Marina Place 1 by Emaar in Rashid Yachts & Marina construction updates cover image featuring a project rendering of a covered terrace looking across a yacht marina in Dubai - Presented by Tohid Fetrat

Emaar · Rashid Yachts & Marina

Marina Place 1 at Rashid Yachts & Marina Construction Updates

Two Marina-Front Blocks and Podium Townhouses, Tracked From Enabling Works to Handover

Marina Place 1 stood at 4.23% on the DLD register after the RERA inspection of 3 April 2026, an early-record baseline for its marina-front blocks.

Construction tracking against RERA inspection data, updated after every recorded inspection.

Direct advisor access. Every message answered personally, never by a call center.

4.23%Construction Progress
3 April 2026Latest RERA Inspection
162 residential unitsTotal Units
Project 3386DLD Registration

Construction Snapshot

Marina Place 1 at Rashid Yachts & Marina at a Glance

Marina Place 1 is Emaar's 162-residence address in Rashid Yachts & Marina, registered with the Dubai Land Department as project 3386 on 15 November 2024 and under construction since 24 April 2025. The latest reading in the supplied record, 4.23% dated 3 April 2026, belongs to enabling and piling works, so the registered anchors below say more about this build than the percentage does for now. What sets the record apart is its mix: two residential blocks of 12 and 9 floors share one podium with townhouses laid out over ground and podium levels, so every later reading describes both building types at once.

DLD Project Number

3386

Project Status

Active

Construction Start

24 April 2025

Total Units

162 residential units

Total Built-Up Area

16,712.96 sq m

Registered Completion Date

31 December 2028 (DLD)

Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.

Inspection Record

Marina Place 1 at Rashid Yachts & Marina Construction Update Timeline

One dated reading makes up the Marina Place 1 record so far: 4.23% on the DLD register following the RERA inspection of 3 April 2026, which found enabling and piling works progressing 344 days after the 24 April 2025 start. That single dot sits close to the left of the track below, with 95.77 points still open before handover; the table row links the April 2026 update, and each later reading joins both as it is recorded.

Inspection MonthConstruction ProgressInspection DateFull Update
April 20264.23%3 April 2026View the April 2026 update

Pace Analysis

How Fast Marina Place 1 at Rashid Yachts & Marina Has Been Built

With a single dated reading, Marina Place 1 has no inspection-to-inspection pace to measure yet. Two figures can still be worked out from the register dates, and both are arithmetic, not a forecast, on 30-day months:

  • Apr 2025 to Apr 2026: enabling and piling, 4.23 points over the 344 days from the 24 April 2025 start to the 3 April 2026 readingAbout 0.37 points per month
  • Apr 2026 to Dec 2028: 95.77 points over the 1,003 days left to the 31 December 2028 registered completion dateAbout 2.86 points per month needed

Read together, the two numbers mark the start of a curve rather than its shape. A 4.23% register reading after 344 days of enabling and piling on a marina-front site is the kind of figure early ground preparation typically produces, because work below ground moves the percentage far less than the podium, the 12 and 9 floor blocks, or the facades will later. The 2.86 figure is only what the remaining 95.77 points divide into across 1,003 days; it predicts nothing, and handover remains expected in Q4 2028. For an end user, the next dated readings show when the podium and the two blocks begin to register; for an investor, they show when the 20% construction completion milestone tied to the 4th instalment is reached, which your SPA governs rather than the indicative August 2026 date in the published plan.

Get the Next Inspection Figure First

Tell me you are tracking Marina Place 1 at Rashid Yachts & Marina and I will send you the next recorded figure and site photos directly, ahead of the page update.

Get the Next Update on WhatsApp

Project Profile

About Marina Place 1 at Rashid Yachts & Marina at Mina Rashid

A 4.23% reading only means something once you know what it is counting toward. The full project guide covers the homes this record will follow to completion:

Marina Place 1 by Emaar in Rashid Yachts & Marina waterfront residential buildings with balconies overlooking a marina with a yacht in the foreground in Dubai - Presented by Tohid Fetrat

Marina Place 1 at Rashid Yachts & Marina with Direct Marina Access

Marina Place 1 at Rashid Yachts & Marina holds 162 Emaar residences, apartments and a limited number of three bedroom townhouses.

