Binghatti · Downtown Dubai · Construction Update
Mercedes-Benz Places Construction Update - April 2026
April 2026 Inspection Records Mercedes-Benz Places at 65.25% Construction Progress in Downtown Dubai
External envelope, MEP and interior finishing works shared the Mercedes-Benz Places site when the 28 April 2026 RERA inspection, still the register's latest, recorded 65.25 percent.
Direct advisor access. Every message answered personally, never by a call center.
Verified DLD Inspection Data
Mercedes-Benz Places Construction Snapshot
A 16.76 point rise since the 14 October 2025 inspection takes Mercedes-Benz Places to the upper end of the envelope and MEP band, less than five points below the 70% level where the finishing band begins. As of September 2026, this 28 April 2026 reading is still the latest in the DLD register.
Mercedes-Benz Places by Binghatti
2545
Active
65.25%
28 April 2026
15 December 2023
150 residences
40,341.18 sq m
Q4 2026
Data source: RERA inspection conducted on 28 April 2026, progress status Main Contract - Progressing, tracked against DLD inspection records. As of September 2026 the register shows no later inspection, so this remains the latest certified reading, about five months old at the time of this update. Construction tracking against RERA inspection data runs across the full tohidfetrat.com project portfolio and is reviewed after every published cycle. Last updated: September 2026.
Want each new reading the day it publishes? Message me on WhatsApp and I will send it to you directly: one message per inspection cycle, nothing else. Message me on WhatsApp
This Inspection Cycle
Mercedes-Benz Places Construction Progress Summary
Between the 14 October 2025 and 28 April 2026 inspections, Mercedes-Benz Places moved from 48.49% to 65.25%, a gain of 16.76 points over 196 days, or about 2.57 points per 30-day month, close to the 2.54 measured over the previous interval. The inspection notes kept the same wording across both cycles, so the gain came from further work inside packages already under way rather than from a newly completed stage.
- Enabling and foundation works, already finished by January 2025
- Substructure works, listed as complete again in April 2026
- No further package moved to complete between October 2025 and April 2026
- Superstructure, still reported as progressing
- External envelope on the tower and external works on the plot
- MEP systems throughout the building
- Internal works alongside internal finishes
- Mobilization, still noted as ongoing
- The 34.75 points still to be certified before 100%
- Completion of the penthouse levels 55 to 66 and the amenity floors
- Building completion procedures, then handover of 150 residences expected in Q4 2026
Payment Linked Progress
What 65.25% Progress Means for Mercedes-Benz Places Buyers
Any Mercedes-Benz Places payment tied to construction is defined by the buyer's own SPA rather than by the register, so the April 2026 figure of 65.25% is best used as the last checkpoint before the finishing band, with 34.75 points still to be certified. At this point in the build, four actions matter most.
Verify the escrow account
With about a third of the certified work still ahead, any payment should go only to the DLD regulated escrow account registered for project 2545 with Sharjah Islamic Bank. Mercedes-Benz Places escrow account verification comes before each transfer; the lookup itself takes about two minutes against the official DLD project record.
Match your SPA to the Q4 2026 handover
Read how your sale and purchase agreement defines completion, the handover notice period and any payment linked to a construction stage, then set those clauses against the Q4 2026 handover and the registered completion date of 31 December 2026. Not sure how your SPA schedule maps to this reading? Send me your SPA schedule and I will map it against the certified milestones.
Line up the snagging inspection
At 65.25%, just below the finishing band and with handover expected in Q4 2026, the pre handover inspection was approaching on this reading rather than already due. Mercedes-Benz Places snagging inspection guide sets out when to book and what a suite or penthouse check covers.
Watch for the next dated reading
The 28 April 2026 figure is still the register's latest as of September 2026, so the next inspection will show whether the recorded pace held. Mercedes-Benz Places construction updates hub keeps all three dated readings side by side.
General framework, not legal advice: milestone definitions, notice periods, and fee obligations are set by your individual SPA and the DLD record, and both should be read directly.
Buying at 65.25%?
Buying into Mercedes-Benz Places after the April 2026 reading means a tower with foundations and substructure already reported complete and roughly two thirds of its progress recorded, while the frame, skin, services and finishes are still being completed ahead of the Q4 2026 handover. Every payment goes to the DLD-registered escrow account for project 2545, released against certified construction progress.
- 65.25% certified on 28 April 2026, the latest dated reading
- Two measured intervals at about 2.54 and 2.57 points a month
- Handover expected in Q4 2026, months rather than years away
- The whole build, from excavation onward, still to come
- No inspection history to judge the builder's pace by
- A multi-year wait for keys, with pricing set at launch
30+ units listed available on the project page as of September 2026; availability shifts between cycles.
About the Development
Mercedes-Benz Places Project Details

Certified at 65.25% on 28 April 2026, Mercedes-Benz Places is a Binghatti hyper-tower developed with Mercedes-Benz, its substructure complete and its frame, envelope, services and finishes still in progress on a planned 341 m building of 150 suites and penthouses. Starting prices: AED 10.99M ≈ USD 2.99M.
Buying on this reading means a short wait with close to two thirds of the build already certified, with handover expected in Q4 2026 and 31 December 2026 as the registered completion date in the DLD record.
Mercedes-Benz Places by Binghatti Project GuideSite Context This Cycle
Explore Mercedes-Benz Places Location on Dubai Map
Plot 319, filed under the DLD's Burj Khalifa area, holds a single tower, so every package the April 2026 report lists as progressing at different stages, from the frame and external envelope to MEP and interior finishes, is stacked on one footprint that rises toward 341 m rather than spread across several buildings.
With handover expected in Q4 2026, the buyer's question at this reading shifts from access to occupancy: the developer's map puts the centre of Downtown Dubai 1.1 km or about 4 minutes away, and the district's roads, retail and Red Line stations already operate, so move-in and leasing plans hinge on the tower's own completion. See the project’s position on the interactive Dubai real estate map.

