Emaar · Rashid Yachts & Marina · Construction Update

Marina Place 2 Construction Update - April 2026

April 2026 Inspection Records Marina Place 2 at 1.52% as Enabling Works Progress at Rashid Yachts & Marina

Site mobilisation and enabling works were under way at Marina Place 2 when RERA inspected on 21 April 2026, with the DLD register reading 1.52 percent.

Direct advisor access. Every message answered personally, never by a call center.

1.52%DLD Register Reading
21 April 2026Inspection Date
Q4 2028Expected Handover
3387DLD Project Number

Verified DLD Inspection Data

Marina Place 2 Construction Snapshot

A 1.52% DLD register reading on 21 April 2026 places Marina Place 2 at the opening of the enabling band, the stage where escrow, Oqood registration and the dated payment schedule weigh more on a buyer's decision than the reading itself.

Project Name

Marina Place 2 by Emaar

Project Number

3387

Project Status

Active

Construction Progress

1.52%

Inspection Date

21 April 2026

Construction Start

24 April 2025

Total Units

179 Residential Units

Total Built Area

18,943.39 sq m

Expected Completion

31 December 2028

Data source: RERA Independent Progress Monitoring Report for the inspection of 21 April 2026 and the Dubai Land Department project register for project 3387, where 1.52% was the latest reading in the supplied record; the report itself prints no percentage. The hero image is a developer rendering, not a site photograph. Construction tracking against RERA inspection data runs across the full tohidfetrat.com project portfolio and is reviewed after every published cycle. Last updated: April 2026.

Want each new reading the day it publishes? Message me on WhatsApp and I will send it to you directly: one message per inspection cycle, nothing else. Message me on WhatsApp

This Inspection Cycle

Marina Place 2 Construction Progress Summary

At the 21 April 2026 inspection the DLD register showed Marina Place 2 at 1.52%, 1.50 points above the previous register reading of 0.02%; the app gives no date for that earlier reading, so the gain cannot be tied to a period or turned into a pace. What the record does fix is the stage: RERA found site mobilisation ongoing and enabling works progressing, with the building itself still ahead.

Completed
  • DLD registration as project 3387 on 15 November 2024
  • Construction start recorded in the register on 24 April 2025
  • Project trust account assigned at Emirates Islamic Bank
In Progress at 1.52%
  • Site mobilisation, recorded as ongoing at the 21 April 2026 visit
  • Enabling works, with the RERA status Enabling Works, Progressing
Ahead of Handover
  • The single building: ground, podium and twelve residential floors
  • Building systems and finishes for 179 residences, two-level townhouses included
  • Remaining RERA inspection cycles toward 100% and the Q4 2028 handover
Next inspectionPublished in the DLD project register after the next RERA site visit; this page records the 21 April 2026 cycle, and later cycles join the hub.
Completion targetQ4 2028 handover; the register showed a registered completion date of 31 December 2028, 985 days after this reading (arithmetic, not a forecast).
Remaining distance98.48 percentage points separated the 21 April 2026 reading from 100%, taken 362 days after the recorded construction start of 24 April 2025.

Payment Linked Progress

What 1.52% Progress Means for Marina Place 2 Buyers

Emaar's launch schedule for Marina Place 2 is an 80/20 plan whose later rows pair a date with a construction milestone, so a reading of 1.52% is the reference point for working out which obligations come next. At this enabling stage, four actions matter most.

Before Any Further Instalment

Verify the escrow account

Any payment still ahead should go only to the DLD regulated escrow account registered for project 3387 at Emirates Islamic Bank. Marina Place 2 escrow account verification is the step before any transfer; the lookup itself takes about two minutes against the official DLD project record.

Before You Sign or Pay

Reread your SPA milestone schedule

By the 21 April 2026 reading, four dated instalments totalling 40% had fallen due on the launch schedule while the register showed 1.52%; the next row, 10% dated August 2026, is labelled against 20% construction completion, and your SPA decides whether the date or the milestone triggers it. Not sure how your installments map to this reading? Send me your SPA schedule and I will map it against the recorded milestones.

After Booking

Confirm your Oqood registration

At the enabling stage the interim Oqood registration with the Dubai Land Department is the record that ties your unit to project 3387; check that it names the correct Marina Place 2 unit and matches your SPA before the next instalment.

Every Cycle

Track the next readings

As of April 2026 the register showed no stage beyond enabling works, so each new entry is worth setting against the dated rows of your plan. Marina Place 2 construction updates hub records each cycle as it publishes.

General framework, not legal advice: milestone definitions, notice periods, and fee obligations are set by your individual SPA and the DLD record, and both should be read directly.

Buying at 1.52%?

Entering at the enabling stage trades certainty for time: the building has not yet risen, handover is planned for Q4 2028, and the price is today's list rather than a finished-building price. Every payment goes to the DLD-registered escrow account for project 3387, released against recorded construction progress.

Entering Now at 1.52%
  • Enabling works on the April 2026 record, the building still to rise
  • Handover planned for Q4 2028, roughly two and a half years after this reading
  • 20% of the 80/20 plan falls due on completion
Typical Late Stage Entry
  • The building largely visible before you commit
  • A shorter wait between purchase and keys
  • Less instalment runway left before completion
From AED 2.08M ≈ USD 566KStarting Price
80/20 Plan20% Due on Completion
Q4 2028Expected Handover
Ask What Is Available at Marina Place 2

Limited units available per the project page as of this update; availability shifts between cycles.

