Mercedes Benz Places by Binghatti construction progress on 20 June 2026 showing the rising tower structure within the Downtown Dubai skyline Captured by Tohid Fetrat

Binghatti · Downtown Dubai

Mercedes-Benz Places Construction Updates

Three Dated Readings on One Downtown Dubai Tower, Tracked Toward a Q4 2026 Handover

Mercedes-Benz Places recorded 65.25% at the 28 April 2026 RERA inspection, its single Downtown Dubai tower having climbed from 26.13% in January 2025 at a near-constant pace.

Construction tracking against RERA inspection data, updated after every recorded inspection.

Direct advisor access. Every message answered personally, never by a call center.

65.25%Construction Progress
28 April 2026Latest RERA Inspection
150 suites and penthousesTotal Units
Project 2545DLD Registration

Construction Snapshot

Mercedes-Benz Places at a Glance

Mercedes-Benz Places is Binghatti's 150-residence tower in Downtown Dubai, developed with Mercedes-Benz and entered in the DLD register as project 2545 on 15 December 2023, the same day construction started. Sixteen and a half months of that build have been measured so far, ending at 65.25% on 28 April 2026, and the six figures below are the registered anchors behind that record. Every point on this page belongs to one building on plot 319, with no sister phase or podium block averaged into it, so the percentage describes a single frame rising toward 341 m.

DLD Project Number

2545

Project Status

Active

Construction Start

15 December 2023

Total Units

150 suites and penthouses

Total Built-Up Area

40,341.18 sq m

Registered Completion Date

31 December 2026 (DLD), handover Q4 2026

Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.

Inspection Record

Mercedes-Benz Places Construction Update Timeline

Three dated inspections make up this record: 26.13% on 23 January 2025, 48.49% on 14 October 2025 and 65.25% on 28 April 2026, a climb of 39.12 points in just over fifteen months. The 0% the register lists before January 2025 carries no inspection date, so the track below starts at the 15 December 2023 construction start instead of at a reading. Each dot marks one inspection, and each table row links its monthly update.

Inspection MonthConstruction ProgressInspection DateFull Update
April 202665.25%28 April 2026View the April 2026 update
October 202548.49%14 October 2025View the October 2025 update
January 202526.13%23 January 2025View the January 2025 update

Pace Analysis

How Fast Mercedes-Benz Places Has Been Built

Two measured intervals sit between the three dated Mercedes-Benz Places readings, and they ran at almost the same speed even though the work listed on site changed between them:

  • Jan 2025 to Oct 2025: superstructure phase, 26.13% to 48.49%About 2.5 points per month
  • Oct 2025 to Apr 2026: envelope, MEP and interior works, 48.49% to 65.25%About 2.6 points per month

Worked per 30-day month, the first interval added 22.36 points over 264 days, about 2.54, and the second added 16.76 points over 196 days, about 2.57. That is a flat curve with no acceleration and no taper, held while the October 2025 and April 2026 reports widened the active work from the frame to the external envelope, MEP and internal finishes. Measured from the 15 December 2023 start to 65.25% on 28 April 2026, the whole build averages about 2.26 points per month, a derived figure that assumes zero on the start date. The registered completion date of 31 December 2026 lay 247 days beyond the April reading with 34.75 points still to certify, which works out at about 4.2 points per month as plain arithmetic, not a forecast: the register records progress rather than dates, and handover is still expected in Q4 2026. For an end user, that 34.75-point gap is the figure to compare against the next inspection; for an investor, two intervals within three hundredths of a point of each other describe a steady contractor rhythm on a single 341 m tower, and the next reading will show whether finishing work changes it.

Get the Next Inspection Figure First

Tell me you are tracking Mercedes-Benz Places and I will send you the next recorded figure and site photos directly, ahead of the page update.

Get the Next Update on WhatsApp

Project Profile

About Mercedes-Benz Places at Downtown Dubai

A percentage only means something next to what it is measuring. The project guide covers the tower this record is tracking toward handover:

Mercedes-Benz Places by Binghatti luxury tower above the Downtown Dubai skyline with Burj Khalifa views at sunset. Presented by Tohid Fetrat.

