Emaar · Dubai Creek Harbour
Moor at Dubai Creek Harbour Construction Updates
Four Creek Beach Buildings, One Shared Registration, a Finished Build Record
Moor's shared DLD registration recorded 100% at its 04 November 2025 inspection, leaving snagging inside four Creek Beach buildings as the last gap before November 2026 handover.
Construction tracking against RERA inspection data, updated after every recorded inspection.
Direct advisor access. Every message answered personally, never by a call center.
Construction Snapshot
Moor at Dubai Creek Harbour at a Glance
Moor at Dubai Creek Harbour is Emaar's group of four mid-rise buildings holding 198 apartments in the Creek Beach district, and it has no DLD project number of its own. It is registered under project 2555, Creek Beach - Canopy - Moor, together with the neighbouring Canopy buildings, so the progress, status and dates below describe that combined registration, while the apartment count is Moor's alone. The registration and its recorded start both predate Moor's July 2024 launch by more than a year, which is why Moor's record opens before Moor itself went on sale.
2555 (Creek Beach - Canopy - Moor)
Finished (DLD, 04 November 2025)
27 May 2023
198 apartments in four buildings
309,598.95 sq m
30 November 2026 (DLD)
Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.
Inspection Record
Moor at Dubai Creek Harbour Construction Update Timeline
Moor's record carries a single dated inspection, and it is the closing one: 100% for project 2555 on 04 November 2025, seventeen points above the 83% of a previous inspection that the register leaves without a date. That is why the track below holds one dot sitting at the end of the bar, and why the table has one row, linked to the November 2025 update that covers the reading in full.
| Inspection Month | Construction Progress | Inspection Date | Full Update |
|---|---|---|---|
| November 2025 | 100% | 04 November 2025 | View the November 2025 update |
Pace Analysis
How Fast Moor at Dubai Creek Harbour Has Been Built
A build rate needs two dated readings, and Moor's register supplies one: 100% on 04 November 2025, after an 83% previous inspection with no date attached. These are the measurable intervals the record does hold:
- Previous inspection (undated) to 04 Nov 2025: 83% to 100%+17 points, no monthly rate
- 29 Aug 2025 to 22 Oct 2025: DCD approval, LPG approval, then the building completion certificate54 days for three approvals
- Launch calendar vs register: 100% instalment dated Nov 2026, 100% recorded 04 Nov 2025About 12 months apart
- 04 Nov 2025 to 23 Sep 2026: age of the latest reading when this page was prepared323 days old
Taken together, these intervals describe a record defined by its ending rather than its curve. The closing 17 points cannot be spread across months because nothing in the register says when the 83% was measured, so any velocity quoted for Moor would be a guess. What the dates do fix is the order of the finish for registration 2555: civil defence approval on 29 August 2025, the LPG approval 18 days later, the DDA building completion certificate 36 days after that, and the 100% inspection 13 days after the certificate. Set that beside Moor's July 2024 launch calendar, which placed its 70% instalment in November 2025, the same month the register recorded 100%. For an owner-occupier the build question is settled and the handover question is not; for an investor, the months between a finished registration and the November 2026 handover are spent on snagging and handover paperwork, not on structural risk.
Get the Next Inspection Figure First
Tell me you are tracking Moor at Dubai Creek Harbour and I will send you the next recorded figure and site photos directly, ahead of the page update.
Get the Next Update on WhatsAppProject Profile
About Moor at Dubai Creek Harbour
A 100% reading on four mid-rise buildings of 198 apartments is a different proposition from the same figure on a single tower, and the project guide sets out exactly what those apartments are:

Moor at Dubai Creek Harbour, Marketed as Moor at Creek Beach
Moor at Dubai Creek Harbour is an Emaar development of 198 apartments with one to three bedrooms in Creek Beach.
View the Moor at Dubai Creek Harbour Project GuideConsidering a Near-Handover Entry?
The Moor apartments still unsold are held by Emaar and priced unit by unit, and that stock shrinks each time one sells. With construction recorded at 100% on 04 November 2025, you would be choosing a finished apartment ahead of the November 2026 handover, so ask me what is available today.
Ask About Remaining Availability on WhatsAppStage Record
Moor at Dubai Creek Harbour Build Stages, Mapped to the Inspections
With only one dated inspection, Moor's stages are anchored to the register, launch and approval dates instead of a run of percentages: from the 24 March 2023 registration of project 2555 to the 100% reading of 04 November 2025, each stage below sits in the window it actually occupied.
Registration and Site Start for Project 2555
Project 2555 was registered on 24 March 2023 with a recorded construction start of 27 May 2023, both dates belonging to the combined registration rather than to Moor alone.
Moor Launches Into a Live Registration
Emaar opened Moor to buyers in July 2024 with a 10% down payment, releasing 198 apartments in four buildings some fourteen months after registration 2555 recorded its start.
Four Mid-Rise Structures
Moor's buildings rose to G+M+5, G+M+6, G+M+7 and G+M+8 in this window. The register shows 83% at the previous inspection but gives it no date, so the window has no fixed end.
Civil Defence, LPG, and Completion Certificate
The independent progress report records the DCD approval on 29 August 2025, the LPG approval from DCD on 16 September 2025 and the DDA building completion certificate on 22 October 2025.
Snagging, Handover Notices, and Keys
Recorded at 100% on 04 November 2025 with meters connected and snagging works ongoing; handover is scheduled for November 2026, the month of the 30 November 2026 registered completion.
What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Moor at Dubai Creek Harbour's own record.
Buyer Position
Tracking Your Position at Moor at Dubai Creek Harbour
This page is one of four project resources that together cover a Moor at Dubai Creek Harbour purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Moor at Dubai Creek Harbour Construction Updates
This page: Moor's construction record under DLD project 2555, from registration to the November 2026 handover.

