged over the 701 days from the 24 September 2024 start to the 26 August 2026 reading of 38.13%, Ivy at DAMAC Riverside has moved about 1.63 points per 30-day month. Reaching 100% by the 31 December 2027 registered completion date would take about 3.77 points per month over the remaining 492 days. Both figures are arithmetic, not a forecast, and the pace analysis explains why no measured pace between two dated readings exists yet.

Handover at Ivy at DAMAC Riverside is scheduled for Q4 2027, and the DLD register lists 31 December 2027 as the registered completion date, the last day of that quarter, so the two dates agree. At the 26 August 2026 reading of 38.13% both were still in the future, and this page's record is updated when each new inspection is recorded, including any change to the registered date.

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is keeping the Ivy at DAMAC Riverside construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.

Ask your question, get your answer. No obligation and no follow-up unless you ask for it.

WhatsApp +971543443597
Get the Latest Status