Meraas · Madinat Jumeirah Living
MJL Nourelle Construction Updates
The Ground-Up Build Record of Three Skybridge-Linked Buildings in Madinat Jumeirah Living
MJL Nourelle recorded 3.95% in the DLD register on 14 July 2026, the first dated reading, fixing an enabling and piling baseline for three skybridge-linked buildings.
Construction tracking against RERA inspection data, updated after every recorded inspection.
Direct advisor access. Every message answered personally, never by a call center.
Construction Snapshot
MJL Nourelle at a Glance
MJL Nourelle is the Meraas development of 236 residences in Madinat Jumeirah Living, entered in the Dubai Land Department register as project 4108 on 02 October 2025 and recorded as started on 07 December 2025. Its record is short so far: one dated reading, 3.95% on 14 July 2026, taken 219 days into construction. What separates it from a single-tower build is the layout, three residential buildings sharing one basement and joined by a skybridge, so the opening readings measure common ground works before any one building can be followed on its own.
4108
Active
07 December 2025
236 residential units
32,255.06 sq m
01 March 2029 (DLD)
Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.
Inspection Record
MJL Nourelle Construction Update Timeline
A single dated reading makes up the MJL Nourelle record so far: 3.95% in the DLD project register on 14 July 2026, the day the RERA monitoring report placed the site at Enabling Works (Progressing). The register also lists a previous inspection at 0.02% with no date attached, so it sits on the track below as an unlabelled dot rather than a table row. The registered completion date of 01 March 2029 marks the far end of the record, about three months before the expected June 2029 handover.
| Inspection Month | Construction Progress | Inspection Date | Full Update |
|---|---|---|---|
| July 2026 | 3.95% | 14 July 2026 | View the July 2026 update |
Pace Analysis
How Fast MJL Nourelle Has Been Built
MJL Nourelle has only one dated reading, so there is no inspection-to-inspection velocity to measure yet. What the registered dates do allow is shown below, as arithmetic on 30-day months and not a forecast:
- 07 Dec 2025 start to 14 Jul 2026: average to date, 3.95 points over 219 daysAbout 0.54 points per month
- 14 Jul 2026 to the 01 Mar 2029 registered completion date: 96.05 points over 961 daysAbout 3.00 points per month
- 14 Jul 2026 to the end of the expected June 2029 handover: 96.05 points over 1,082 daysAbout 2.66 points per month
There is no curve to read on this record yet. The 0.02% listed as the previous inspection has no date, so the 3.93 points separating it from the 3.95% of 14 July 2026 cannot be spread across a known period. The 0.54 average is low for a plain reason: the 219 days after the 07 December 2025 start went into enabling works and piling for a basement shared by three buildings, stages that come before any floor rises. The 3.00 and 2.66 figures are simply the averages the remaining 96.05 points would need between July 2026 and the registered completion date or the end of June 2029. For an investor, the first real signal is the next dated reading, which can be measured against 14 July 2026; for an end user, the reading to watch is the one that first records structure above ground, since that is where the shared basement gives way to three separate buildings.
Get the Next Inspection Figure First
Tell me you are tracking MJL Nourelle and I will send you the next recorded figure and site photos directly, ahead of the page update.
Get the Next Update on WhatsAppProject Profile
About MJL Nourelle at Madinat Jumeirah Living
A 3.95% reading on 14 July 2026 says little until it is set against what is planned for the plot. The project guide covers the finished MJL Nourelle that this record is tracking toward:

MJL Nourelle: Three Meraas Buildings Joined by a Skybridge
MJL Nourelle is a Meraas project in Madinat Jumeirah Living of 236 apartments, with sky gardens and infinity pools.
View the MJL Nourelle Project GuideConsidering an Early-Stage Entry?
Buying into MJL Nourelle while the July 2026 record still shows enabling and piling works means choosing from the units still listed long before the three buildings rise. Availability moves between inspection cycles, so ask me for the current list before you decide.
Ask About Remaining Availability on WhatsAppStage Record
MJL Nourelle Build Stages, Mapped to the Inspections
Each stage below is tied to the window it occupies in the MJL Nourelle record, from the 02 October 2025 registration to the 3.95% reading of 14 July 2026, with the stages not yet reached marked as such rather than given invented dates.
Registration and Construction Start
DLD registration as project 4108 on 02 October 2025, followed 66 days later by the recorded construction start on 07 December 2025.
Enabling Works and Piling
By the 14 July 2026 inspection the RERA report put the site at Enabling Works (Progressing) with piling under way, and the DLD register read 3.95%, up from an undated 0.02%.
Shared Basement and Ground Levels
The basement and ground levels that run beneath all three buildings; no register reading after 14 July 2026 is on this record yet to place this stage.
Three Buildings and the Skybridge
Floors rising on Buildings 1, 2 and 3 and the skybridge that joins them; this stage opens on the record when a dated reading first shows structure above ground.
Finishing, Amenities, and Handover
Apartment fit-out, the rooftop gym and skybridge pools, and final works toward the expected June 2029 handover, still 96.05 points away at the 14 July 2026 reading.
What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on MJL Nourelle's own record.
Buyer Position
Tracking Your Position at MJL Nourelle
This page is one of four project resources that together cover a MJL Nourelle purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

MJL Nourelle Construction Updates
This page: every DLD register reading for MJL Nourelle, from the July 2026 baseline to handover.

