Marina Shores Construction Update showing the residential tower under construction on 11 July 2026 in Dubai Marina Captured by Tohid Fetrat

Emaar Properties · Dubai Marina

Marina Shores Construction Updates

The Verified Build Record on the Dubai Marina Promenade

Marina Shores reached 87.18% construction at its 14 May 2026 RERA inspection, closing the last stretch of Emaar's 53-storey Dubai Marina Promenade tower before December handover.

Construction tracking against RERA inspection data, updated after every recorded inspection.

Direct advisor access. Every message answered personally, never by a call center.

87.18%Construction Progress
14 May 2026Latest RERA Inspection
437 ResidencesTotal Units
Project 2425DLD Registration

Construction Snapshot

Marina Shores at a Glance

Marina Shores is Emaar's single 53-storey tower on Plot 58 in Marsa Dubai, registered with the DLD as project 2425 and recorded at 87.18% on 14 May 2026. Divide its 49,091.59 sq m built-up area across 437 registered residences and the shape of the build becomes clear: this is a vertical, compact-footprint project that stacks its density over 52 residential levels rather than spreading it across a plot, which is why the finishing phase carries as much of the schedule as the structure did.

DLD Project Number

2425

Project Status

Active

Construction Start

18 December 2022

Total Units

437 residential units

Total Built-Up Area

49,091.59 sq m

Registered Completion Date

31 December 2026 (DLD)

Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.

Inspection Record

Marina Shores Construction Update Timeline

Two readings sit in the published record for project 2425: 87.18% recorded on 14 May 2026, and the 81.87% carried in that same report as the preceding inspection. The 5.31-point move between them is verified; the date behind the earlier figure is not published, so it is shown here as a reading rather than a dated row. The track below plots both against the 100% handover line.

Inspection MonthConstruction ProgressInspection DateFull Update
May 202687.18%14 May 2026View the May 2026 update
Preceding inspection81.87%Carried in the 14 May 2026 report; date not publishedNo monthly update published for this reading

Pace Analysis

How Fast Marina Shores Has Been Built

Pace is what a single percentage cannot tell you. The published record for Marina Shores supports two measures, and it is worth being precise about which is which:

  • Dec 2022 start to May 2026 inspection: 0% to 87.18% across roughly 41 monthsAbout 2.1 points per month
  • Preceding reading to 14 May 2026: 81.87% to 87.18%, interval not publishedPlus 5.31 points, pace not computable

A phase-by-phase velocity curve needs at least two dated readings, and the RERA record for project 2425 currently publishes one, so this page does not draw a curve it cannot verify. What the record does support is a whole-build average of roughly 2.1 points per month from the 18 December 2022 start to the 87.18% reading, and a verified 5.31-point step to that latest figure. What the inspection brief adds is more useful than a synthetic curve would be: piling, foundations, substructure and superstructure are recorded complete, and the remaining work is MEP installation, facade, external areas and interior finishes. That is the profile of a tower whose visible construction is behind it and whose remaining percentage is bought in commissioning and finishing, which historically moves slowly and then lands. For a buyer weighing the 31 December 2026 registered completion, the useful question is no longer whether the structure will rise but how quickly the finishing trades clear.

Get the Next Inspection Figure First

Tell me you are tracking Marina Shores and I will send you the next recorded figure and site photos directly, ahead of the page update.

Get the Next Update on WhatsApp

Project Profile

About Marina Shores at Dubai Marina

The build percentage only matters in the context of what is being delivered. The full project guide covers what buyers are tracking toward on this page:

Marina Shores at Dubai Marina by Emaar Properties illuminated waterfront residential tower and marina skyline at dusk in Dubai Presented by Tohid Fetrat

Marina Shores Project Guide

One to four bedroom apartments and a single five bedroom penthouse across 52 residential levels, the amenity deck, the Promenade-front position on Plot 58, and the full investment case behind Emaar's last marina-front tower.

View the Marina Shores Project Guide

Considering a Near-Handover Entry?

Availability at Marina Shores continues to shift as the tower approaches completion. If the record on this page is what brought you here, ask me for current availability before remaining inventory narrows further.

Ask About Remaining Availability on WhatsApp

Stage Record

Marina Shores Build Stages, Mapped to the Record

Rather than a generic construction sequence, each stage below is anchored to a date or a percentage the record actually carries for project 2425, from DLD registration in July 2022 to the 87.18% reading of May 2026.

Jul 2022 to Dec 2022

Registration to Site Start

Project 2425 was registered with the Dubai Land Department on 07 July 2022; construction was recorded as started on 18 December 2022, about five months later.

Dec 2022 onward

Piling, Foundations, and Substructure

Two basement levels and the podium set out beneath a 49,091.59 sq m built-up area on a constrained Promenade-front plot. The RERA record publishes no percentage reading inside this window.

To the 81.87% reading

Superstructure to 53 Storeys

The 2B plus G plus 52 frame topped out and the inspection brief now logs piling, foundations, substructure and superstructure as complete, which is why no further structural percentage is in play.

81.87% to 87.18%

Facade, MEP, and Interior Fit-Out

The verified 5.31-point step to the May 2026 reading was bought in envelope, MEP installation, external areas and interior finishes rather than in visible structure.

Current Phase 14 May 2026 at 87.18%

Finishing, Commissioning, and Delivery

Apartment finishing, systems commissioning across 52 residential levels, and external works toward the 31 December 2026 registered completion, recorded at 87.18% on 14 May 2026.