Mercedes-Benz Places: Binghatti's Downtown Hyper-Tower

Mercedes-Benz Places is Binghatti's hyper-tower in Downtown Dubai, created with Mercedes-Benz, holding 150 suites and penthouses up to a triplex.

View the Mercedes-Benz Places Project Guide

Considering an Entry Before Handover?

With a Q4 2026 handover in view and residences stacked from level 12 up to level 66, which layouts remain open at Mercedes-Benz Places changes between inspection cycles. If this record is what brought you here, ask me for current availability before choosing a level band.

Ask About Remaining Availability on WhatsApp

Stage Record

Mercedes-Benz Places Build Stages, Mapped to the Inspections

Each stage below is pinned to the window it occupied in the Mercedes-Benz Places record, from the 15 December 2023 start through three dated reports, so the current phase reflects what the 28 April 2026 report still listed as in progress rather than a textbook sequence.

Dec 2023 to Jan 2025

Enabling Works and Foundations

From the 15 December 2023 start to the first dated inspection: by 23 January 2025 the enabling and foundation works on plot 319 were reported complete.

Jan 2025 at 26.13%

First Dated Reading

The 23 January 2025 report opened the record at 26.13%, with the structure advancing and MEP and internal works already begun while mobilization continued.

Current PhaseJan 2025 onward, 65.25% at 28 Apr 2026

Superstructure Toward 341 m

Substructure was reported complete by 14 October 2025 at 48.49%, yet the superstructure was still listed as progressing on 28 April 2026 at 65.25%, so the frame remains the current phase.

Oct 2025 onward, in parallel

Envelope, MEP and Interior Finishes

Started before the frame is finished: the 14 October 2025 and 28 April 2026 reports both list external envelope, MEP, external works and internal finishes as progressing.

After 28 Apr 2026 to Q4 2026

Finishing, Commissioning and Handover

The 34.75 points still uncertified after 28 April 2026 lead to handover, expected in Q4 2026, and the registered completion date of 31 December 2026 sits behind it.

What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Mercedes-Benz Places's own record.

Buyer Position

Tracking Your Position at Mercedes-Benz Places

This page is one of four project resources that together cover a Mercedes-Benz Places purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Mercedes Benz Places by Binghatti construction progress on 20 June 2026 showing the rising tower structure within the Downtown Dubai skyline Captured by Tohid Fetrat
You Are Here

Mercedes-Benz Places Construction Updates

This page: every dated Mercedes-Benz Places reading, 26.13% in January 2025 through 65.25% in April 2026.

Mercedes-Benz Places Golden Visa illustration featuring the landmark tower and UAE Golden Visa card representing luxury property investment opportunities in Dubai. Presented by Tohid Fetrat

Mercedes-Benz Places Golden Visa: Suite or Penthouse, Every Type

Binghatti's Mercedes-Benz Places, 150 residences in Downtown Dubai, qualifies at all six types from the Pagoda Suite to triplex penthouse.

Read the Mercedes-Benz Places Golden Visa Guide
Mercedes-Benz Places escrow account illustration featuring the landmark tower with security shield and lock symbols representing protected property investment in Dubai. Presented by Tohid Fetrat

Mercedes-Benz Places Escrow: Binghatti's Downtown Account at Sharjah Islamic Bank

Binghatti's Mercedes-Benz Places in Downtown Dubai is DLD project 2545, 163 units escrowed at Sharjah Islamic Bank, 65.25% certified April 2026.

Verify the Mercedes-Benz Places Escrow Account
Mercedes-Benz Places Snagging Inspection featuring the iconic tower in day and night views with the Downtown Dubai skyline Presented by Tohid Fetrat

Mercedes-Benz Places Snagging for a Branded Hyper-Tower

Mercedes-Benz Places is the residential hyper-tower Binghatti is building with Mercedes-Benz in Downtown Dubai, holding 150 freehold residences.

Book Mercedes-Benz Places Snagging

Approaching Handover

Between 65.25% and Handover: What Mercedes-Benz Places Buyers Should Do Now

The April 2026 inspection left Mercedes-Benz Places 4.75 points short of 70%: once a reading crosses that mark, this record turns from following the build to preparing for handover, and on 28 April 2026 the superstructure was still listed as progressing. Payments tied to construction and the terms of your contract are the work that matters at this reading, and both are easier to settle before the next inspection is published than after it.

