Emaar · Dubai Creek Harbour
Lotus at Dubai Creek Harbour Construction Updates
The Finished Build Record of Four Mid-Rise Buildings on One Creek Beach Plot
Lotus at Dubai Creek Harbour reached 100% in the DLD register on 4 October 2024, completing four mid-rise Creek Beach buildings that now stand Finished and Ready.
Construction tracking against RERA inspection data, updated after every recorded inspection.
Direct advisor access. Every message answered personally, never by a call center.
Construction Snapshot
Lotus at Dubai Creek Harbour at a Glance
Lotus is Emaar's 270-unit apartment community in the Creek Beach district of Dubai Creek Harbour, built as four mid-rise buildings rather than a single tower. About thirty-one months separate its recorded construction start on 5 March 2022 from the 100% register reading of 4 October 2024, and the figures below are the DLD-registered anchors behind that record. Because project 2377 is recorded as one entry, buildings as different as G+M+6 and G+M+11 share a single progress figure: the heights vary across the cluster, the finish line does not.
2377
Finished
05 March 2022
270 units
336,531.98 sq m
30 September 2025 (DLD)
Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.
Inspection Record
Lotus at Dubai Creek Harbour Construction Update Timeline
The Lotus record holds one dated reading: 100% on 4 October 2024, logged against a previous register figure of 94.56% that carries no date. The single dot on the track marks that reading, and the table row links the October 2024 update with its full inspection notes. At the 23 September 2026 build of this page the reading is 719 days old, about twenty-three and a half months, and it remains the latest in the supplied register record.
| Inspection Month | Construction Progress | Inspection Date | Full Update |
|---|---|---|---|
| October 2024 | 100% | 4 October 2024 | View the October 2024 update |
Reading the dates: the DLD-registered completion date for project 2377 is 30 September 2025, and that date has now passed. The register had already logged 100% on 4 October 2024, 361 days before it, and now lists the project as Finished with handover status Ready. The registered date is an administrative anchor fixed at project registration, and the record shows no revised date in its place.
Pace Analysis
How Fast Lotus at Dubai Creek Harbour Has Been Built
With only one dated reading in the Lotus record, there is no pair of inspections to turn into a monthly rate, so this analysis measures the record in steps and durations instead:
- Undated previous reading to 4 Oct 2024: closing step, 94.56% to 100%+5.44 points, no rate computed
- 5 Mar 2022 recorded start to the 4 Oct 2024 reading of 100%About 31 months
- 4 Oct 2024 reading of 100% against the registered completion date of 30 September 2025361 days ahead
- 4 Oct 2024 reading of 100% to the 23 Sep 2026 build of this page719 days old
What the Lotus record shows is a finish line, not a curve. The register stepped from an undated 94.56% straight to 100%, and because the earlier figure has no date, any points-per-month number drawn from it would be invented; the 5.44 point step is reported here as a size, not a speed. The durations carry the real information: roughly 31 months from the recorded start to 100% for four buildings ranging from G+M+6 to G+M+11, and a full reading logged 361 days inside the registered completion window. For an end user, that moves the question from construction to the condition and title of one apartment; for an investor, it is a delivery that landed well ahead of its registered date, with the caveat that a reading 719 days old should be rechecked before it carries a decision.
Get the Next Inspection Figure First
Tell me you are tracking Lotus at Dubai Creek Harbour and I will send you the next recorded figure and site photos directly, ahead of the page update.
Get the Next Update on WhatsAppProject Profile
About Lotus at Dubai Creek Harbour
A completion record only matters in the context of what was delivered. The full project guide covers the finished apartments this page has been tracking:

Lotus at Dubai Creek Harbour, Four Buildings Around a Community Plaza
Lotus at Dubai Creek Harbour is a four-building Emaar development in Creek Beach, 270 apartments around a landscaped plaza.
View the Lotus at Dubai Creek Harbour Project GuideConsidering a Ready Entry at Lotus?
Lotus is listed with limited units available, and in a finished community the remaining apartments are released one at a time rather than by phase. If the record on this page is what brought you here, ask me for current availability before the choice of floors and outlooks narrows further.
Ask About Remaining Availability on WhatsAppStage Record
Lotus at Dubai Creek Harbour Build Stages, Mapped to the Inspections
Rather than a generic construction sequence, each stage below is anchored to what the Lotus record actually dates, so you can see which windows are fixed by a recorded date and which the register leaves open.
Registration and Site Start
The register records construction as started on 05 March 2022 and the project as registered on 29 March 2022, opening one record for all 270 units on plot 169 in Al Khairan First.
Structure Across Four Buildings
The four buildings rose to their final configurations of G+M+6, G+M+7, G+M+10 and G+M+11; the supplied register holds no dated reading inside this window.
Enclosure and Fit-Out
The register's previous reading of 94.56% carries no date, so this window cannot be fixed to a month; it is the last figure the record shows before the October 2024 inspection.
Completion Recorded
The 4 October 2024 inspection logged 100% in the register, and the IPMR of that date recorded construction substantially completed, BCC and DCD issued, and all DEWA meters installed.
Delivered and Ready
The register now lists project 2377 as Finished and its registered completion date has passed; handover status is Ready, and each apartment is accepted on its own condition.
What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Lotus at Dubai Creek Harbour's own record.
Buyer Position
Tracking Your Position at Lotus at Dubai Creek Harbour
This page is one of four project resources that together cover a Lotus at Dubai Creek Harbour purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Lotus at Dubai Creek Harbour Construction Updates
This page: the Lotus completion record, from the March 2022 start to the 100% register reading.