What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on the Marina Shores record.

Buyer Position

Tracking Your Position at Marina Shores

This page is one of four project resources that together cover a Marina Shores purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Marina Shores Construction Update showing the residential tower under construction on 11 July 2026 in Dubai Marina Captured by Tohid Fetrat
You Are Here

Marina Shores Construction Updates

This page: the verified inspection record for Marina Shores, from the December 2022 start to handover.

Golden Visa residency opportunity at Marina Shores featuring luxury waterfront living in Dubai Marina Presented by Tohid Fetrat

Marina Shores Golden Visa

Check whether a qualifying Marina Shores purchase supports 10-year UAE Golden Visa residency eligibility.

Read the Marina Shores Golden Visa Guide
Secure escrow account protection at Marina Shores featuring the luxury pool deck and waterfront residential tower Presented by Tohid Fetrat

Marina Shores Escrow Account

Verify the ADCB escrow account holding Marina Shores payments against each certified construction milestone released.

Verify the Marina Shores Escrow Account
Marina Shores Snagging Inspection showing the residential tower on 11 July 2026 in Dubai Marina Captured by Tohid Fetrat

Marina Shores Snagging Inspection

At 87.18% recorded progress, arrange independent defect documentation before accepting your Dubai Marina residence.

Book Marina Shores Snagging

Approaching Handover

Between 87.18% and Handover: What Marina Shores Buyers Should Do Now

The 12.82 points still open at Marina Shores are closed by commissioning, finishes and approvals rather than by anything visible from the Promenade, which makes this the window where buyer preparation matters most. Handover notices at comparable projects typically give buyers a short window to complete their appointment, so the three steps below happen now, not when the notice arrives.

First, arrange independent snagging so defects in your residence are documented before you accept it; the Marina Shores snagging page covers timing and the glazing, balcony and high-rise systems checks that matter in a marine-front tower.

Second, confirm your remaining installments against the certified milestones on the Marina Shores escrow account page, so the final payments on an 80/20 structure track verified progress rather than requests.

Third, if your purchase may qualify for residency, settle eligibility before handover through the Marina Shores Golden Visa guide, since the title deed timing affects the application path.

Send me your unit number on WhatsApp and I will tell you what the May inspection means for your handover and map the sequence for your specific residence.

The Wider Picture

Explore Dubai Marina Structure

A build record is only half the picture; the other half is the district it is being delivered into. These three pages put the Marina Shores percentage in its market, community, and developer context:

Dubai Marina waterfront skyline and yacht harbor view for Dubai Marina Properties for Sale Captured by Tohid Fetrat

Dubai Marina Waterfront Properties for Sale

Compare marina-front residences delivering around Marina Shores as its 53-storey tower closes on handover.

See Dubai Marina Properties for Sale
Aerial sunset view of Dubai Marina with illuminated towers and waterfront skyline showcasing luxury urban living in Dubai presented by Tohid Fetrat.

Dubai Marina Community Overview

See where this 437-residence tower lands inside a mature waterfront district of 150 plus towers.

Explore the Dubai Marina Community
Emaar Properties developer showcasing Downtown Dubai skyline with Burj Khalifa and surrounding residential and commercial towers at dusk Presented by Tohid Fetrat

Emaar Properties Developer Profile

Review Emaar's delivery record across Dubai Marina before Marina Shores reaches its December 2026 handover.

View the Emaar Properties Developer Profile

Construction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.

FAQs

Marina Shores Construction Updates Frequently Asked Questions

Marina Shores is an active DLD-registered project (number 2425) in its finishing and commissioning phase, recorded at 87.18% at the inspection of 14 May 2026. The full record is in the inspection timeline above.

The 14 May 2026 inspection recorded 87.18% construction progress, up 5.31 points from the 81.87% carried in the same report as the preceding reading. The full site report for that period is in the Marina Shores May 2026 construction update.

The DLD-registered completion date for project 2425 is 31 December 2026, and the 14 May 2026 inspection recorded 87.18%, leaving 12.82 points to close in finishing and commissioning. That registered date has not lapsed, and this page's record is updated when the next inspection is recorded.

DLD registration records show 437 residential units across a total built-up area of 49,091.59 sq m, held in a single 53-storey tower configured as two basements, ground, and 52 residential levels topped by one penthouse floor.

From the 18 December 2022 start to the 87.18% reading of 14 May 2026, roughly 41 months, construction averaged about 2.1 percentage points per month. A phase-by-phase pace curve cannot be drawn because the earlier 81.87% reading is published without its inspection date; the reasoning is set out in the pace analysis above.

Project 2425 was registered with the Dubai Land Department on 07 July 2022, and construction was recorded as started on 18 December 2022, about five months later.

Yes. The inspection brief behind the 87.18% reading of 14 May 2026 logs piling, foundations, substructure and superstructure as complete across the 53-storey tower, with MEP installation, facade, external areas and interior finishes carrying the remaining percentage.

With the tower at 87.18% and a 31 December 2026 registered completion, buyers typically arrange an independent inspection through the Marina Shores snagging inspection page around the handover appointment, check remaining installments against certified milestones on the Marina Shores escrow verification record, and settle residency questions through the Marina Shores Golden Visa eligibility guide before the title deed is issued.

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments - Presented by Tohid Fetrat

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is keeping the Marina Shores construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.

Ask your question, get your answer. No obligation and no follow-up unless you ask for it.

Get the Latest Status