MJL Nourelle Golden Visa: Five Apartment Types in Madinat Jumeirah Living
MJL Nourelle, Meraas's 236 residential units in Madinat Jumeirah Living, qualifies at all five apartment types from the 1 bedroom.
Read the MJL Nourelle Golden Visa Guide
MJL Nourelle Escrow: Meraas at Madinat Jumeirah Living
MJL Nourelle at Madinat Jumeirah Living escrows 236 units with Mashreq as DLD project 4108, certified 3.95% in July 2026.
Verify the MJL Nourelle Escrow AccountApproaching Handover
Between 3.95% and Handover: What MJL Nourelle Buyers Should Do Now
At 3.95% on 14 July 2026, MJL Nourelle has its whole structure still ahead before the June 2029 handover, so the useful work for buyers now is protecting payments and planning residency rather than preparing for keys. The developer's launch schedule dates its next instalment to December 2026, and the schedule in your own SPA is the one that governs, which is why the three checks below belong before that payment rather than after it.
First, match every instalment to the project 4108 trust account at Mashreq Bank PSC; the MJL Nourelle escrow account page shows how to check it against the DLD record before you transfer.
Second, if residency is part of the plan, use the MJL Nourelle Golden Visa guide to settle how an off-plan purchase at this stage fits your application timing ahead of the June 2029 handover.
Third, follow the record itself: the MJL Nourelle July 2026 construction update holds the full detail of the current reading, and each later month joins the inspection timeline above as it is recorded.
Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.
The Wider Picture
Explore Madinat Jumeirah Living Structure
The MJL Nourelle reading of 3.95% on 14 July 2026 is easier to judge with the community and the developer around it in view. These three pages supply that context:

Madinat Jumeirah Living: MJL Nourelle Residences Opposite Burj Al Arab
Madinat Jumeirah Living, a freehold Meraas apartment community in Umm Suqeim 3, lists MJL Nourelle residences on a 20/55/25 payment plan.
See Madinat Jumeirah Living Properties for Sale
Madinat Jumeirah Living: Low-Rise Freehold Apartments Opposite Burj Al Arab
Madinat Jumeirah Living has low-rise apartments in Umm Suqeim, an air-conditioned footbridge to the Souk and Burj Al Arab views.
Explore the Madinat Jumeirah Living Community
Meraas: Lifestyle Destinations From City Walk to Port de La Mer
Meraas is the name behind City Walk, Bluewaters Island and Madinat Jumeirah Living, from beachfront communities to luxury mixed-use districts.
View the Meraas Developer ProfileConstruction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.
FAQs
MJL Nourelle Construction Updates Frequently Asked Questions
MJL Nourelle, DLD project 4108, is an active project at enabling and piling stage, with the Dubai Land Department register reading 3.95% construction progress as of 14 July 2026. The RERA monitoring report of that date records the stage as Enabling Works (Progressing) and prints no percentage. Every reading so far sits in the inspection timeline above.
Two readings appear in the DLD register for MJL Nourelle: 3.95% on 14 July 2026, and a previous inspection at 0.02% whose date is not shown, a difference of 3.93 points. Only the 14 July 2026 reading is dated, so it forms the single row of this page's timeline; its full detail is in the July 2026 MJL Nourelle construction update.
No measured pace exists yet for MJL Nourelle, because the only earlier reading, 0.02%, is undated. As arithmetic, not a forecast: 3.95% by 14 July 2026 over the 219 days since the 07 December 2025 start averages about 0.54 points per 30-day month, and the remaining 96.05 points work out to about 3.00 points per month to the registered completion date of 01 March 2029, or about 2.66 to the end of June 2029. The working is set out in the pace analysis above.
The DLD register lists 01 March 2029 as the registered completion date for project 4108, a date about three months before the June 2029 handover expected for MJL Nourelle. With 3.95% recorded on 14 July 2026, the registered date has not lapsed, and this record is updated as each new register reading appears.
The RERA project description for MJL Nourelle lists 236 residential units in three buildings: Building 1 with a total of 66 residential units, Building 2 with 81 and Building 3 with 89, each G+10F+R, above shared basement, ground and roof amenity levels described as 2B+2F. Apartment types and layouts are covered in the MJL Nourelle project guide.
The DLD register records the MJL Nourelle construction start as 07 December 2025, 66 days after the project was registered on 02 October 2025. The first dated reading came 219 days after the start: 3.95% on 14 July 2026.

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is keeping the MJL Nourelle construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.