Lotus at Dubai Creek Harbour Golden Visa: 270 Creek Beach Units
Lotus at Dubai Creek Harbour, Emaar's 270-unit Creek Beach community, qualifies at 2 and 3 bedrooms; 1 bedroom apartments do not.
Read the Lotus at Dubai Creek Harbour Golden Visa Guide
Lotus at Dubai Creek Harbour Escrow: Dubai Islamic Bank's Creek Record
Dubai Islamic Bank held escrow for Lotus at Dubai Creek Harbour, DLD project 2377: 270 units, 100% certified October 2024.
Verify the Lotus at Dubai Creek Harbour Escrow Account
Lotus at Dubai Creek Harbour Snagging From G+M+6 to G+M+11
Lotus at Dubai Creek Harbour is an Emaar community of 270 apartments in four mid-rise buildings that face a shared plaza.
Book Lotus at Dubai Creek Harbour SnaggingApproaching Handover
Between 100% and Handover: What Lotus at Dubai Creek Harbour Buyers Should Do Now
The Lotus record closed at 100% on 4 October 2024, so what stands between a buyer and a settled apartment is no longer construction but verification: the condition of one unit, the payment history behind it, and the residency arithmetic. Ready apartments move on the timetable of the transfer rather than the build, which is why these three checks belong before you commit or collect keys, not after.
First, arrange an independent inspection of your specific apartment, because a project-level 100% says nothing about one unit's finishes; the Lotus snagging inspection guide sets out what gets checked and when.
Second, if you bought at launch, set your final 30% instalment, the one tied to construction completion, against the record on the Lotus escrow account guide; a buyer of a ready unit can use the same page to see how the project's funds were held.
Third, if residency is part of the plan, check your apartment type in the Lotus Golden Visa guide first, since the 1 bedroom tier sits below the property value threshold while the 2 and 3 bedroom tiers clear it.
Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.
The Wider Picture
Explore Dubai Creek Harbour Structure
A build record is only half the picture; the other half is what has been delivered around it. These three pages put the Lotus completion record in its market, community, and developer context:

Dubai Creek Harbour Properties for Sale
Browse waterfront apartments, branded residences and penthouses for sale in Dubai Creek Harbour.
See Dubai Creek Harbour Properties for Sale
Dubai Creek Harbour: Emaar's Waterfront City With a Marina and Urban Beach
Dubai Creek Harbour is Emaar's waterfront city between Downtown Dubai and the Creek, planned for 48,500 homes with skyline views.
Explore the Dubai Creek Harbour Community
Emaar Properties: Burj Khalifa, Downtown Dubai and Twenty Master Communities
Emaar, founded in 1997, built Burj Khalifa and Downtown Dubai and has delivered over 85,000 homes across twenty master communities.
View the Emaar Properties Developer ProfileConstruction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.
FAQs
Lotus at Dubai Creek Harbour Construction Updates Frequently Asked Questions
Lotus at Dubai Creek Harbour is complete: the DLD register lists project 2377 as Finished, with construction progress of 100% recorded on 4 October 2024, and the Independent Progress Monitoring Report of that date gives a Progress Status of Completed. Handover status is Ready. That reading was 719 days old at the 23 September 2026 build of this page, and the full record is in the Lotus inspection timeline above.
The latest percentage on record is 100%, logged in the DLD register on 4 October 2024, up 5.44 points from a previous register reading of 94.56% that carries no date. The inspection notes behind that figure are set out in the Lotus October 2024 construction update.
Lotus at Dubai Creek Harbour reached 100% in the DLD register on 4 October 2024, 361 days ahead of its registered completion date of 30 September 2025. That registered date has since passed, which is expected for a project already recorded as Finished: it was an administrative anchor set at registration, not a forecast still waiting to be met, and the record shows no revised date in its place. Handover status is Ready, and this page's record is updated if the register entry changes.
The DLD register records 270 units at Lotus at Dubai Creek Harbour, all 1, 2 and 3 bedroom apartments, spread across four mid-rise buildings of G+M+6, G+M+7, G+M+10 and G+M+11 around an inner community plaza in Creek Beach. The units are counted for project 2377 as a whole, and the construction record on this page covers all four buildings together.
The DLD register shows Lotus at Dubai Creek Harbour registered on 29 March 2022, with a recorded construction start of 05 March 2022. The first dated reading in the supplied record is the 100% of 4 October 2024, and no earlier inspection carries a date.
The DLD register entry for Lotus at Dubai Creek Harbour pairs the 4 October 2024 reading of 100% with a previous inspection figure of 94.56% that has no date attached, and no construction update exists for any earlier Lotus period. Without two dated readings there is no interval to measure, so this page reports the 5.44 point step as a size and computes no monthly pace; the durations that can be measured are in the Lotus pace analysis above.

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is keeping the Lotus at Dubai Creek Harbour construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.
Ask your question, get your answer. No obligation and no follow-up unless you ask for it.