Marina Place 1 by Emaar in Rashid Yachts & Marina project rendering used for the April 2026 construction update showing the planned glazed podium entrance and building facade in Dubai - Presented by Tohid Fetrat

Emaar · Rashid Yachts & Marina · Construction Update

Marina Place 1 Construction Update - April 2026

April 2026 Inspection Records Marina Place 1 at 4.23% Construction Progress in Rashid Yachts & Marina

Enabling and piling works were progressing at Marina Place 1 when RERA inspected the site on 3 April 2026, with the DLD register reading 4.23 percent.

Direct advisor access. Every message answered personally, never by a call center.

4.23%DLD Register Reading
3 April 2026Inspection Date
Q4 2028Expected Completion
3386DLD Project Number

Verified DLD Inspection Data

Marina Place 1 Construction Snapshot

A 4.23% register reading dated 3 April 2026 places Marina Place 1 in the earliest construction band, where the figure matters less for how the building looks and more for when milestone-linked instalments and escrow checks come into play.

Project Name

Marina Place 1 by Emaar

Project Number

3386

Project Status

Active

Construction Progress

4.23%

Inspection Date

3 April 2026

Construction Start

24 April 2025

Total Units

162 residential units

Total Built Area

16,712.96 sq m

Expected Completion

Q4 2028

Data source: RERA inspection conducted on 3 April 2026 (Independent Progress Monitoring Report, progress status Enabling Works, Progressing) and the DLD project register for project 3386, which carries the 4.23% reading; the inspection report itself prints no percentage. This is the latest reading in the supplied record. The header image is a developer rendering of the planned podium entrance, not a site photograph. Construction tracking against RERA inspection data runs across the full tohidfetrat.com project portfolio and is reviewed after every published cycle. Last updated: April 2026.

Want each new reading the day it publishes? Message me on WhatsApp and I will send it to you directly: one message per inspection cycle, nothing else. Message me on WhatsApp

This Inspection Cycle

Marina Place 1 Construction Progress Summary

Marina Place 1 entered the DLD register on 15 November 2024 and construction started on 24 April 2025, 160 days later. When RERA inspected the site on 3 April 2026, 344 days into the build, the report found enabling and piling works progressing. No earlier dated reading exists in the supplied record, so this cycle sets a starting point rather than a measured movement.

Recorded
  • DLD project registration on 15 November 2024
  • Construction start logged on 24 April 2025
  • Trust account recorded with Emirates NBD for project 3386
In Progress at 4.23%
  • Enabling works across the marina-front site
  • Piling works, reported as progressing on 3 April 2026
  • RERA progress status: Enabling Works, Progressing
Ahead of Handover
  • Shared underground tank and ground level works
  • Ground and first-floor amenity levels
  • Two residential blocks of 12 and 9 floors with podium townhouses
  • Roof works, then handover expected in Q4 2028
Next inspectionNot dated in the supplied record; readings after 3 April 2026 appear in the DLD project register for project 3386 and are added to this cluster as they publish.
Completion targetHandover expected in Q4 2028; the registered completion date in the DLD record is 31 December 2028, 1,003 days after this inspection.
Remaining distance95.77 percentage points separate the 3 April 2026 reading from 100%. Arithmetic, not a forecast: the whole-build average so far is about 0.37 points per month, and reaching 100% by the registered completion date would take about 2.86 points per month; early enabling and piling stages typically register low percentages.

Payment Linked Progress

What 4.23% Progress Means for Marina Place 1 Buyers

Emaar's published 80/20 plan for Marina Place 1 set its first four instalments to calendar dates, together 40% falling due by January 2026, and links the next five to construction completion, starting with 20% completion at an indicative August 2026 date. Against a 4.23% reading, the timing of those milestone-linked instalments follows actual construction progress as your SPA defines it. At this stage, four actions matter most.

Before Any Further Instalment

Verify the escrow account

Every instalment should go only to the DLD regulated escrow account registered for project 3386, held with Emirates NBD. Marina Place 1 escrow account verification is the step before any transfer; the lookup itself takes about two minutes against the official DLD project record.

Before the 20% Milestone

Reread your SPA milestone schedule

Check how your sale and purchase agreement defines the 20% construction completion trigger for the 4th instalment and how each milestone is notified, then map those clauses against the 4.23% reading of 3 April 2026. Not sure how your installments map to this reading? Send me your SPA schedule and I will map it against the recorded milestones.

After Booking

Confirm your Oqood registration

Oqood is the DLD interim register for off plan units. Check that your Marina Place 1 unit is recorded under your name against project 3386 and that the registered details match your SPA, because that record carries your purchase through every later stage to title.

Every Cycle

Track the remaining cycles

With 95.77 points still to be recorded before 100%, many inspection readings lie between this one and handover in Q4 2028. Marina Place 1 construction updates keep each dated reading in one place.

General framework, not legal advice: milestone definitions, notice periods, and fee obligations are set by your individual SPA and the DLD record, and both should be read directly.

Buying at 4.23%?

Entering at enabling and piling stage trades certainty for runway: the site is at its earliest recorded stage, handover is expected in Q4 2028, and most of the milestone-linked schedule still lies ahead. Every payment goes to the DLD-registered escrow account for project 3386, released against construction progress recorded through RERA inspections.

Entering Now at 4.23%
  • Enabling and piling works progressing per the 3 April 2026 RERA report
  • Handover expected in Q4 2028, a runway of more than two years
  • 60% of the 80/20 plan tied to construction milestones not yet reached
Typical Late Stage Entry
  • Most construction risk retired by the time of entry
  • Months rather than years to the delivery horizon
  • Shorter runway, with most of the price due close to handover
AED 2.08M ≈ USD 566KStarting Price
80/20 Plan20% Due on Completion
Q4 2028Expected Handover
Ask What Is Available at Marina Place 1

Limited units available as of this update; availability shifts between cycles.