Buyer Resources for This Project
Investing in Mercedes-Benz Places Toward the Finishing Stage
Close to the finishing band, planning turns to residency paperwork, the protection of the payments that remain, and the inspection that comes with handover. Each resource below is matched to the April 2026 position of Mercedes-Benz Places.

Mercedes-Benz Places Construction Updates
This page: the 28 April 2026 reading of 65.25%, still the latest in the DLD register.

Mercedes-Benz Places Golden Visa: Suite or Penthouse, Every Type
Binghatti's Mercedes-Benz Places, 150 residences in Downtown Dubai, qualifies at all six types from the Pagoda Suite to triplex penthouse.
Read Mercedes-Benz Places Golden Visa Guide
Mercedes-Benz Places Escrow: Binghatti's Downtown Account at Sharjah Islamic Bank
Binghatti's Mercedes-Benz Places in Downtown Dubai is DLD project 2545, 163 units escrowed at Sharjah Islamic Bank, 65.25% certified April 2026.
Verify Mercedes-Benz Places Escrow Account
Mercedes-Benz Places Snagging for a Branded Hyper-Tower
Mercedes-Benz Places is the residential hyper-tower Binghatti is building with Mercedes-Benz in Downtown Dubai, holding 150 freehold residences.
Book Mercedes-Benz Places Snagging InspectionUpdate Timeline
Other Mercedes-Benz Places Construction Updates
April 2026 is the third dated reading in the register's sequence for Mercedes-Benz Places, after 48.49% in October 2025 and 26.13% in the Mercedes-Benz Places January 2025 construction update.
Where This Update Fits
Explore Mercedes-Benz Places Structure
The April 2026 report connects to a wider record: the Downtown Dubai district around plot 319, Binghatti as the developer delivering the tower, and the listings a buyer would weigh against it.

Downtown Dubai Properties for Sale
Browse apartments, branded residences and penthouses for sale around Burj Khalifa and The Dubai Mall.
See Downtown Dubai Properties for Sale
Downtown Dubai Community Overview
Read the Downtown Dubai guide: Emaar's city core around Burj Khalifa, The Dubai Mall and Dubai Opera, with prices and returns.
Explore the Downtown Dubai Community
Binghatti: Record Construction Speed and Branded Towers With Bugatti and Mercedes-Benz
Binghatti has delivered more than 60 projects since 2008, with 27 under development and two master communities across Dubai.
View the Binghatti Developer ProfileFAQs
Mercedes-Benz Places Construction Progress in April 2026: Frequently Asked Questions
The RERA inspection of 28 April 2026 put Mercedes-Benz Places, DLD project number 2545, at 65.25% construction progress, with the previous inspection listed as 48.49% on 14 October 2025. The register gives the progress status as Main Contract - Progressing and the project status as Active, and as of September 2026 it shows no inspection later than 28 April 2026.
Yes, as of September 2026. The 28 April 2026 report records progress rather than dates and did not revise the timeline: handover is expected in Q4 2026, and 31 December 2026 remains the registered completion date in the DLD record, 247 days after that inspection. Registered dates can be revised between cycles, and every dated reading for the tower is kept on the Mercedes-Benz Places construction updates hub.
Recorded progress went from 48.49% on 14 October 2025 to 65.25% on 28 April 2026, a rise of 16.76 percentage points over 196 days, or about 2.57 points per 30-day month. The earlier interval, from 26.13% in January 2025 to the October 2025 reading, ran at about 2.54 points per 30-day month, so the two dated intervals on record moved at a similar rate. Both figures describe past readings and are not a forecast.
The 28 April 2026 report listed enabling, foundation and substructure works as completed and mobilization as still ongoing, while the superstructure, external envelope, MEP systems, external works, internal works and internal finishes were progressing at different stages. Its notes are worded the same as in October 2025, so the 16.76-point rise came from further work inside those packages rather than from a newly completed one; the report does not break the work down by floor.
Yes. As of September 2026 the DLD register lists no inspection after 28 April 2026, so the 65.25% figure is about five months old at the time of this update and any later site work is not yet certified. Photographs taken on site on 20 June 2026 show the rising tower structure within the Downtown Dubai skyline, but a photograph carries no percentage; only the next RERA inspection will add one.
At 65.25% on 28 April 2026 the tower sat 4.75 points below 70%, the level at which this tracker moves a project into its finishing band, where snagging and handover preparation come to the front. With internal finishes already under way but the superstructure and external envelope still listed as in progress, the report describes a building between its envelope and finishing stages rather than one ready for pre handover checks.
A Question the FAQ Can Not Answer?

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is helping you read the April 2026 inspection record for Mercedes-Benz Places correctly before your next payment decision. Client identities and transactions are never published or referenced. Message me directly: you will always reach me personally, never a call center or sales team.
Ask your question, get your answer. No obligation and no follow-up unless you ask for it.