Mykonos at DAMAC Lagoons Construction Updates
The DLD Register Record of 575 Townhouses off Hessa Street
Mykonos at DAMAC Lagoons read 81.06% on the DLD register on 30 September 2026, leaving townhouse finishes, MEP and external works before the estimated Q2 2027 handover.
Construction tracking against RERA inspection data, updated after every recorded inspection.
Direct advisor access. Every message answered personally, never by a call center.
Construction Snapshot
Mykonos at DAMAC Lagoons at a Glance
Mykonos at DAMAC Lagoons by DAMAC groups 575 townhouses inside the DAMAC Lagoons masterplan off Hessa Street, registered with the Dubai Land Department as project 2487 on 21 October 2022. Building began on 12 February 2023, and the register read 81.06% on 30 September 2026, a little over three and a half years later. Because the cluster is made up entirely of 4 and 5 bedroom townhouses rising two or three floors, its record follows hundreds of low-rise homes moving through the same trades together, which is why the RERA report describes Mykonos by trade (envelope, MEP, finishes, external works) rather than by floor.
2487
Active
12 February 2023
575 townhouses
95,906.76 sq m
31 December 2025 (DLD)
Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.
Inspection Record
Mykonos at DAMAC Lagoons Construction Update Timeline
So far the Mykonos record on this site is short: one dated register reading, 81.06% on 30 September 2026, sitting just above a previous inspection of 79.74% that the register lists without a date. Both dots sit on the track below, the earlier one unlabelled because the two readings are too close to print side by side, and the dated reading is carried on the cluster's first monthly page, the September 2026 update, which is linked in the table.
| Inspection Month | Construction Progress | Inspection Date | Full Update |
|---|---|---|---|
| September 2026 | 81.06% | 30 September 2026 | View the September 2026 update |
Reading the dates: the DLD-registered completion date for project 2487 is 31 December 2025, while the inspection of 30 September 2026 recorded 81.06%. The registered date is an administrative anchor from project registration; DAMAC's estimated handover for the Mykonos townhouses is Q2 2027, and actual handover is confirmed by DAMAC as final inspections complete.
Pace Analysis
How Fast Mykonos at DAMAC Lagoons Has Been Built
With one dated reading on file, Mykonos has no measured pace between two inspections yet. What its register does support is arithmetic from the February 2023 start, shown below and labelled as arithmetic, not a forecast:
- Feb 2023 to Sep 2026: whole-build average, 0% at the 12 February 2023 start to 81.06% on 30 September 2026 over 1,326 days (arithmetic, not a forecast)About 1.83 points per month
- Sep 2026 to Jun 2027: the remaining 18.94 points from 81.06% to 100% by 30 June 2027, the end of the estimated Q2 2027 handover quarter, over 273 days (arithmetic, not a forecast)About 2.08 points per month
Neither number is a rate measured between two dated Mykonos inspections. The 1.83 figure blends everything since February 2023, from the enabling and foundation months through the townhouse frames, into one average; the 2.08 figure is simply the distance from the 30 September 2026 reading to 100%, divided by the days left in the quarter DAMAC has estimated for handover. The undated 79.74% previous reading cannot turn either into a measured pace. What the RERA report adds is the shape of the remainder: every structural trade sits in its substantially completed column, so the last 18.94 points belong to fit-out, MEP, envelope and external works spread across 575 homes at once. For an end user planning a move, and for an investor timing an exit, the next dated register reading is the one that will turn these two averages into a measured Mykonos pace.
Get the Next Inspection Figure First
Tell me you are tracking Mykonos at DAMAC Lagoons and I will send you the next recorded figure and site photos directly, ahead of the page update.
Get the Next Update on WhatsAppProject Profile
About Mykonos at DAMAC Lagoons
A register reading only means something next to what is being delivered. The project guide covers the 575 townhouses measured by the 30 September 2026 reading on this page:

Mykonos at DAMAC Lagoons, Greek Island-Themed Townhouses
Mykonos at DAMAC Lagoons is a DAMAC cluster of 575 four and five bedroom townhouses, one of the community's destination-themed clusters.
View the Mykonos at DAMAC Lagoons Project GuideConsidering a Late-Stage Entry?
Limited units are available at Mykonos, and what remains shifts as the cluster moves through its finishing works. If the record on this page is what brought you here, ask me for current availability across the 4 and 5 bedroom townhouses before the remaining choice narrows further.
Ask About Remaining Availability on WhatsAppStage Record
Mykonos at DAMAC Lagoons Build Stages, Mapped to the Inspections
Each stage below is pinned to the dates in the Mykonos record: registration on 21 October 2022, the construction start of 12 February 2023, and the RERA inspection of 30 September 2026, which sorts the cluster's work into completed and progressing trades.
Registration and Site Activation
Registered as project 2487 on 21 October 2022, Mykonos started construction 114 days later on 12 February 2023, opening mobilization across the cluster plot.
Enabling Works, Foundations and Sub-Structure
Enabling, foundation and sub-structure works for the 575 homes, all listed as substantially completed in the RERA report of 30 September 2026.
Townhouse Superstructure
Concrete frames and blockwork for homes the RERA report describes as G+1 and G+2, recorded as substantially completed at the 30 September 2026 inspection.
Envelope, MEP, Finishes and External Works
At the 30 September 2026 inspection the RERA report had MEP and internal works, the envelope and the internal finishes at advanced stages, with external works and cluster infrastructure moving alongside.
Completion, Snagging and Handover
The remaining 18.94 points from the 30 September 2026 reading, then the completion notice, buyer snagging inspections and keys, with handover estimated for Q2 2027.
What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Mykonos at DAMAC Lagoons's own record.
Buyer Position
Tracking Your Position at Mykonos at DAMAC Lagoons
This page is one of four project resources that together cover a Mykonos at DAMAC Lagoons purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Mykonos at DAMAC Lagoons Construction Updates
This page: the DLD register record for Mykonos at DAMAC Lagoons, from 2022 registration to handover.

