Morocco 2 at DAMAC Lagoons by DAMAC in DAMAC Lagoons construction updates cover image featuring a project rendering of a modern villa with balconies, a swimming pool and palms in Dubai - Presented by Tohid Fetrat

DAMAC · DAMAC Lagoons

Morocco 2 at DAMAC Lagoons Construction Updates

The DLD Register Record of 554 Moroccan-Inspired Villas and Townhouses Off Hessa Street

Morocco 2 reached 65.34% on the DLD register at its 17 July 2026 inspection, a climb in which the villa and townhouse superstructure was still progressing.

Construction tracking against RERA inspection data, updated after every recorded inspection.

Direct advisor access. Every message answered personally, never by a call center.

65.34%Construction Progress
17 July 2026Latest RERA Inspection
554 villas and townhousesTotal Units
Project 2690DLD Registration

Construction Snapshot

Morocco 2 at DAMAC Lagoons at a Glance

Morocco 2 at DAMAC Lagoons by DAMAC is a cluster of 554 villas and townhouses recorded on the Dubai Land Department register under project number 2690, and that register stood at 65.34% when RERA inspected the site on 17 July 2026. Almost three years separate that reading from the 29 August 2023 construction start, yet it is the only dated inspection on file, so the cards below are the fixed anchors this record rests on. Read the percentage as one average across 554 low-rise homes, not as the state of any single villa or townhouse.

DLD Project Number

2690

Project Status

Active

Construction Start

29 August 2023

Total Units

554 villas and townhouses

Total Built-Up Area

144,545.26 sq m

Registered Completion Date

Q4 2026

Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.

Inspection Record

Morocco 2 at DAMAC Lagoons Construction Update Timeline

This record is short: one dated inspection, 65.34% on 17 July 2026, and an earlier 59.83% that the DLD register lists as the previous inspection but without a date, so it appears on the track below as a dot with no month and has no row in the table. The dated anchors before them are registration on 14 July 2023 and the 29 August 2023 construction start, where the track begins; the July 2026 row links the full monthly update.

Inspection MonthConstruction ProgressInspection DateFull Update
July 202665.34%17 July 2026View the July 2026 update

Pace Analysis

How Fast Morocco 2 at DAMAC Lagoons Has Been Built

Only one reading on the Morocco 2 register carries a date, so no pace between two inspections can be measured yet. What the record does support is arithmetic against fixed dates, shown below and labelled as arithmetic, not a forecast:

  • 29 Aug 2023 to 17 Jul 2026: whole-build average from construction start to 65.34% over 1,053 days (arithmetic, not a forecast)About 1.86 points per month
  • 17 Jul 2026 to 31-12-2026: the remaining 34.66 points over 167 days to the close of the stated Q4 2026 handover quarter (arithmetic, not a forecast)About 6.23 points per month

Read together, the two figures describe the shape of the work still to come rather than a verdict on it. The 1.86 average folds in the enabling and foundation works that the RERA report of 17 July 2026 listed as substantially completed, along with a superstructure it still recorded as progressing; the 6.23 figure is simply what the 34.66 remaining register points would require if 100% were reached by the last day of Q4 2026. A cluster of 554 villas and townhouses need not climb at an even rate: in July the report had external works, finishes, the envelope and MEP all moving at different stages in parallel, and the weighting the register gives each package is not published. The undated 59.83% reading adds direction but no rate. For an end user planning a move, the useful step is written confirmation of the handover timetable from DAMAC; for an investor weighing an entry or exit, the next dated reading will give this record its first measured pace, and setting it against 6.23 is the clearest test of how the register and the Q4 2026 quarter line up.

Get the Next Inspection Figure First

Tell me you are tracking Morocco 2 at DAMAC Lagoons and I will send you the next recorded figure and site photos directly, ahead of the page update.

Get the Next Update on WhatsApp

Project Profile

About Morocco 2 at DAMAC Lagoons

A register percentage only means something next to what is being built. The project guide covers the 554 townhouses and villas this record follows toward the Q4 2026 handover:

Morocco 2 at DAMAC Lagoons by DAMAC in DAMAC Lagoons project rendering of modern two-storey villas along a landscaped residential street in Dubai - Presented by Tohid Fetrat

Morocco 2 at DAMAC Lagoons, the Tranquility Hub

Morocco 2 at DAMAC Lagoons is the second phase of DAMAC's Morocco cluster, 554 townhouses and villas around a wellness theme.

View the Morocco 2 at DAMAC Lagoons Project Guide

Considering a Late-Stage Entry?

