Montura by Emaar in Grand Polo Club and Resort construction updates cover image featuring a project rendering of villas along a landscaped residential street in Dubai - Presented by Tohid Fetrat

Emaar · Grand Polo Club and Resort

Montura at Grand Polo Club & Resort Construction Updates

The Verified Build Record Beside the Polo Fields

Montura reached 11.08% construction at its 05 August 2026 RERA inspection, the first dated reading establishing how Emaar's 179-villa Grand Polo cluster rises from foundations.

Construction tracking against RERA inspection data, updated after every recorded inspection.

Direct advisor access. Every message answered personally, never by a call center.

11.08%Construction Progress
05 August 2026Latest RERA Inspection
179 villasTotal Units
Project 3700DLD Registration

Construction Snapshot

Montura at Grand Polo Club & Resort at a Glance

Montura is Emaar's 179-villa release wrapped around the polo fields and clubhouse that sit at the centre of Grand Polo Club and Resort, on plot 2920 in Dubai Investment Park Second. Just under seventeen months separate its 13 March 2025 construction start from the 11.08% recorded at the August 2026 inspection, and the figures below are the DLD-registered anchors behind that reading. Because every home here is a G+1+roof footprint rather than a floor plate in a tower, a single percentage has to carry foundations, structure, and street infrastructure moving in parallel across the whole cluster.

DLD Project Number

3700

Project Status

Active

Construction Start

13 March 2025

Total Units

179 villas

Total Built-Up Area

103,128.81 sq m

Registered Completion Date

30 June 2029

Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.

Inspection Record

Montura at Grand Polo Club & Resort Construction Update Timeline

One dated inspection anchors this record so far: 11.08% verified on 05 August 2026, sixteen months and three weeks after work started on the plots. The register also carries an earlier Montura reading of 2.88% with no date published against it, which is why it is described here but left off the track below. Only readings that carry a date are plotted, and every future inspection is added to this table as it lands.

Inspection MonthConstruction ProgressInspection DateFull Update
August 202611.08%05 August 2026View the August 2026 update

Pace Analysis

How Fast Montura at Grand Polo Club & Resort Has Been Built

With one dated inspection on the record, Montura's pace cannot yet be measured between readings. What the register does support is a rate derived from groundbreaking and a rate implied by the completion date it carries:

  • 13 Mar 2025 start to 05 Aug 2026 inspection: ground to 11.08%About 0.7 points per month, derived
  • 05 Aug 2026 to the 30 Jun 2029 registered completion: 11.08% to 100%About 2.6 points per month, schedule-implied

Two things follow from that arithmetic. The first is that 0.7 points per month is a starting condition rather than a forecast: excavation, service corridors, and enabling works consume programme time while certifying very little percentage, which is why the opening stretch of a villa cluster reads slower than the middle of one. The second is that the 2.6 points per month implied by the 30 June 2029 registered date is close to four times the rate recorded so far, and that step up has to come from repetition, because 179 near-identical villa shells certify far more quickly once the first structural cycle is proven on the plots. The 8.20 point gain from the register's undated 2.88% reading confirms movement but cannot be turned into a velocity, since no interval sits behind it. For a buyer, the practical test is the January 2027 instalment tied to 30% completion: it sits 18.92 points above the current figure, and the next two or three readings will show whether the step up is happening on the ground or on paper.

Get the Next Inspection Figure First

Tell me you are tracking Montura at Grand Polo Club & Resort and I will send you the next recorded figure and site photos directly, ahead of the page update.

Get the Next Update on WhatsApp

Project Profile

About Montura at Grand Polo Club & Resort at Grand Polo Dubai

A percentage this early is only meaningful against what it is building toward. The project guide covers the villas, plot positions, and masterplan setting behind the 11.08% reading:

Montura by Emaar in Grand Polo Club and Resort two-storey villa front exterior with broad glazing landscaped garden and covered parking in Dubai - Presented by Tohid Fetrat

Montura at Grand Polo Club & Resort: Villas Around Three Polo Fields

Montura at Grand Polo Club & Resort is Emaar's villa cluster of 179 homes around three polo fields and the clubhouse.

View the Montura at Grand Polo Club & Resort Project Guide

Considering an Early-Stage Entry?