About the Development

Marina Place 2 Project Details

Marina Place 2 by Emaar in Rashid Yachts & Marina project rendering of an elevated residential terrace with people overlooking the marina, yachts and waterfront skyline in Dubai - Presented by Tohid Fetrat
Rashid Yachts & Marina · Emaar

Still at mobilisation and enabling works in April 2026, Marina Place 2 is one G+P+12 building of 179 residences, split between 1 to 3 bedroom apartments and two-level 3 bedroom townhouses. Starting prices: AED 2.08M ≈ USD 566K.

For buyers entering at this stage, the trade off is a long build still ahead against committing before the building rises, with handover expected in Q4 2028 and the remaining instalments set by your SPA.

Marina Place 2 at Rashid Yachts & Marina Project Guide

Site Context This Cycle

Explore Marina Place 2 Location on Dubai Map

Marina Place 2 sits inside Rashid Yachts & Marina with direct access to the marina, set between the old trading quarters of Bur Dubai and the business towers along Sheikh Zayed Road; in April 2026 its waterfront plot was still at mobilisation and enabling works, the work that prepares the ground before a building rises on it.

Unlike the build itself, the district around it already operates, with a working marina, a waterfront promenade and occupied residential buildings, so buyers at this early stage are judging an established address rather than a future one, and the Q4 2028 handover is the main variable. See the project's position on the interactive Dubai real estate map. See the project’s position on the interactive Dubai real estate map.

Interactive Dubai real estate map preview
Click to view Marina Place 2 at Rashid Yachts & Marina by Emaar on Dubai Map

Buyer Resources for This Project

Investing in Marina Place 2 During Enabling Works

The enabling band is where payment protection, residency planning and a long build horizon all need settling before the building rises. Each resource below is matched to where Marina Place 2 stood in April 2026.

Marina Place 2 by Emaar in Rashid Yachts & Marina construction updates cover image featuring a project rendering of residential buildings beside an illuminated waterfront promenade and yachts in Dubai - Presented by Tohid Fetrat
You Are Here

Marina Place 2 Construction Updates

This page: the 21 April 2026 inspection record for Marina Place 2 at the enabling stage.

Marina Place 2 by Emaar in Rashid Yachts & Marina Golden Visa concept graphic showing a gold card above a rendered waterfront swimming pool, residential balconies and planted poolside in Dubai - Presented by Tohid Fetrat

Marina Place 2 at Rashid Yachts & Marina Golden Visa: Four Layouts

Marina Place 2 at Rashid Yachts & Marina holds 179 Emaar residences; all four layouts start at or above the line.

Read the Marina Place 2 Golden Visa Guide
Marina Place 2 by Emaar in Rashid Yachts & Marina escrow account concept graphic showing a shield and padlock above a rendered residential building entrance and glazed lobby in Dubai - Presented by Tohid Fetrat

Marina Place 2 at Rashid Yachts & Marina Escrow, at Emirates Islamic

Marina Place 2 at Rashid Yachts & Marina escrows 180 units at Emirates Islamic, DLD project 3387, 1.52% certified April 2026.

Verify the Marina Place 2 Escrow Account

Update Timeline

Other Marina Place 2 Construction Updates

April 2026 is the first monthly report in this series for Marina Place 2, so the timeline starts here; later readings join the hub as each cycle publishes.

All Marina Place 2 Construction Updates

FAQs

Marina Place 2 Construction Progress in April 2026: Frequently Asked Questions

At the RERA inspection of 21 April 2026, the Dubai Land Department project register recorded Marina Place 2 (project 3387) at 1.52%. The RERA report for that visit prints no percentage of its own; it gives the progress status as Enabling Works, Progressing.

It can, but the April 2026 record showed no change: at the 21 April 2026 reading the register carried a registered completion date of 31 December 2028, which falls inside the Q4 2028 handover. Registered dates can be revised between inspection cycles, and any revision would appear in a later update; how readings feed the timeline is covered on the Marina Place 2 construction updates hub.

For Marina Place 2 in April 2026, 1.52% described a site still being prepared for its building rather than a building under way: RERA recorded mobilisation as ongoing and enabling works as progressing, and the record shows no later stage at that inspection. The ground, podium and twelve residential floors of the single building were all still ahead.

The DLD app's inspection card for 21 April 2026 lists 0.02% as the previous inspection but shows no date for it, so the interval between the two readings cannot be established. This page therefore plots 0.02% as an undated previous-inspection marker and draws no pace or monthly rate from the pair.

The Independent Progress Monitoring Report for 21 April 2026 notes that site mobilisation was ongoing and that enabling works were progressing, and it carries inspection photographs. It describes the project as a residential development of 1 building (G+P+12 floors) with 179 residential units and 1 retail unit.

The DLD register records project 3387 as registered on 15 November 2024 and construction as started on 24 April 2025, 160 days later. The 21 April 2026 inspection fell 362 days after that recorded start date.

A Question the FAQ Can Not Answer?

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is helping you read the April 2026 inspection record for Marina Place 2 at Rashid Yachts & Marina correctly before your next payment decision. Client identities and transactions are never published or referenced. Message me directly: you will always reach me personally, never a call center or sales team.

Ask your question, get your answer. No obligation and no follow-up unless you ask for it.

Get Progress Alerts