Limited units remain at Morocco 2, and the mix of what is on offer keeps moving as the build heads toward its Q4 2026 handover. If this record is what brought you here, ask me for current availability before the remaining choice narrows further.

Ask About Remaining Availability on WhatsApp

Stage Record

Morocco 2 at DAMAC Lagoons Build Stages, Mapped to the Inspections

Each stage below is pinned to the dates and RERA notes in Morocco 2's own record rather than to a generic build sequence. Because a single dated inspection covers 554 homes, several stages were running side by side on 17 July 2026, and the windows overlap accordingly.

Jul 2023 to Aug 2023

Registration and Construction Start

DLD registration of project 2690 on 14 July 2023, followed 46 days later by the 29 August 2023 construction start, the point where the track above begins.

From Aug 2023, substantially completed by Jul 2026

Enabling Works and Foundations

Site enabling and the foundations beneath the villas and townhouses, both recorded as substantially completed in the RERA report of 17 July 2026.

From Aug 2023, still progressing in Jul 2026

Substructure and Superstructure

The building frames for 554 homes, described by the RERA report as (B+G+1+R) and (G+1+R) villas, were at an advanced stage but still progressing on 17 July 2026.

Current PhaseJul 2026, 65.34% at last reading

Envelope, MEP, and Internal Works

On 17 July 2026 internal works were at an advanced stage while MEP, internal finishes and the external envelope each sat at different stages, overlapping frame work still under way.

Jul 2026 to the Q4 2026 handover

External Works, Infrastructure, and Handover

External works and infrastructure were progressing in July 2026; the remaining 34.66 register points lead to 100% and the handover expected in Q4 2026.

What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Morocco 2 at DAMAC Lagoons's own record.

Buyer Position

Tracking Your Position at Morocco 2 at DAMAC Lagoons

This page is one of four project resources that together cover a Morocco 2 at DAMAC Lagoons purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Morocco 2 at DAMAC Lagoons by DAMAC in DAMAC Lagoons construction updates cover image featuring a project rendering of a modern villa with balconies, a swimming pool and palms in Dubai - Presented by Tohid Fetrat
You Are Here

Morocco 2 at DAMAC Lagoons Construction Updates

This page: the DLD register record for Morocco 2 from its August 2023 start to handover.

Morocco 2 at DAMAC Lagoons by DAMAC in DAMAC Lagoons Golden Visa concept graphic featuring a gold card above a modern villa and landscaped residential street in Dubai - Presented by Tohid Fetrat

Morocco 2 at DAMAC Lagoons Golden Visa: One Qualifying Purchase

Morocco 2 at DAMAC Lagoons, 554 villas and townhouses, clears the threshold at all four home types on a single purchase.

Read the Morocco 2 at DAMAC Lagoons Golden Visa Guide
Morocco 2 at DAMAC Lagoons by DAMAC in DAMAC Lagoons escrow account concept graphic with a shield and padlock above a rendered modern villa and swimming pool in Dubai - Presented by Tohid Fetrat

Morocco 2 at DAMAC Lagoons: The Second Morocco Escrow Account

Morocco 2 at DAMAC Lagoons pays Emirates NBD escrow as DLD project 2690, its 554 units 65.34% certified July 2026.

Verify the Morocco 2 at DAMAC Lagoons Escrow Account
Morocco 2 at DAMAC Lagoons by DAMAC in DAMAC Lagoons snagging inspection page cover featuring a rendered bedroom with an upholstered bed, decorative wall and glazed balcony in Dubai - Presented by Tohid Fetrat

Morocco 2 at DAMAC Lagoons Snagging Along Hessa Street

Morocco 2 at DAMAC Lagoons brings 554 DAMAC villas and townhouses in four home types to the master community.

Book Morocco 2 at DAMAC Lagoons Snagging

Approaching Handover

Between 65.34% and Handover: What Morocco 2 at DAMAC Lagoons Buyers Should Do Now

The 17 July 2026 reading left Morocco 2 just under the 70% mark that DAMAC's published launch payment plan uses for its first construction-linked instalment, with further instalments at 80% and 90% and 20% due on completion; the schedule a buyer signs is the one confirmed in the SPA, and later buyers' terms can differ. With handover expected in Q4 2026, those milestone calls and the handover notice your SPA sets can arrive close together, so the three steps below belong in the coming weeks, not on the day a notice lands.

First, match each construction-linked call against the register before paying: the launch plan ties 2% to 70% completion, 2% to 80% and 1% to 90%, and the Morocco 2 at DAMAC Lagoons escrow account page explains how those payments are held for project 2690.

