Kore by Imtiaz in Dubai Land Residence Complex project rendering used for the August 2026 construction update showing planned residential towers and landscaping in Dubai - Presented by Tohid Fetrat

Imtiaz · Dubai Land Residence Complex · Construction Update

Kore by Imtiaz Construction Update - August 2026

August 2026 Inspection Records Kore by Imtiaz at a 0% Pre-Construction Baseline in Dubai Land Residence Complex

No construction activities had started when RERA inspected the Kore by Imtiaz plot on 11 August 2026, and the DLD register opens the record at 0%.

Direct advisor access. Every message answered personally, never by a call center.

0%DLD Register Reading
11 August 2026Inspection Date
Q4 2028Expected Completion
4549DLD Project Number

Verified DLD Inspection Data

Kore by Imtiaz Construction Snapshot

A 0% baseline, the first reading on record, places Kore by Imtiaz in the pre-construction band, the stage where escrow and registration checks count for more than any progress figure.

Project Name

Kore by Imtiaz

Project Number

4549

Project Status

Active

Construction Progress

0%

Inspection Date

11 August 2026

Construction Start

15 November 2026 (scheduled)

Total Units

351 residential units

Total Built Area

18,355.05 sq m

Expected Completion

Q4 2028

Data source: the Dubai Land Department project register reading dated 11 August 2026 and the RERA Independent Progress Monitoring Report from the same inspection, which records that no construction activities had started. Construction tracking against RERA inspection data runs across the full tohidfetrat.com project portfolio and is reviewed after every published cycle. The hero image is a developer rendering of the planned building, not a site photograph. Last updated: August 2026.

Want each new reading the day it publishes? Message me on WhatsApp and I will send it to you directly: one message per inspection cycle, nothing else. Message me on WhatsApp

This Inspection Cycle

Kore by Imtiaz Construction Progress Summary

Kore by Imtiaz was inspected on 11 August 2026, 22 days before its DLD registration on 2 September 2026, and the register records that first visit at 0%. With the registered construction start scheduled for 15 November 2026 in the DLD register, this report documents the starting line rather than a period of site works.

On Record
  • DLD registration of project 4549 on 2 September 2026
  • Baseline RERA inspection dated 11 August 2026
  • Trust account bank named in the RERA report: First Abu Dhabi Bank
At the 0% Baseline
  • No construction activities started at the time of inspection
  • RERA progress status recorded as N/A
  • The report carries an inspection photograph
Ahead of Handover
  • Registered construction start scheduled for 15 November 2026
  • One building: a basement, ground floor, three podium levels, 13 residential floors and a roof level
  • 351 residences, with handover expected in Q4 2028
Next inspectionPosted to the DLD project register after the next RERA site visit; no date has been announced, and this page records the August 2026 reading only.
Completion targetQ4 2028 handover per Imtiaz; the DLD register carries a registered completion date of 15 December 2028, inside that quarter.
Remaining distanceAll 100 percentage points remain between the August 2026 baseline and handover readiness.

Payment Linked Progress

What 0% Progress Means for Kore Buyers

Kore by Imtiaz is sold on two developer plans, 50/50 and 60/40 post-handover, whose instalments follow an indicative calendar rather than construction milestones. At the 0% baseline only the 20% booking payment had fallen due under either plan, and the first dated instalment, 5%, is set for 15 February 2027. At this stage of Kore, four actions matter most.

Before the Booking Payment

Verify the escrow account

Every payment toward a Kore apartment should go only to the DLD regulated escrow account registered for project 4549, held with First Abu Dhabi Bank. Kore by Imtiaz escrow account verification is the step before any transfer; the lookup itself takes about two minutes against the official DLD project record.

Before 15 February 2027

Reread your SPA payment schedule

Check which of the two plans your sale and purchase agreement carries and whether its instalment dates match the developer's indicative calendar, since the SPA is the binding version. Not sure how your instalments map to this reading? Send me your SPA schedule and I will map it against the recorded milestones.

After Signing the SPA

Confirm your Oqood registration

Your off-plan purchase should be recorded in the DLD Oqood register against project 4549, registered on 2 September 2026, with the 4% DLD registration fee paid alongside the 20% booking instalment. Keep the Oqood registration record with your SPA.

Every Cycle

Track the first construction readings

The registered construction start of 15 November 2026 is the next dated milestone in the register. The Kore by Imtiaz construction updates hub logs each new reading as it is posted.

General framework, not legal advice: instalment dates, registration steps, and fee obligations are set by your individual SPA and the DLD record, and both should be read directly.

Buying at 0%?

Entering before construction starts trades certainty for runway: nothing has been built yet and the delivery horizon runs to Q4 2028, while the payment calendar spreads instalments across the build at launch-stage pricing. Every payment goes to the DLD-registered escrow account for project 4549, released against inspected construction progress.

Entering at the 0% Baseline
  • No construction activities started at the 11 August 2026 inspection
  • Handover expected in Q4 2028, with the full build still ahead
  • 20% on booking, then dated 5% to 10% instalments from 15 February 2027
Typical Late Stage Entry
  • Built progress visible in the inspection record before you commit
  • Months rather than years until the expected handover
  • A larger share of the price due close to completion
AED 679K ≈ USD 185KStarting Price
50/50 or 60/40 PlanTwo Developer Payment Plans
Q4 2028Expected Handover
Ask What Is Available at Kore

Limited units available, per the project page as of this update; availability shifts between cycles.