View the Marina Place 1 at Rashid Yachts & Marina Project Guide

Considering an Early-Stage Entry?

Limited units are available at Marina Place 1, and what is on offer shifts between inspection cycles. If this record is what brought you here, ask me for the current options before you weigh the milestone-linked part of the plan.

Ask About Remaining Availability on WhatsApp

Stage Record

Marina Place 1 at Rashid Yachts & Marina Build Stages, Mapped to the Inspections

Each stage below is tied to the window it occupies in the Marina Place 1 record, from registration in November 2024 to the expected Q4 2028 handover; stages that no reading has reached yet are marked as not yet recorded rather than given dates.

Nov 2024 to Apr 2025

Registration and Site Mobilisation

Registered with the DLD as project 3386 on 15 November 2024; construction started on 24 April 2025, 160 days later, on the marina-front site.

Current PhaseApr 2025 onward, 4.23% at last reading

Enabling and Piling Works

The RERA inspection of 3 April 2026 reported enabling and piling works progressing, status Enabling Works, Progressing, with the DLD register at 4.23%.

Not yet recorded

Underground Tank and Podium Levels

As described in the 3 April 2026 report: a shared underground tank, ground and first-floor amenity levels, and townhouses over ground and podium levels.

Not yet recorded

Two Residential Blocks

Blocks of 12 and 9 floors rising from the podium, with apartments drawn on levels 1 to 12 in the developer floor plans; no reading covers this stage yet.

Toward Q4 2028

Roof, Finishing, and Handover

Roof works and finishing close the build; the registered completion date is 31 December 2028, and handover is expected in Q4 2028.

What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Marina Place 1 at Rashid Yachts & Marina 's own record.

Buyer Position

Tracking Your Position at Marina Place 1 at Rashid Yachts & Marina

This page is one of four project resources that together cover a Marina Place 1 at Rashid Yachts & Marina purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Marina Place 1 by Emaar in Rashid Yachts & Marina construction updates cover image featuring a project rendering of a covered terrace looking across a yacht marina in Dubai - Presented by Tohid Fetrat
You Are Here

Marina Place 1 at Rashid Yachts & Marina Construction Updates

This page: Marina Place 1's dated DLD register record, from the April 2025 start to handover.

Marina Place 1 by Emaar in Rashid Yachts & Marina Golden Visa concept graphic with a gold card above a landscaped outdoor recreation area in Dubai - Presented by Tohid Fetrat

Marina Place 1 at Rashid Yachts & Marina Golden Visa: Different Margins

Emaar's 162-residence Marina Place 1 at Rashid Yachts & Marina starts all four unit types at or above the threshold.

Read the Marina Place 1 at Rashid Yachts & Marina Golden Visa Guide
Marina Place 1 by Emaar in Rashid Yachts & Marina escrow account protection concept with visible shield and padlock icons over a landscaped outdoor swimming pool in Dubai - Presented by Tohid Fetrat

Marina Place 1 at Rashid Yachts & Marina Escrow: Emirates NBD File

Marina Place 1 at Rashid Yachts & Marina is DLD project 3386, 162 units, Emirates NBD escrow, 4.23% certified April 2026.

Verify the Marina Place 1 at Rashid Yachts & Marina Escrow Account

Approaching Handover

Between 4.23% and Handover: What Marina Place 1 at Rashid Yachts & Marina Buyers Should Do Now

At 4.23% almost the whole build still lies ahead, so the useful buyer work at Marina Place 1 right now is about payments and paperwork rather than finishes. Of the 80/20 plan Emaar published at launch, the four instalments fixed to calendar dates, 40% in total, were all due by January 2026; the 4th instalment is the first one tied to construction, at 20% completion with an indicative August 2026 date, against a register reading of 4.23% dated 3 April 2026. When it actually falls due follows recorded progress under your SPA, so the three checks below belong before the next milestone notice arrives, not after it.