Moor at Dubai Creek Harbour Golden Visa in the Creek Beach District
Moor at Dubai Creek Harbour, 198 Emaar apartments under DLD project 2555, qualifies at 2 and 3 bedrooms only.
Read the Moor at Dubai Creek Harbour Golden Visa Guide
Moor at Dubai Creek Harbour Escrow: A Mashreq Account at 100%
Moor at Dubai Creek Harbour reached 100% certified in November 2025, with 444 units escrowed at Mashreq under DLD project 2555.
Verify the Moor at Dubai Creek Harbour Escrow Account
Moor at Dubai Creek Harbour Snagging in Four Mid-Rise Buildings
Moor at Dubai Creek Harbour is Emaar's collection of 198 freehold apartments, one to three bedrooms, in the Creek Beach district.
Book Moor at Dubai Creek Harbour SnaggingApproaching Handover
Between 100% and Handover: What Moor at Dubai Creek Harbour Buyers Should Do Now
Nothing structural stands between Moor's 100% reading of 04 November 2025 and its November 2026 handover; the independent report names snagging works as the only item still in progress, and the next event most owners will see is Emaar's handover notice. The period that notice allows is set by each buyer's SPA and can be short, so the three steps below are worth finishing before it arrives rather than after.
First, have your apartment independently inspected so defects are logged before you accept it; the Moor snagging inspection page sets out timing and scope for a building where snagging was still recorded as ongoing at the 100% inspection.
Second, before any remaining payment, check the trust account registered to project 2555 on the Moor escrow account page and reread your SPA's instalment clause: the launch schedule tied its 80%, 90% and 100% instalments to construction triggers but dated them February 2026, May 2026 and November 2026, and with 100% recorded on 04 November 2025 triggers and dates no longer agree, so your own SPA decides which one governs.
Third, if residency is part of the plan, settle eligibility before handover through the Moor at Dubai Creek Harbour Golden Visa guide: the two and three bedroom apartments, from AED 2.50M ≈ USD 681K, clear the property threshold on their own, while the one bedroom from AED 1.68M ≈ USD 457K does not.
Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.
The Wider Picture
Explore Dubai Creek Harbour Structure
Moor finished inside a master community that is still being built out around Creek Beach. These three pages set its record against the market, the community and the developer:

Dubai Creek Harbour Properties for Sale
Browse waterfront apartments, branded residences and penthouses for sale in Dubai Creek Harbour.
See Dubai Creek Harbour Properties for Sale
Dubai Creek Harbour: Emaar's Waterfront City With a Marina and Urban Beach
Dubai Creek Harbour is Emaar's waterfront city between Downtown Dubai and the Creek, planned for 48,500 homes with skyline views.
Explore the Dubai Creek Harbour Community
Emaar Properties: Burj Khalifa, Downtown Dubai and Twenty Master Communities
Emaar, founded in 1997, built Burj Khalifa and Downtown Dubai and has delivered over 85,000 homes across twenty master communities.
View the Emaar Properties Developer ProfileConstruction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.
FAQs
Moor at Dubai Creek Harbour Construction Updates Frequently Asked Questions
Construction at Moor at Dubai Creek Harbour is recorded complete: the DLD register showed 100% for project 2555 at the inspection of 04 November 2025, with the project status Finished, and handover is scheduled for November 2026. That reading was 323 days old on 23 September 2026, so re-verify project 2555 on Dubai REST before relying on it. The full record is in the Moor inspection timeline above.
Moor's inspection history on the DLD register holds one dated reading: 100% for project 2555 on 04 November 2025, up 17 points from 83% at the previous inspection. The register gives no date for that 83% reading, so the 17-point rise cannot be turned into a monthly pace and there is no second dated point to plot. The independent progress report for the same 04 November 2025 visit records the site's construction work as finished, with a progress status of Completed.
Moor's registered completion date on the DLD register is 30 November 2026, the same month as the scheduled November 2026 handover, and on 23 September 2026 it was still 68 days away, so it had not lapsed. Construction for project 2555 had been recorded at 100% on 04 November 2025, so the months between that reading and the registered date are taken up by snagging and by handover notices under each buyer's SPA rather than by building work.
Moor at Dubai Creek Harbour has 198 apartments in four mid-rise buildings. The independent progress report of 04 November 2025 lists Building 1 at G+M+8 with 58 units, Building 2 at G+M+5 with 38, Building 3 at G+M+6 with 48 and Building 4 at G+M+7 with 54. The register's unit and area totals for project 2555 include the neighbouring Canopy buildings, so they are not Moor figures, and this page publishes no built-up area for Moor.
One reading covers both because Canopy and Moor were registered together as DLD project 2555, Creek Beach - Canopy - Moor, rather than as two separate projects. The register therefore holds a single progress figure, status, date set and trust account for the pair, and the 100% of 04 November 2025 describes the whole registration. Moor's own figures on this page, 198 apartments in four buildings, come from the Moor lines of the independent progress report rather than from the register totals.
The independent progress report of 04 November 2025 records three approvals for project 2555, the registration that covers Moor: a Dubai Civil Defence (DCD) approval dated 29 August 2025, an LPG approval from DCD dated 16 September 2025 and a building completion certificate from DDA dated 22 October 2025. The 100% inspection followed 13 days after that certificate, and the same report notes water and electricity meters connected and snagging works ongoing.

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is keeping the Moor at Dubai Creek Harbour construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.
Ask your question, get your answer. No obligation and no follow-up unless you ask for it.