Montura is listed with limited units available, and plot position is the part of an early-stage purchase that cannot be changed later. If the record on this page is what brought you here, ask me what is still open while the choice of position is still yours to make.

Ask About Remaining Availability on WhatsApp

Stage Record

Montura at Grand Polo Club & Resort Build Stages, Mapped to the Inspections

Each stage below is tied to the window it occupies in Montura's own record and instalment schedule rather than to a generic construction sequence, so you can see where the 11.08% reading sits and what has to certify next.

Mar 2025 to mid 2026

Site Activation and Enabling Works

From the 13 March 2025 construction start, registered with the DLD on 22 April 2025: mobilization across plot 2920 and enabling works ahead of the villa foundations.

Current PhaseAug 2026 at 11.08%

Foundations, Structure, and Infrastructure

The 05 August 2026 reading found mobilization, enabling, foundation, structure, and infrastructure all in motion across the villa plots, none of them yet certified complete.

Scheduled to Jul 2027, 30% and 50% milestones

Villa Superstructure Across the Plots

G+1+roof shells repeating plot by plot toward the 30% completion milestone dated January 2027 and the 50% milestone dated July 2027 on the Emaar instalment schedule.

Scheduled Jul 2027 to Jul 2028, 80% and 90% milestones

Facades, Fit-Out, and Community Landscaping

Facade, mechanical and electrical, and interior packages alongside the forest walk, floral garden, and street landscaping, spanning the 80% milestone dated March 2028 and 90% dated July 2028.

Scheduled to 30 Jun 2029

Finishing, Commissioning, and Delivery

Final finishes, systems commissioning, and community completion works toward the DLD-registered date of 30 June 2029 and the Q2 2029 handover window.

What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Montura at Grand Polo Club & Resort's own record.

Buyer Position

Tracking Your Position at Montura at Grand Polo Club & Resort

This page is one of four project resources that together cover a Montura at Grand Polo Club & Resort purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Montura by Emaar in Grand Polo Club and Resort construction updates cover image featuring a project rendering of villas along a landscaped residential street in Dubai - Presented by Tohid Fetrat
You Are Here

Montura at Grand Polo Club & Resort Construction Updates

This page: every dated RERA reading for Montura at Grand Polo, groundbreaking through to handover.

Montura by Emaar in Grand Polo Club and Resort Golden Visa concept with a gold card above a villa rendering with a private pool and landscaped garden in Dubai - Presented by Tohid Fetrat

Montura at Grand Polo Club & Resort Golden Visa: The Question Settled

Every current release at Montura at Grand Polo Club & Resort, the 4 and 5 bedroom villa types, qualifies individually.

Read the Montura at Grand Polo Club & Resort Golden Visa Guide
Montura by Emaar in Grand Polo Club and Resort escrow account protection concept with shield and padlock icons above a villa rendering and landscaped outdoor seating in Dubai - Presented by Tohid Fetrat

The First Montura at Grand Polo Club & Resort Escrow Account

Montura at Grand Polo Club & Resort pays Abu Dhabi Commercial Bank escrow, DLD project 3700, certified 11.08% in August 2026.

Verify the Montura at Grand Polo Club & Resort Escrow Account

Approaching Handover

Between 11.08% and Handover: What Montura at Grand Polo Club & Resort Buyers Should Do Now

At 11.08% the work that protects a Montura buyer is administrative rather than physical. The percentage is still low, but the payment machinery keyed to it is already running: instalment five falls due in January 2027 against 30% certified completion, a milestone 18.92 points beyond today's figure. That puts the three checks below in the months before the milestone lands, not after it.

First, confirm the destination of your funds. The DLD entry for project 3700 puts the escrow with Abu Dhabi Commercial Bank under developer Emaar Development P.J.S.C., and the Montura at Grand Polo escrow account page sets out how to run that verification yourself.

Second, line your sale and purchase agreement up against certified milestones rather than calendar dates, because every payment after January 2027 is certified at the 50%, 80%, 90%, and finally 100% marks. The Montura at Grand Polo payment plan lays out the full nine-instalment structure.

Third, if the purchase is meant to support residency, settle eligibility now rather than near handover. The Montura at Grand Polo Golden Visa eligibility guide covers how an off-plan villa purchase is assessed while the title deed is still years away.

Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.

The Wider Picture

Explore Grand Polo Dubai Structure

A build record is only half the picture; the other half is what is rising around it. These three pages put Montura's 11.08% in its masterplan, community, and developer context:

Grand Polo Villas and Townhouses for Sale luxury villa with private pool and outdoor lounge at Grand Polo Club and Resort Dubai Presented by Tohid Fetrat

Grand Polo Dubai Properties for Sale

Browse villas and townhouses for sale at Grand Polo Club & Resort, comparing Equiterra, Selvara and Chevalia.

See Grand Polo Dubai Properties for Sale
Grand Polo Club and Resort by Emaar clubhouse overlooking the polo fields with palm lined landscape in Dubai Presented by Tohid Fetrat

Grand Polo Dubai Community Overview

Read the Grand Polo Club & Resort guide: Emaar's 60 million sq ft equestrian estate community of villas and townhouses.

Explore the Grand Polo Dubai Community
Emaar Properties developer showcasing Downtown Dubai skyline with Burj Khalifa and surrounding residential and commercial towers at dusk Presented by Tohid Fetrat

Emaar Properties: Burj Khalifa, Downtown Dubai and Twenty Master Communities

Emaar, founded in 1997, built Burj Khalifa and Downtown Dubai and has delivered over 85,000 homes across twenty master communities.

View the Emaar Properties Developer Profile

Construction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.

FAQs

Montura at Grand Polo Club & Resort Construction Updates Frequently Asked Questions

Montura is an active DLD-registered project (number 3700) in its foundation, structure, and infrastructure phase, recorded at 11.08% at the RERA inspection of 05 August 2026. The full record is in the inspection timeline above.

The 05 August 2026 inspection recorded 11.08% construction progress, 8.20 points above the register's previous Montura reading of 2.88%. That earlier reading carries no published date, so the gain is documented while the interval behind it is not. The site report for the cycle is in the August 2026 construction update.

From the 13 March 2025 construction start to the 05 August 2026 inspection, the record works out at roughly 0.7 percentage points per month, a figure derived from the start date rather than measured between two dated readings. Closing the remaining 88.92 points by the registered completion date of 30 June 2029 implies about 2.6 points per month. The breakdown is in the pace analysis above.

The DLD-registered completion date for project 3700 is 30 June 2029, which places handover inside Q2 2029. Measured from the 11.08% verified on 05 August 2026, that leaves 88.92 percentage points still to certify. This page's record is updated as each RERA inspection is published.

Montura is a 179-villa release of four and five bedroom homes in the G+1+roof format. The DLD register for project 3700 records a total built-up area of 103,128.81 sq m across the development.

Construction started on 13 March 2025, with DLD project registration recorded on 22 April 2025. The first dated reading on this page's record is the 11.08% verified on 05 August 2026, roughly seventeen months later.

The inspection notes dated 05 August 2026 list five work packages in motion across the villa plots, none of them recorded as complete at 11.08%: mobilization, enabling, foundations, structure, and infrastructure. Several packages moving together is the normal reading for a low-rise cluster where 179 plots advance in parallel rather than one structure rising floor by floor.

Emaar prices the Montura instalments against certified construction percentages rather than calendar dates alone: 30% completion is dated January 2027, 50% July 2027, 80% March 2028, 90% July 2028, and 100% June 2029. Against the 11.08% verified on 05 August 2026, the first of those milestones sits 18.92 points ahead. The bank releasing funds against them is identified on the Montura escrow account verification page.

The cluster sits on plot 2920 within Dubai Investment Park Second, along the southern side of the Grand Polo masterplan where villa streets bend around the polo fields, stables, and clubhouse. Three releases carry the Montura name around that green core, and the Chevalia Estate and Chevalia Fields clusters sit beside them.

The RERA project description for number 3700 records a residential development of villas in the G+1+roof format, meaning a ground floor, one upper floor, and a roof level on each plot. Layouts and plot positions sit in the Montura at Grand Polo villa guide.

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is keeping the Montura at Grand Polo Club & Resort construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.

Ask your question, get your answer. No obligation and no follow-up unless you ask for it.

WhatsApp +971543443597
Get the Latest Status