First, pay only into the Sharjah Islamic Bank escrow account registered for project 2545; the Mercedes-Benz Places escrow verification guide shows how to confirm the details before each transfer.

Second, set the completion and handover-notice clauses in your SPA beside two dates, the Q4 2026 handover and the registered 31 December 2026 completion, since the register certifies progress, not dates.

Third, follow the record rather than word of mouth: the latest certified detail sits in the Mercedes-Benz Places April 2026 reading in full, and the next dated inspection will show whether the 2.5 to 2.6 point monthly rhythm carried into the finishing works.

Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.

The Wider Picture

Explore Downtown Dubai Structure

A single-tower record reads best against its surroundings. These three pages place the Mercedes-Benz Places build in the Downtown Dubai market, the district around plot 319, and Binghatti's wider portfolio:

Downtown Dubai Properties for Sale featuring Burj Khalifa, Dubai Mall, Dubai Fountain and the iconic skyline of central Dubai. Presented by Tohid Fetrat

Downtown Dubai Properties for Sale

Browse apartments, branded residences and penthouses for sale around Burj Khalifa and The Dubai Mall.

See Downtown Dubai Properties for Sale
Downtown Dubai skyline at sunset featuring Burj Khalifa and Address Sky View Towers — captured and curated by Tohid Fetrat.

Downtown Dubai Community Overview

Read the Downtown Dubai guide: Emaar's city core around Burj Khalifa, The Dubai Mall and Dubai Opera, with prices and returns.

Explore the Downtown Dubai Community
Binghatti luxury towers in Dubai – Bugatti Residences, Mercedes-Benz Places, and Skyblade by Binghatti, representing iconic branded architecture and innovation, presented by Tohid Fetrat.

Binghatti: Record Construction Speed and Branded Towers With Bugatti and Mercedes-Benz

Binghatti has delivered more than 60 projects since 2008, with 27 under development and two master communities across Dubai.

View the Binghatti Developer Profile

Construction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.

FAQs

Mercedes-Benz Places Construction Updates Frequently Asked Questions

Mercedes-Benz Places is an active DLD-registered project (number 2545) whose latest RERA inspection, on 28 April 2026, recorded 65.25% construction progress with the status Main Contract - Progressing. As of September 2026 no later reading appears in the register, and that report still showed the frame, envelope, MEP systems and interior finishes as work in progress. The full record is in the Mercedes-Benz Places inspection timeline above.

The most recent inspection of Mercedes-Benz Places, on 28 April 2026, recorded 65.25%, up 16.76 points from the 48.49% recorded on 14 October 2025, across an interval of 196 days. The site report for that reading is in the Mercedes-Benz Places April 2026 construction report.

Handover of Mercedes-Benz Places is expected in Q4 2026, and its DLD-registered completion date of 31 December 2026 has not passed. That date lay 247 days after the 28 April 2026 inspection that recorded 65.25%, leaving 34.75 points to be certified. The register records construction progress rather than revised dates, so no single reading moves the handover on its own, and this page's record is updated when the next inspection is recorded.

Mercedes-Benz Places comprises 150 residences, suites and penthouses in a single tower, and the DLD record for project 2545 lists a total built area of 40,341.18 sq m. Layouts and sizes for every tier are in the Mercedes-Benz Places residence guide.

Between dated inspections, Mercedes-Benz Places gained 22.36 points from 23 January 2025 to 14 October 2025, about 2.54 points per 30-day month, and 16.76 points from 14 October 2025 to 28 April 2026, about 2.57 points per 30-day month. Measured from the 15 December 2023 start to the 65.25% of 28 April 2026, the derived whole-build average is about 2.26 points per month. These are past measurements, not a forecast; the breakdown is in the Mercedes-Benz Places pace analysis.

Construction of Mercedes-Benz Places started on 15 December 2023, the same date the project was registered with the DLD as number 2545. The first dated inspection, on 23 January 2025, recorded 26.13%; the 0% shown before it in the register carries no inspection date. That first reading has its own page, the Mercedes-Benz Places January 2025 inspection report.

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is keeping the Mercedes-Benz Places construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.