About the Development

Marina Place 1 Project Details

Marina Place 1 by Emaar in Rashid Yachts & Marina waterfront residential buildings with balconies overlooking a marina with a yacht in the foreground in Dubai - Presented by Tohid Fetrat
Rashid Yachts & Marina · Emaar

With enabling and piling works progressing as of 3 April 2026, Marina Place 1 is at the start of a build planned to deliver 162 residences: 1 to 3 bedroom apartments across two blocks of 12 and 9 floors, plus a limited number of two-level townhouses. Starting prices: AED 2.08M ≈ USD 566K.

For buyers entering at this stage, the trade off is a longer wait to handover in Q4 2028 against more of the payment plan still tied to construction milestones beyond the April 2026 reading.

Marina Place 1 by Emaar Project Guide

Site Context This Cycle

Explore Marina Place 1 Location on Dubai Map

Marina Place 1 sits on a marina-front plot in Rashid Yachts & Marina, and the developer's key layout arranges its residential blocks around a central pool courtyard with the frontage facing the water. On a waterfront site, the ground has to be prepared and piled before anything rises, which is why enabling and piling works define the April 2026 inspection rather than any visible building.

Rashid Yachts & Marina is organised around a full-service marina with residences, restaurants and shops, so the surroundings of Marina Place 1 are further along than the building itself; with handover expected in Q4 2028, buyers can judge the setting now and follow the building reading by reading. See the project's position on the interactive Dubai real estate map. See the project’s position on the interactive Dubai real estate map.

Interactive Dubai real estate map preview
Click to view Marina Place 1 on Dubai Map

Buyer Resources for This Project

Investing in Marina Place 1 During Early Construction Progress

At enabling stage, escrow checks, Oqood registration, and residency planning matter far more than finishes. Each resource below is matched to where Marina Place 1 stood on 3 April 2026.

Marina Place 1 by Emaar in Rashid Yachts & Marina construction updates cover image featuring a project rendering of a covered terrace looking across a yacht marina in Dubai - Presented by Tohid Fetrat
You Are Here

Marina Place 1 Construction Updates

This page: the April 2026 inspection record for Marina Place 1 at enabling and piling stage.

Marina Place 1 by Emaar in Rashid Yachts & Marina Golden Visa concept graphic with a gold card above a landscaped outdoor recreation area in Dubai - Presented by Tohid Fetrat

Marina Place 1 at Rashid Yachts & Marina Golden Visa: Different Margins

Emaar's 162-residence Marina Place 1 at Rashid Yachts & Marina starts all four unit types at or above the threshold.

Read Marina Place 1 Golden Visa Guide
Marina Place 1 by Emaar in Rashid Yachts & Marina escrow account protection concept with visible shield and padlock icons over a landscaped outdoor swimming pool in Dubai - Presented by Tohid Fetrat

Marina Place 1 at Rashid Yachts & Marina Escrow: Emirates NBD File

Marina Place 1 at Rashid Yachts & Marina is DLD project 3386, 162 units, Emirates NBD escrow, 4.23% certified April 2026.

Verify Marina Place 1 Escrow Account

Update Timeline

Other Marina Place 1 Construction Updates

April 2026 is the opening monthly record for Marina Place 1; each later inspection joins the timeline as it is published, so the build can be followed reading by reading.

All Marina Place 1 Construction Updates

FAQs

Marina Place 1 Construction Progress in April 2026: Frequently Asked Questions

The DLD project register records Marina Place 1 at 4.23% construction progress following the RERA inspection of 3 April 2026, and the inspection report lists the progress status as Enabling Works, Progressing. The report itself prints no percentage: 4.23% is the register reading for project 3386.

Handover is expected in Q4 2028, and the DLD record as of April 2026 carries a registered completion date of 31 December 2028, which falls inside that quarter. Registered completion dates can be revised between inspection cycles, so the date is worth checking against the DLD register at each new reading; any revision would be stated in a later update.

The Independent Progress Monitoring Report dated 3 April 2026 notes that enabling and piling works were progressing at the site. It describes the planned development as townhouses over ground and podium levels, a shared underground tank, ground and first-floor amenity levels, two residential blocks of 12 and 9 floors, and a roof. The report carries inspection photographs; they are record documents and are not reproduced here.

On 3 April 2026 the site was still in enabling and piling works, the stage before the underground tank, the amenity levels and the two residential blocks rise, and early stages like this typically register low percentages. The figure places Marina Place 1 at the start of its build, 344 days after construction began on 24 April 2025, with handover expected in Q4 2028.

The app's inspection card dated 3 April 2026 shows 4.23% as current progress, and the app's previous-inspection figure also reads 4.23%, undated. Without a date for the earlier figure, no movement between the two readings can be measured, so this record reports the 3 April 2026 value on its own and draws no pace conclusion from the pair.

The DLD register lists Marina Place 1 as registered on 15 November 2024, the same month as the down payment in Emaar's published plan, with construction starting on 24 April 2025, 160 days later. The April 2026 inspection took place on 3 April 2026, 344 days after that start date.

A Question the FAQ Can Not Answer?

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is helping you read the April 2026 inspection record for Marina Place 1 at Rashid Yachts & Marina correctly before your next payment decision. Client identities and transactions are never published or referenced. Message me directly: you will always reach me personally, never a call center or sales team.

Ask your question, get your answer. No obligation and no follow-up unless you ask for it.

Get Progress Alerts