Second, follow the dated readings rather than the headline figure alone; the Morocco 2 July 2026 RERA inspection notes explain the 65.34% reading, and the next dated reading will add the first measured pace to this record.

Third, line up an independent inspection of your villa or townhouse ahead of the Q4 2026 handover; the Morocco 2 at DAMAC Lagoons snagging page covers timing around the handover appointment and what to check.

Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.

The Wider Picture

Explore DAMAC Lagoons Structure

One cluster's register reading sits inside a much larger build-out. These three pages set Morocco 2's July 2026 progress against the DAMAC Lagoons market, the master community around it, and the developer delivering it:

DAMAC Lagoons properties for sale in Dubai including villas, townhouses and apartments within landscaped residential surroundings, Presented by Tohid Fetrat

DAMAC Lagoons: Mediterranean-Themed Villas, Townhouses, Apartments and Offices

DAMAC Lagoons sits opposite DAMAC Hills in Dubailand, with 11 themed clusters and 3 projects of villas, townhouses, apartments and offices.

See DAMAC Lagoons Properties for Sale
DAMAC Lagoons master community with crystal lagoon waterfront villas sandy beaches palm trees and leisure amenities in Dubai Presented by Tohid Fetrat

DAMAC Lagoons Community Overview

Read the DAMAC Lagoons guide: Mediterranean-themed clusters and crystal lagoons across a 45 million sq ft waterfront masterplan.

Explore the DAMAC Lagoons Community
DAMAC Properties development overlooking Dubai skyline and waterfront with modern architecture at sunset in Dubai Presented by Tohid Fetrat

DAMAC Properties: Lagoon Communities, Golf Villas and Branded Collaborations

Founded in 2002, DAMAC has delivered 48,000 homes and is known for large-scale master communities, luxury residential projects and branded collaborations.

View the DAMAC Developer Profile

Construction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.

FAQs

Morocco 2 at DAMAC Lagoons Construction Updates Frequently Asked Questions

Morocco 2 at DAMAC Lagoons stood at 65.34% on the DLD register after the RERA inspection of 17 July 2026, an active project under number 2690 whose RERA report of the same date gave its progress status as Main Contract, Progressing. That reading was 98 days old when this page was built on 23 October 2026; the full record is in the Morocco 2 inspection timeline above.

Progress at Morocco 2 at DAMAC Lagoons is tracked through the Dubai Land Department project register for project 2690, which posted 65.34% after the RERA inspection of 17 July 2026, 5.51 points above the previous 59.83% reading that the register lists without a date. Each dated reading gets its own row in the timeline and its own monthly page, beginning with the Morocco 2 July 2026 construction update.

No registered completion date for Morocco 2 at DAMAC Lagoons appears in the records reviewed for this page. The Dubai REST project screens reviewed for project 2690 show the registration date of 14 July 2023 and the start date of 29 August 2023, and the RERA report of 17 July 2026 prints no completion date, so none is shown and none is estimated. The handover expected for Morocco 2 is Q4 2026; to look for a registered date, search Dubai REST for Damac Lagoons - Morocco 2 or project 2690, and read the completion clause in your own SPA.

Morocco 2 at DAMAC Lagoons comprises 554 homes, the count shown on the DLD register for project 2690 and on the RERA report of 17 July 2026. That report describes them as (B+G+1+R) and (G+1+R) villas, meaning basement, ground, first and roof levels or ground, first and roof levels, built with a concrete structure and blockwork and carrying internal and external finishes. The homes offered are 4 and 5 bedroom townhouses and 6 and 7 bedroom villas; no labelled built-up area figure appears in the records reviewed, so none is quoted.

Arithmetic on the Morocco 2 at DAMAC Lagoons record gives a whole-build average of about 1.86 points per month: 65.34% over the 1,053 days from the 29 August 2023 start to the 17 July 2026 reading. Reaching 100% by the end of Q4 2026 would take about 6.23 points per month over the remaining 167 days. Both figures are arithmetic, not a forecast; the next dated reading will allow the first measured pace, and the working is set out in the Morocco 2 pace analysis above.

Morocco 2 at DAMAC Lagoons entered the Dubai Land Department register as project 2690 on 14 July 2023, and work on site followed 46 days later, with construction starting on 29 August 2023. The only dated inspection on its record, 65.34% on 17 July 2026, came 1,053 days after that start, so the earlier years appear on this page as dated milestones and stage windows rather than as inspection rows.

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is keeping the Morocco 2 at DAMAC Lagoons construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.