First, confirm that every remaining instalment is directed to the Emirates NBD trust account for project 3386; the Marina Place 1 escrow account page shows how to check the account and how releases follow recorded milestones.

Second, if residency is part of your plan, settle the eligibility questions while most of the price is still ahead of you through the Marina Place 1 Golden Visa eligibility guide, since eligibility rests on the property value the DLD holds on record when you apply.

Third, place your unit within the configuration, one of the two blocks or the podium townhouses, using the Marina Place 1 project guide, so you know which part of the build your home depends on as the readings move.

Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.

The Wider Picture

Explore Mina Rashid Structure

A build record at enabling stage reads best against what already surrounds the site. These three pages place the Marina Place 1 readings in their market, community, and developer context:

Waterfront apartment buildings with modern architecture overlooking a marina filled with luxury yachts at Rashid Yachts and Marina by Emaar in Dubai Presented by Tohid Fetrat

Mina Rashid Properties for Sale

Browse waterfront apartments for sale at Rashid Yachts & Marina, with projects, prices and payment plans.

See Mina Rashid Properties for Sale
Luxury yachts at Rashid Yachts and Marina waterfront community with modern residences and marina promenade in Mina Rashid Dubai Presented by Tohid Fetrat

Mina Rashid Community Overview

Read the Rashid Yachts & Marina guide: Emaar's transformation of historic Port Rashid into a marina lifestyle community.

Explore the Mina Rashid Community
Emaar Properties developer showcasing Downtown Dubai skyline with Burj Khalifa and surrounding residential and commercial towers at dusk Presented by Tohid Fetrat

Emaar Properties: Burj Khalifa, Downtown Dubai and Twenty Master Communities

Emaar, founded in 1997, built Burj Khalifa and Downtown Dubai and has delivered over 85,000 homes across twenty master communities.

View the Emaar Properties Developer Profile

Construction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.

FAQs

Marina Place 1 at Rashid Yachts & Marina Construction Updates Frequently Asked Questions

Marina Place 1 is listed as Active on the Dubai Land Department register under project number 3386, with 162 units and a register reading of 4.23% dated 3 April 2026, the latest reading in the supplied record. The RERA inspection report of that date gives the progress status as Enabling Works, Progressing.

The Marina Place 1 record holds one dated reading: 4.23% on 3 April 2026, logged against the RERA inspection of that day. The DLD app's previous-inspection figure also reads 4.23%, undated, so no point change can be measured between the two; the detail of that cycle is in the Marina Place 1 April 2026 construction update, and each later reading is added to the inspection timeline as it is recorded.

Marina Place 1 has a registered completion date of 31 December 2028 in the DLD record and an expected handover in Q4 2028, and the two agree, because 31 December 2028 is the last day of that quarter. The registered date was set when the project was registered on 15 November 2024; at the 3 April 2026 reading it had not lapsed, with 1,003 days still to run.

Marina Place 1 is being built to deliver 162 residential units, the figure on the DLD register for project 3386: 1, 2 and 3 bedroom apartments plus a limited number of 3 bedroom townhouses. The register reading behind those 162 homes was 4.23% on 3 April 2026, and handover is expected in Q4 2028.

Marina Place 1 is planned as two residential blocks, one of 12 floors and one of 9, over a shared underground tank and ground and first-floor amenity levels, with the townhouses set across ground and podium levels, according to the RERA inspection report of 3 April 2026. Emaar's floor plans place the apartments on levels 1 to 12 and draw each townhouse as a two-level home with a ground-level terrace below a podium-level balcony.

Arithmetic, not a forecast: Marina Place 1 averaged about 0.37 points per month from the 24 April 2025 start to the 4.23% reading of 3 April 2026, and reaching 100% by the registered completion date of 31 December 2028 would take about 2.86 points per month over the remaining 1,003 days. Enabling and piling stages usually register low percentages, so these figures describe the record rather than predict it; the working is in the pace analysis above.

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is keeping the Marina Place 1 at Rashid Yachts & Marina construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.