About the Development

Kore by Imtiaz Project Details

Kore by Imtiaz in Dubai Land Residence Complex project rendering of residential towers and landscaped community grounds in Dubai - Presented by Tohid Fetrat
Dubai Land Residence Complex · Imtiaz

With construction not yet started at the August 2026 inspection, Kore by Imtiaz remains a pre-construction residential building of 351 studio, one-bedroom and two-bedroom apartments that Imtiaz sells fully furnished. Starting prices: AED 679K ≈ USD 185K.

For buyers entering at this stage, the trade off is the longest wait in exchange for the widest instalment runway, with handover expected in Q4 2028 per Imtiaz.

Kore by Imtiaz Project Guide

Site Context This Cycle

Explore Kore by Imtiaz Location on Dubai Map

Imtiaz's location map places Kore on a plot between a main road and a curved community loop in Dubai Land Residence Complex, with the vehicle entry and exit marked on the loop side. At the August 2026 inspection that plot showed no construction activity, so this cycle fixes the site's starting condition rather than any sequence of works.

The same map names Zayed University, Hamdan Bin Mohammed Smart University, Lycee International School, The Aquila School and HM Equestrian Club around the plot, which means the district's schools and institutions frame the site well before the building does, a point for buyers weighing a Q4 2028 move-in or rental plan. See the project's position on the interactive Dubai real estate map. See the project’s position on the interactive Dubai real estate map.

Interactive Dubai real estate map preview
Click to view Kore by Imtiaz on Dubai Map

Buyer Resources for This Project

Investing in Kore by Imtiaz Before Construction Starts

The pre-construction band is where payment protection, registration, and residency questions are settled. Each resource below is matched to where Kore by Imtiaz stands right now.

Kore by Imtiaz in Dubai Land Residence Complex construction updates cover image featuring a project rendering of residential towers and landscaped community surroundings in Dubai - Presented by Tohid Fetrat
You Are Here

Kore by Imtiaz Construction Updates

This page: the August 2026 baseline record for Kore by Imtiaz, logged before any site works.

Kore by Imtiaz in Dubai Land Residence Complex Golden Visa concept graphic with a gold card beside a rendering of residential towers in Dubai - Presented by Tohid Fetrat

Kore by Imtiaz Golden Visa: Every Apartment Against the AED 2M Line

Kore by Imtiaz, 351 residences in Dubai Land Residence Complex, has no studio, 1 or 2 bedroom that clears the threshold.

Read Kore by Imtiaz Golden Visa Guide
Kore by Imtiaz in Dubai Land Residence Complex escrow account concept graphic featuring a shield and padlock alongside a rendered residential building in Dubai - Presented by Tohid Fetrat

Kore by Imtiaz Escrow: A First Abu Dhabi Bank Account, Newly Opened

Kore by Imtiaz is DLD project 4549, its 351 units paying First Abu Dhabi Bank escrow, 0% certified August 2026.

Verify Kore by Imtiaz Escrow Account

Update Timeline

Other Kore by Imtiaz Construction Updates

This August 2026 baseline is the first reading on record for Kore by Imtiaz; every later inspection joins the timeline as it is posted to the register.

All Kore by Imtiaz Construction Updates

FAQs

Kore by Imtiaz Construction Progress in August 2026: Frequently Asked Questions

As of the inspection dated 11 August 2026, Kore by Imtiaz stands at 0% in the Dubai Land Department project register under project number 4549, the first reading on record for the project. The RERA Independent Progress Monitoring Report from the same visit prints no percentage and lists the RERA progress status as N/A.

A single 0% baseline cannot show whether a project is ahead of or behind schedule, because there is no earlier reading to measure it against. As of August 2026, Imtiaz states expected completion in Q4 2028 and the DLD register carries a registered completion date of 15 December 2028, inside that quarter; either date can be revised in a later cycle. How readings are tracked from one inspection to the next is covered on the Kore by Imtiaz construction updates hub.

The report for the 11 August 2026 visit records that no construction activities had started at the time of inspection, and it carries an inspection photograph. It describes the project as B+G+3P+13+R, Residential Building: a basement, ground floor, three podium levels, 13 residential floors and a roof level.

Yes. The inspection is dated 11 August 2026 and the DLD registration 2 September 2026, 22 days later. Both dates are shown here exactly as the register records them, and the 0% reading serves as the baseline for every later inspection of the project.

The DLD register lists a registered construction start date of 15 November 2026, about three months after the August 2026 inspection. It is a scheduled date in the register, not a recorded site event; the first reading taken after it will be the earliest evidence of whether site works are under way.

No. The hero image is a developer rendering of the planned building and its landscaping, not a photograph of the plot in August 2026. Because no construction activities had started at the 11 August 2026 inspection, no image on this page shows built progress.

A Question the FAQ Can Not Answer?

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is helping you read the August 2026 inspection record for Kore by Imtiaz correctly before your next payment decision. Client identities and transactions are never published or referenced. Message me directly: you will always reach me personally, never a call center or sales team.

Ask your question, get your answer. No obligation and no follow-up unless you ask for it.

Get Progress Alerts