Mykonos at DAMAC Lagoons Golden Visa: Two Townhouse Layouts Above
Mykonos at DAMAC Lagoons, 575 townhouses DAMAC is building, qualifies at both 4 and 5 bedroom layouts with no second property.
Read the Mykonos at DAMAC Lagoons Golden Visa Guide
Mykonos at DAMAC Lagoons: The 575-Unit Escrow on Record
Mykonos at DAMAC Lagoons, DLD project 2487, puts 575 units into Emirates NBD escrow, certified 81.06% September 2026.
Verify the Mykonos at DAMAC Lagoons Escrow Account
Mykonos at DAMAC Lagoons Snagging for a Greek Island Themed Cluster
Mykonos at DAMAC Lagoons is DAMAC Properties' cluster of 575 townhouses split between 4 and 5 bedroom homes.
Book Mykonos at DAMAC Lagoons SnaggingApproaching Handover
Between 81.06% and Handover: What Mykonos at DAMAC Lagoons Buyers Should Do Now
On the 30 September 2026 reading, 18.94 points separate Mykonos from 100%, and the RERA report places that remainder in fit-out, MEP, envelope and external works rather than in structure. The notice period before your handover appointment is set by your SPA and can be short, so the three steps below belong in the months before the estimated Q2 2027 handover, not after the notice arrives.
First, arrange independent snagging so defects across the two or three floors of your townhouse are recorded before you accept it; the Mykonos snagging inspection page covers timing and what gets checked.
Second, match your remaining instalments, including the 20% due on completion under the 80/20 launch plan, against the Emirates NBD escrow account on the Mykonos escrow account page, so the final payments follow DLD-verified progress rather than requests.
Third, if residency is part of your plan, settle eligibility through the Mykonos Golden Visa page before handover, since the move from Oqood registration to title deed changes the document an application rests on.
Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.
The Wider Picture
Explore DAMAC Lagoons Structure
A register record for one cluster is only half the picture; the other half is what is taking shape around it. These three pages put the Mykonos build in its market, masterplan and developer context:

DAMAC Lagoons: Mediterranean-Themed Villas, Townhouses, Apartments and Offices
DAMAC Lagoons sits opposite DAMAC Hills in Dubailand, with 11 themed clusters and 3 projects of villas, townhouses, apartments and offices.
See DAMAC Lagoons Properties for Sale
DAMAC Lagoons Community Overview
Read the DAMAC Lagoons guide: Mediterranean-themed clusters and crystal lagoons across a 45 million sq ft waterfront masterplan.
Explore the DAMAC Lagoons Community
DAMAC Properties: Lagoon Communities, Golf Villas and Branded Collaborations
Founded in 2002, DAMAC has delivered 48,000 homes and is known for large-scale master communities, luxury residential projects and branded collaborations.
View the DAMAC Developer ProfileConstruction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.
FAQs
Mykonos at DAMAC Lagoons Construction Updates Frequently Asked Questions
Mykonos at DAMAC Lagoons is an active project on the Dubai Land Department register under number 2487, recorded at 81.06% construction progress at the inspection of 30 September 2026. The RERA report of that date records every structural trade, from enabling works up to the superstructure, as substantially completed, with the main contract still progressing. The full record is in the inspection timeline above.
This page follows the Dubai Land Department register entry for project 2487, read together with the RERA progress monitoring report, which prints no percentage of its own. The latest register reading is 81.06% on 30 September 2026, 1.32 points above the previous inspection of 79.74%, a reading the register shows without a date. That reading is set out in the Mykonos September 2026 construction update.
The register lists 31 December 2025 as the registered completion date for project 2487, while the inspection of 30 September 2026 recorded 81.06%, so that date has passed with the townhouses still in their finishing works. The registered date is an administrative anchor fixed when the project was registered on 21 October 2022; DAMAC's estimated handover is Q2 2027, actual handover is confirmed by DAMAC as final inspections complete, and this page's record is updated when the closing inspection is recorded.
The DLD register lists 575 units for Mykonos at DAMAC Lagoons, and the RERA report of 30 September 2026 describes them as G+1 and G+2 homes with a concrete structure and blockwork, finished inside and out. They are sold as 4 bedroom and 5 bedroom townhouses, laid out over two and three floors respectively according to DAMAC's floor plans, so every reading on this page covers all 575 homes at once.
Construction at Mykonos at DAMAC Lagoons started on 12 February 2023, 114 days after the project was registered with the Dubai Land Department on 21 October 2022. By the inspection of 30 September 2026, 1,326 days after that start, the register read 81.06%.
Spread over the 1,326 days from the 12 February 2023 start to the 30 September 2026 reading of 81.06%, the register has moved about 1.83 points per month. Covering the remaining 18.94 points by 30 June 2027, the last day of the estimated Q2 2027 handover quarter, works out at about 2.08 points per month. Both figures are arithmetic, not a forecast, because only one dated reading is on file; the working is in the pace analysis above.

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is keeping the Mykonos at DAMAC Lagoons construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.
Ask your question, get your answer. No obligation and no follow-up unless you ask for it.